A special inspector shall demonstrate competence to the satisfaction of the
_____________ - ANSWER-Building Official
The special inspector observes critical building or structural elements identified in
the statements of special inspections for compliance with __________ and
__________ approved by the building official. - ANSWER-plans, specifications
All nonconforming items shall be brought to the immediate attention of the -
ANSWER-Contractor
What are approved plans? - ANSWER-Plans that have been approved by
governing jurisdiction.
Who can employ an approved inspection agency? - ANSWER-Owner or Owner's
agent
Special inspections are in addition to the ______________ performed by the city
inspector and the _____________ performed by the structural engineer of record. -
ANSWER-Jurisdictional/Municipal Inspections, Structural observation
Special inspections review the _____________ while jurisdictional inspection
reviews the ____________ - ANSWER-Fine details, Broad details
,When nonconforming items are not corrected the special inspector shall notify the
_________ and _________ - ANSWER-Register Design Professional, Building
Official
The permit applicant shall submit a statement of special inspections prepared by
the____________ - ANSWER-Registered design professional
Who shall the special inspector furnish inspection reports (progress reports) to? -
ANSWER-Building official, Registered design professional, and other designated
people
Who performs a structural observation? - ANSWER-Registered Design
professional.
_____________ is a full time observation of work requiring special inspection -
ANSWER-continuous special inspection
Is special inspection required for concrete placement of 3000 psi concrete in
isolated spread footings for a single story warehouse? - ANSWER-No. (isolated
spread footings) IBC 1705.3
Explain what periodic special inspection is - ANSWER-Special inspection by the
special inspector who is intermittently present where the work to be inspected has
been or is being performed.
Is special inspection required for concrete placement of continuous footings, for
poured in place walls, if the building is two stories in height and engineer included
all footings in his statement of special inspection. - ANSWER-Yes (IBC 1705.3)
, If it takes 6 1/2 hours to pour 4 shear walls and 26 columns on the third level of a
ten story building, how much time is the special inspector required to be on site? -
ANSWER-As long as it takes. (IBC Table 1705.3)
What other tests are required every time strength tests are cast? - ANSWER-
Temperature, air content, and slump (IBC Table 1705.3 #6)
Where does it specify the type and extent of special inspections required? -
ANSWER-Statement of special instruction (IBC 1704.3.1)
Structural observation is required for all buildings over ______ in height for
buildings located in Seismic Design Category D. - ANSWER-75ft (IBC 1704.2
exception 1)
Who can waive the requirement of special inspection on work of a minor nature? -
ANSWER-Building official
The inspection of curing temperatures and techniques for concrete should be -
ANSWER-Verified w/ periodic special inspection (IBC Table 1705.3)
The type and extent of each special inspection shall be located in
a.) Chapter 17 of building code
b.) the statement of special inspection
c.) the job specifications
d.) the approved plans - ANSWER-b.) The statement of special inspection
QUESTIONS & CORRECT ANSWERS LATEST
2026/2027
A special inspector shall demonstrate competence to the satisfaction of the
_____________ - ANSWER-Building Official
The special inspector observes critical building or structural elements identified in
the statements of special inspections for compliance with __________ and
__________ approved by the building official. - ANSWER-plans, specifications
All nonconforming items shall be brought to the immediate attention of the -
ANSWER-Contractor
What are approved plans? - ANSWER-Plans that have been approved by
governing jurisdiction.
Who can employ an approved inspection agency? - ANSWER-Owner or Owner's
agent
Special inspections are in addition to the ______________ performed by the city
inspector and the _____________ performed by the structural engineer of record. -
ANSWER-Jurisdictional/Municipal Inspections, Structural observation
Special inspections review the _____________ while jurisdictional inspection
reviews the ____________ - ANSWER-Fine details, Broad details
,When nonconforming items are not corrected the special inspector shall notify the
_________ and _________ - ANSWER-Register Design Professional, Building
Official
The permit applicant shall submit a statement of special inspections prepared by
the____________ - ANSWER-Registered design professional
Who shall the special inspector furnish inspection reports (progress reports) to? -
ANSWER-Building official, Registered design professional, and other designated
people
Who performs a structural observation? - ANSWER-Registered Design
professional.
_____________ is a full time observation of work requiring special inspection -
ANSWER-continuous special inspection
Is special inspection required for concrete placement of 3000 psi concrete in
isolated spread footings for a single story warehouse? - ANSWER-No. (isolated
spread footings) IBC 1705.3
Explain what periodic special inspection is - ANSWER-Special inspection by the
special inspector who is intermittently present where the work to be inspected has
been or is being performed.
Is special inspection required for concrete placement of continuous footings, for
poured in place walls, if the building is two stories in height and engineer included
all footings in his statement of special inspection. - ANSWER-Yes (IBC 1705.3)
, If it takes 6 1/2 hours to pour 4 shear walls and 26 columns on the third level of a
ten story building, how much time is the special inspector required to be on site? -
ANSWER-As long as it takes. (IBC Table 1705.3)
What other tests are required every time strength tests are cast? - ANSWER-
Temperature, air content, and slump (IBC Table 1705.3 #6)
Where does it specify the type and extent of special inspections required? -
ANSWER-Statement of special instruction (IBC 1704.3.1)
Structural observation is required for all buildings over ______ in height for
buildings located in Seismic Design Category D. - ANSWER-75ft (IBC 1704.2
exception 1)
Who can waive the requirement of special inspection on work of a minor nature? -
ANSWER-Building official
The inspection of curing temperatures and techniques for concrete should be -
ANSWER-Verified w/ periodic special inspection (IBC Table 1705.3)
The type and extent of each special inspection shall be located in
a.) Chapter 17 of building code
b.) the statement of special inspection
c.) the job specifications
d.) the approved plans - ANSWER-b.) The statement of special inspection