ENGV 380 Quiz 3 – Construction Industry,
Management Functions & Estimates | Questions &
Answers | Liberty University 2026
1. Which project participant typically owns or finances the construction project?
A. General contractor
B. Owner
C. Subcontractor
D. Material supplier
Correct Answer: B. Owner
Rationale: The owner initiates or commissions the project, provides or arranges
financing, and ultimately receives the completed facility.
2. In a traditional design-bid-build project, who is primarily responsible for
preparing the design documents?
A. General contractor
B. Material supplier
C. Architect or engineer
D. Equipment operator
Correct Answer: C. Architect or engineer
Rationale: The design professional develops drawings, specifications, and other
technical documents used to define the project.
3. What is the primary responsibility of a general contractor?
A. Financing the owner's project
B. Executing and coordinating construction work
,C. Approving building codes
D. Designing all government regulations
Correct Answer: B. Executing and coordinating construction work
Rationale: The general contractor manages construction operations and
coordinates subcontractors, labor, materials, and equipment.
4. A subcontractor is generally hired to:
A. Perform specialized construction work
B. Finance the entire project
C. Replace the project owner
D. Approve architectural drawings
Correct Answer: A. Perform specialized construction work
Rationale: Subcontractors typically perform specialized portions of the
construction scope, such as electrical, plumbing, mechanical, or concrete work.
5. Which participant commonly supplies construction materials?
A. Surety
B. Material supplier
C. Owner's representative
D. Building inspector
Correct Answer: B. Material supplier
Rationale: Material suppliers provide products required for construction, such as
concrete, steel, lumber, piping, and finishes.
6. What is the primary purpose of a construction contract?
A. To establish the rights and obligations of the parties
B. To eliminate all construction risks
,C. To replace project drawings
D. To determine employee salaries
Correct Answer: A. To establish the rights and obligations of the parties
Rationale: The contract establishes responsibilities, compensation, scope,
performance requirements, and other legal obligations.
7. Which professional is most directly associated with monitoring structural
design requirements?
A. Structural engineer
B. Payroll clerk
C. Equipment operator
D. Purchasing agent
Correct Answer: A. Structural engineer
Rationale: Structural engineers design and analyze structural systems to meet
applicable requirements.
8. Which participant normally provides bonding services to support contractual
obligations?
A. Surety
B. Architect
C. Laborer
D. Supplier
Correct Answer: A. Surety
Rationale: A surety provides bonds that guarantee specified obligations, subject
to the terms of the bond.
SECTION 2: CONSTRUCTION MANAGEMENT FUNCTIONS
, 9. Which management function establishes what must be accomplished and
how resources will be used?
A. Planning
B. Inspection
C. Closeout
D. Demolition
Correct Answer: A. Planning
Rationale: Planning identifies activities, resources, constraints, sequence, and
methods needed to accomplish project objectives.
10. Organizing primarily involves:
A. Determining organizational responsibilities and relationships
B. Calculating concrete volume only
C. Testing soil samples only
D. Purchasing fuel only
Correct Answer: A. Determining organizational responsibilities and relationships
Rationale: Organizing establishes authority, responsibility, communication, and
resource relationships.
11. Which function involves comparing actual performance with planned
performance?
A. Controlling
B. Estimating
C. Demolition
D. Procurement only
Correct Answer: A. Controlling
Rationale: Controlling involves monitoring performance, identifying variances,
and taking corrective action.
Management Functions & Estimates | Questions &
Answers | Liberty University 2026
1. Which project participant typically owns or finances the construction project?
A. General contractor
B. Owner
C. Subcontractor
D. Material supplier
Correct Answer: B. Owner
Rationale: The owner initiates or commissions the project, provides or arranges
financing, and ultimately receives the completed facility.
2. In a traditional design-bid-build project, who is primarily responsible for
preparing the design documents?
A. General contractor
B. Material supplier
C. Architect or engineer
D. Equipment operator
Correct Answer: C. Architect or engineer
Rationale: The design professional develops drawings, specifications, and other
technical documents used to define the project.
3. What is the primary responsibility of a general contractor?
A. Financing the owner's project
B. Executing and coordinating construction work
,C. Approving building codes
D. Designing all government regulations
Correct Answer: B. Executing and coordinating construction work
Rationale: The general contractor manages construction operations and
coordinates subcontractors, labor, materials, and equipment.
4. A subcontractor is generally hired to:
A. Perform specialized construction work
B. Finance the entire project
C. Replace the project owner
D. Approve architectural drawings
Correct Answer: A. Perform specialized construction work
Rationale: Subcontractors typically perform specialized portions of the
construction scope, such as electrical, plumbing, mechanical, or concrete work.
5. Which participant commonly supplies construction materials?
A. Surety
B. Material supplier
C. Owner's representative
D. Building inspector
Correct Answer: B. Material supplier
Rationale: Material suppliers provide products required for construction, such as
concrete, steel, lumber, piping, and finishes.
6. What is the primary purpose of a construction contract?
A. To establish the rights and obligations of the parties
B. To eliminate all construction risks
,C. To replace project drawings
D. To determine employee salaries
Correct Answer: A. To establish the rights and obligations of the parties
Rationale: The contract establishes responsibilities, compensation, scope,
performance requirements, and other legal obligations.
7. Which professional is most directly associated with monitoring structural
design requirements?
A. Structural engineer
B. Payroll clerk
C. Equipment operator
D. Purchasing agent
Correct Answer: A. Structural engineer
Rationale: Structural engineers design and analyze structural systems to meet
applicable requirements.
8. Which participant normally provides bonding services to support contractual
obligations?
A. Surety
B. Architect
C. Laborer
D. Supplier
Correct Answer: A. Surety
Rationale: A surety provides bonds that guarantee specified obligations, subject
to the terms of the bond.
SECTION 2: CONSTRUCTION MANAGEMENT FUNCTIONS
, 9. Which management function establishes what must be accomplished and
how resources will be used?
A. Planning
B. Inspection
C. Closeout
D. Demolition
Correct Answer: A. Planning
Rationale: Planning identifies activities, resources, constraints, sequence, and
methods needed to accomplish project objectives.
10. Organizing primarily involves:
A. Determining organizational responsibilities and relationships
B. Calculating concrete volume only
C. Testing soil samples only
D. Purchasing fuel only
Correct Answer: A. Determining organizational responsibilities and relationships
Rationale: Organizing establishes authority, responsibility, communication, and
resource relationships.
11. Which function involves comparing actual performance with planned
performance?
A. Controlling
B. Estimating
C. Demolition
D. Procurement only
Correct Answer: A. Controlling
Rationale: Controlling involves monitoring performance, identifying variances,
and taking corrective action.