1. BPMN
Answer:
Business Processing Modeling Notation
Question:
2. Process decomposition is used to:
Answer:
1. Improve understanding by breaking down large models
2. Improve diagram readability
3. Improve usability of sub-processes
Question:
3. Sub-process:
Answer:
A self contained, composite activity that can be broken down into smaller units of work
Question:
4. Task:
Answer:
An activity capturing a unit of work that cannot be further broken down
Question:
5. Representing a sub-process at the Child Level: Message flows can cross sup process boundaries
Answer:
Indicate messages emanating from/incoming into the sub-process
Question:
6. Representing a sub-process at the Child Level: Start with at least one start event
Answer:
If multiple, first occurring will trigger the sub-process
Question:
7. Representing a sub-process at the Child Level: Finish with at least one end event
Answer:
The sub-process will complete once all tokens have reached an event. May need an (X)OR-split after
sub-process to understand what events(s) have been reached
Question:
8. In order to maximize reuse, it is possible to....
Answer:
"extract" the sub-process and store it as a separate file in the process model respiratory
, Question:
9. What is a sub-process called?
Answer:
Global model and is invoked via a "call" activity
Question:
10. What are the three types of repetition...
Answer:
1. Loop
2. Parallel
3. Unstructured
Question:
11. SESE
Answer:
Single Entry Single Exit Fragment A fragment delimited by a single entry node and a single exit node
Question:
12. Notation for Loop Activities: What is a loop used for?
Answer:
To capture sequential repetition, meaning that instances of the loop activity
Question:
13. BPMN provides the..... to allow the repetition of a task or sub-process
Answer:
Loop activity notation
Question:
14. What is a loop activity?
Answer:
A shorthand notation for a block-structured repetition which is delimited by a single entry point to the
cycle, and a single exit point from the cycle
Question:
15. Parallel Repetition
Answer:
Used for multi-instance activity which is executed multiple times concurrently Ex.
- Request quotes from multiple suppliers
-Check the availability for each line in an order separately
- Send and gather questionnaires from multiple witness in the context of an insurance claim
Question:
16. Uncontrolled Repetition
Answer:
- Represents an ad-hoc sub-process
- Contains activities to be executed in arbitrary order and number of times
- May define order os sub-set of activities by sequence flow
AND CORRECT ANSWERS
Question:
1. BPMN
Answer:
Business Processing Modeling Notation
Question:
2. Process decomposition is used to:
Answer:
1. Improve understanding by breaking down large models
2. Improve diagram readability
3. Improve usability of sub-processes
Question:
3. Sub-process:
Answer:
A self contained, composite activity that can be broken down into smaller units of work
Question:
4. Task:
Answer:
An activity capturing a unit of work that cannot be further broken down
Question:
5. Representing a sub-process at the Child Level: Message flows can cross sup process boundaries
Answer:
Indicate messages emanating from/incoming into the sub-process
Question:
6. Representing a sub-process at the Child Level: Start with at least one start event
Answer:
If multiple, first occurring will trigger the sub-process
Question:
7. Representing a sub-process at the Child Level: Finish with at least one end event
Answer:
The sub-process will complete once all tokens have reached an event. May need an (X)OR-split after
sub-process to understand what events(s) have been reached
Question:
8. In order to maximize reuse, it is possible to....
Answer:
"extract" the sub-process and store it as a separate file in the process model respiratory
, Question:
9. What is a sub-process called?
Answer:
Global model and is invoked via a "call" activity
Question:
10. What are the three types of repetition...
Answer:
1. Loop
2. Parallel
3. Unstructured
Question:
11. SESE
Answer:
Single Entry Single Exit Fragment A fragment delimited by a single entry node and a single exit node
Question:
12. Notation for Loop Activities: What is a loop used for?
Answer:
To capture sequential repetition, meaning that instances of the loop activity
Question:
13. BPMN provides the..... to allow the repetition of a task or sub-process
Answer:
Loop activity notation
Question:
14. What is a loop activity?
Answer:
A shorthand notation for a block-structured repetition which is delimited by a single entry point to the
cycle, and a single exit point from the cycle
Question:
15. Parallel Repetition
Answer:
Used for multi-instance activity which is executed multiple times concurrently Ex.
- Request quotes from multiple suppliers
-Check the availability for each line in an order separately
- Send and gather questionnaires from multiple witness in the context of an insurance claim
Question:
16. Uncontrolled Repetition
Answer:
- Represents an ad-hoc sub-process
- Contains activities to be executed in arbitrary order and number of times
- May define order os sub-set of activities by sequence flow