• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 94 pages
Exam (elaborations)

New Mexico GF-9 Utility Lines Exam – 300-Question Practice & Study Guide with Explanations 2026

Document preview thumbnail
Preview 4 out of 94 pages

New Mexico GF-9 Utility Lines Exam – 300-Question Practice & Study Guide with Explanations 2026

Content preview

New Mexico GF-9 Utility Lines
Exam – 300-Question Practice &
Study Guide with Explanations
2026




Multiple Choice Questions

1. A licensed GF-9 Utility Lines contractor is hired to install a new water main. The
project also requires repaving a driveway that was damaged during construction.
Under NMAC 14.6.6, is this paving work permitted under the GF-9 license?

A) Yes, because the GF-9 license includes all types of paving
B) Yes, because paving is necessary and incidental to the utility installation
C) No, the GF-9 contractor must hire a separate, licensed paving contractor for any
paving work
D) No, unless the GF-9 contractor also holds a General Building (GB-98) license

Answer: B) Yes, because paving is necessary and incidental to the utility
installation

,Rationale: The GF-9 license specifically includes "paving and surfacing necessary and
incidental to the completion of the installation of such facilities." While it does not
authorize standalone paving projects, it does allow a GF-9 contractor to restore paving
that was cut or removed to complete the utility work .




2. What is the minimum verified work experience required for a Qualifying Party
(QP) to obtain a GF-9 license in New Mexico?

A) 1 year (2,000 hours)
B) 2 years (4,000 hours)
C) 3 years (6,000 hours)
D) 4 years (8,000 hours)

Answer: B) 2 years (4,000 hours)

Rationale: New Mexico regulations require two years (4,000 hours) of verified work
experience specifically for the GF-9 Utility Lines and Systems classification. This experience
must be documented and notarized as part of the Qualifying Party application process .




3. Which agency regulates safe excavation near underground facilities in New
Mexico?

A) OSHA only
B) Department of Transportation
C) New Mexico Public Regulation Commission (NMPRC)
D) Department of Energy

Answer: C) New Mexico Public Regulation Commission (NMPRC)

,Rationale: The New Mexico Public Regulation Commission (NMPRC) enforces regulations
under the Damage Prevention Law. This includes oversight of the One Call system and
enforcement of excavation safety requirements .




4. According to the New Mexico Excavation Law, how many working days before
excavation must you notify the New Mexico One Call system (811)?

A) One working day
B) Two working days
C) Three working days
D) Five working days

Answer: B) Two working days

Rationale: The New Mexico Excavation Law requires excavators to notify the One-Call
center at least two working days prior to starting excavation. This timeline excludes
weekends and legal holidays, giving utility operators sufficient time to mark their lines.
Commencing work before this window expires shifts all liability for damages to the
excavator .




5. If a utility operator marks the location of an underground gas line, what is the
width of the "tolerance zone" on either side of that mark where excavation
restrictions apply?

A) 12 inches
B) 18 inches
C) 24 inches
D) 36 inches

, Answer: B) 18 inches

Rationale: The tolerance zone is defined as the width of the underground facility plus 18
inches on either side of the outside edge of the facility as indicated by the locate marks.
Within this zone, mechanical excavation is prohibited and hand digging or vacuum
excavation is required .




6. What restrictions apply within the tolerance zone when excavating?

A) Mechanical excavation is permitted with a spotter
B) Only hand digging or vacuum excavation is permitted to expose the facility
C) No excavation of any kind is permitted
D) Mechanical excavation is permitted at reduced speed

Answer: B) Only hand digging or vacuum excavation is permitted to expose the
facility

Rationale: Within the 18-inch tolerance zone, the use of mechanical earthmoving
equipment is strictly prohibited. The law requires excavators to expose the facility using
non-destructive means such as hand digging or vacuum excavation .




7. What is the scope of work authorized by the GF-9 Utility Lines license?

A) Only water line installation
B) Only gas line installation
C) Construction, installation, alteration, and repair of utility lines for sewage, natural gas,
and water
D) General building construction

Document information

Uploaded on
September 6, 2026
Number of pages
94
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$60.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
andrewmwas167
3.0
(2)
Sold
3
Followers
0
Items
915
Last sold
2 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions