SECTION ONE — QUESTIONS 1–100
1. What is the primary purpose of a project charter?
A) To document detailed task assignments for team members
B) To formally authorize the project and establish its high-level objectives
C) To create the project schedule and budget baseline
D) To identify and analyze potential project risks
Correct Answer: B) To formally authorize the project and establish its high-level objectives
Rationale: The project charter is the foundational document that formally authorizes a project and
gives the project manager authority to proceed. It establishes the project's purpose, high-level
objectives, and identifies key stakeholders. Detailed task assignments, schedules, and risk analysis
occur later in the planning phase, not during project initiation.
2. During which project life cycle phase does the project team complete the activities to create
project deliverables?
A) Defining
B) Planning
C) Executing
D) Closing
Correct Answer: C) Executing
Rationale: The executing phase is where the project team performs the work defined in the project
management plan to produce deliverables and outcomes. The defining phase establishes the project,
planning creates the roadmap, and closing finalizes the project. Understanding this distinction is
essential for exam questions about where work actually occurs.
3. A project manager discovers that a vendor cannot deliver critical materials on time, threatening
the project schedule. Which action should the project manager take first?
A) Immediately notify all stakeholders of the delay
B) Assess the impact on the overall project schedule and identify alternatives
C) Cancel the vendor contract and find a new supplier
D) Adjust the project baseline to reflect the new timeline
Correct Answer: B) Assess the impact on the overall project schedule and identify alternatives
Rationale: Before taking action, the project manager must first understand the full scope of the
problem and evaluate options. Assessing impact allows informed decision-making about corrective
actions. Notifying stakeholders, changing vendors, or adjusting baselines without analysis could lead
to premature or incorrect responses that may worsen the situation.
,4. In which organizational structure do the project manager and functional manager share
authority?
A) Functional
B) Projectized
C) Matrix
D) Hierarchical
Correct Answer: C) Matrix
Rationale: In a matrix organization, authority is shared between the project manager and functional
managers. Functional organizations concentrate authority with functional managers, while
projectized organizations give full authority to project managers. The matrix structure balances
competing priorities but can create resource conflicts and dual reporting relationships.
5. What document establishes the expected scope, schedule, and cost for a project?
A) Project proposal
B) Project baseline
C) Requirements documentation
D) Work breakdown structure
Correct Answer: B) Project baseline
Rationale: A project baseline is the approved version of the project's scope, schedule, and cost that
serves as a reference point for measuring performance. It is established after planning is complete
and approved. Deviations from the baseline indicate project performance issues and trigger change
control processes when modifications are needed.
6. A project manager is analyzing the triple constraints for a construction project. An unexpected
underground storage tank is discovered, requiring the planned building addition to be cancelled.
Which constraint does this directly affect?
A) Schedule
B) Cost
C) Scope
D) Quality
Correct Answer: C) Scope
Rationale: Scope defines what the project will deliver. Cancelling a planned building addition changes
the deliverables and therefore directly impacts project scope. Schedule would be affected if timelines
change, and cost if budget changes, but the fundamental change here is what the project will
produce. This illustrates how triple constraints interconnect.
7. Which document is created during the defining phase and includes major project outcomes,
deliverables, and high-level estimates?
A) Project management plan
B) Project proposal
C) Work breakdown structure
D) Risk register
Correct Answer: B) Project proposal
Rationale: The project proposal is developed during the defining (initiating) phase and outlines what
the project will accomplish, its major deliverables, and preliminary estimates. The project
, management plan is created during planning, the WBS during planning, and the risk register during
risk management planning. The proposal sets the stage for formal project authorization.
8. What is the primary purpose of a work breakdown structure (WBS)?
A) To track project expenses against the budget
B) To hierarchically decompose project deliverables into manageable components
C) To document stakeholder communication preferences
D) To establish the project's critical path
Correct Answer: B) To hierarchically decompose project deliverables into manageable components
Rationale: The WBS breaks down the total project scope into smaller, more manageable work
packages that can be estimated, scheduled, and assigned. It provides a visual representation of all
work required to complete the project. Cost tracking, communication planning, and schedule
development are separate processes that use the WBS as input.
9. A project manager notices team members are confused about their specific responsibilities for
project tasks. Which tool would best clarify these assignments?
A) Gantt chart
B) Responsibility assignment matrix
C) Risk register
D) Stakeholder register
Correct Answer: B) Responsibility assignment matrix
Rationale: A responsibility assignment matrix, such as a RACI chart, clarifies who is responsible,
accountable, consulted, and informed for each project task. Gantt charts show timing but not
ownership, while risk and stakeholder registers address different concerns. Clear responsibility
documentation prevents confusion and ensures accountability throughout the project.
10. What is gathered and documented by the project manager during the project closing phase?
A) Revised activity durations
B) Project outcomes and lessons learned
C) New risk response strategies
D) Updated stakeholder requirements
Correct Answer: B) Project outcomes and lessons learned
Rationale: During closing, the project manager documents lessons learned to benefit future projects
and confirms that project outcomes meet requirements. Activity durations and risk responses are
addressed during planning and executing, while stakeholder requirements are gathered earlier. The
closing phase captures knowledge that can improve organizational project management maturity.
11. Which process group occurs throughout the entire project life cycle?
A) Initiating
B) Planning
C) Executing
D) Monitoring and Controlling
Correct Answer: D) Monitoring and Controlling
Rationale: Monitoring and Controlling processes run concurrently with all other process groups,
continuously tracking, reviewing, and regulating project progress. Initiating occurs primarily at the