1.
A gas-line contractor is installing a new natural-gas piping system
serving several appliances in a commercial building. Before selecting
pipe sizes, the contractor determines the gas demand of each appliance
and calculates the total demand carried by each section of the piping
system. Why is this procedure essential?
A. It ensures that every pipe segment operates at exactly the same
pressure
B. It ensures that pipe diameters are adequate to deliver the required gas
volume without excessive pressure loss
C. It eliminates the requirement for pressure testing
D. It allows the contractor to use any piping material regardless of its
listing
Answer: B.
Rationale: Proper sizing must account for the connected appliance
demand and allowable pressure drop. An undersized system can cause
inadequate appliance inlet pressure, poor combustion, nuisance
shutdowns, and unsafe operating conditions. Pipe sizing is therefore
based on the required gas flow and permitted pressure loss rather than
simply making every section the same size.
1
,2.
A contractor is installing a gas piping system in which the available gas
pressure at the point of delivery is known. The contractor wants to
determine the appropriate pipe size using a sizing table. Which
information is most important in addition to the available inlet pressure?
A. Paint color of the pipe
B. Total developed length and gas demand
C. Number of workers on the project
D. Manufacturer's warranty period
Answer: B.
Rationale: Gas-sizing procedures generally require the designer or
installer to consider the system's gas demand, available pressure,
allowable pressure drop, pipe material, and developed length or sizing
method specified by the applicable code. Longer runs generally create
greater frictional pressure loss.
3.
A natural-gas piping system supplies a furnace rated at 100,000 Btu/h
and a water heater rated at 40,000 Btu/h. A branch serving only the
water heater is being sized. What appliance load should normally be
used for that branch?
A. 40,000 Btu/h
B. 60,000 Btu/h
C. 100,000 Btu/h
D. 140,000 Btu/h
Answer: A.
Rationale: A branch that serves only the water heater is sized
according to the demand of the appliances actually supplied by that
2
,branch. The furnace's 100,000 Btu/h demand belongs to the upstream
section carrying both appliances, not to the isolated water-heater
branch.
4.
During installation, a worker discovers that a section of metallic gas
piping will pass through a concrete masonry wall. What is the primary
concern when the pipe penetrates the wall?
A. Increasing gas pressure
B. Preventing physical damage and harmful contact with the masonry
C. Increasing the pipe's gas capacity
D. Eliminating the need for supports
Answer: B.
Rationale: Piping passing through walls or other structural elements
must be protected against mechanical damage, corrosion, and
damaging contact where required. The installation must preserve the
integrity of the piping while accommodating movement and preventing
abrasion.
5.
A contractor is installing a gas appliance and places the appliance
shutoff valve in a location that cannot be reached without removing a
permanent wall panel. Which statement is most accurate?
A. The arrangement is acceptable because the valve exists
B. The valve should be accessible for appliance servicing and
emergency shutoff
C. The valve is unnecessary if the appliance has an ignition control
D. The valve may be concealed if it is painted yellow
3
, Answer: B.
Rationale: An appliance shutoff is intended to permit the gas supply to
an individual appliance to be isolated for servicing or emergencies. A
valve that cannot reasonably be accessed defeats this safety function
and generally does not satisfy accessibility requirements.
6.
A gas piping installation has been completed, but the contractor has not
yet connected the appliances. Before the system is placed into service,
the piping must undergo the required testing procedure. What is the
primary purpose of this test?
A. To determine whether the appliances have adequate combustion air
B. To demonstrate that the piping system is free from prohibited leakage
C. To determine the BTU rating of the appliances
D. To verify the building's electrical grounding system
Answer: B.
Rationale: Pressure testing is used to verify the integrity of the gas
piping system. The system must demonstrate that it can withstand the
specified test conditions without unacceptable loss or leakage before
being placed into service.
7.
A contractor performs a gas-piping pressure test and observes that the
pressure gauge decreases significantly during the test period. Which
action is most appropriate?
A. Immediately connect the appliances
B. Increase the test pressure until the gauge stops moving