NEBOSH EVALUATION EXAMS ANSWERS AND
QUESTIONS SET A+
✔✔Outline FOUR types of work activity associated with an oil platform that might
require permit to-work AND give a reason in EACH case for the requirement. - ✔✔Hot
Work

Hot Work Permits are generally applied to any type of work, which involves actual or
potential sources of ignition, and work for which there may be a risk of a fire and/or
explosion, or which involves the emission of toxic fumes from the application of heat.

Cold work

Cold work shall include but not be limited to the following: scaffolding, cleaning, over
side working, painting

Confined space entry

A confined space is any vessel, enclosure or compartment large enough to take a
person where the atmosphere may be dangerous or incompatible to a person entering
because of flammable/toxic gases and other substances or oxygen deficiency.

Isolation

An Isolation Certificate is required before any work can be started on process,
mechanical or electrical plant or equipment. An Isolation Certificate is also required
where access to the site of work is restricted or its safety is jeopardized by any adjacent
plant or equipment. An activity cannot commence until all the necessary isolation
requirements are in place

Diving

Diving certificate can be used to control the diving activity itself and to ensure that there
are no other activities taking place nearby which create unnecessary additional risks
e.g. over-side work, live firewater intake pumps.

,✔✔Identify TWO ways in which vapour clouds can be generated - ✔✔Sudden
depressurization

Rupture of vessel

Loss of containment

Uncontrolled buildup of pressure

✔✔Outline how a vapour cloud explosion can be generated - ✔✔Vapour cloud
explosion can be generated by;

Confined / unconfined generation

Vapour cloud explosions may arise from vaporization of a release of liquefied gas from
a ruptured vessel or pipeline

✔✔Identify the physical consequences of vapour cloud explosions - ✔✔Physical
consequences of vapour cloud explosions;

Overpressure

Fire & explosion

Resulting debris as airborne missiles

✔✔A pump containing flammable corrosive slurry has been stopped for maintenance.

An operator will prepare the pump for maintenance using a nitrogen supply, drain
header and collection vessel. Using this information;

Outline EIGHT risks to the operator when preparing the pump for maintenance. -
✔✔Asphyxiation due to displacement of 02

Fire

Explosion

Irritant/Corrosive substance

Incorrect isolation of valves

Incorrect Lock Out/Tag Out system

Lack of gas monitoring

, Burst pressure lines causing injury

✔✔Oil and gas installations use water for cooling and heating although it can be a
hazard in some situations.

Identify risks with water AND give a practical example in EACH case - ✔✔When stored
under pressure as in Fire lines and steam water lines

May contain bacteria if not circulated e.g. dead end pipe legs

May cause an unstable reaction when mixed with some hydrocarbons

✔✔Outline operational control measures that could minimize the risk of plant damage or
injury during start-up or shutdown of a process - ✔✔Shutdown:

Ensure work carried out under the controls of a PTW

All services are;

Stopped
Isolated
Drained down
Blanked

Empty & drain hydrocarbon facilities, with all liquids, gases and residues removed
leaving the plant safe to work on

Eliminate or control ignition sources

Suitable supervision of the operation

Certification of items that have been maintained or replaced

Start-up:

Establish all isolations reconnected, all blanks removed

Ensure all safety systems are operational

Ensure all systems are tested before start-up

Complete PTW

Emergency plan - in place

Document information

Uploaded on
September 14, 2026
Number of pages
23
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$18.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
2
Followers
3
Items
6140
Last sold
19 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions