The right to repossess or replevy unused materials from a jobsite will not be
effective if someone, in good faith, purchased it after removal from the site of
the improvement.
True.
The contractor must within _____ days after the receipt of the property owner's
request, furnish to property owner or the property owner's agent a list of the
subcontractors and suppliers who have a contract with the contractor as of the
date the request is received by the contractor.
10 days.
A property perfected lien may be discharged by an order of the circuit court of
the _____ where the property is located.
county
When any interested party files a complaint, the clerk will issue a summons to
the lienor to show cause within _____ days why his or her lien should not to be
enforced by action or vacated and canceled of record.
20 days
,If a lienor fails to show cause why his or her lien should not be enforced or fails
to start such action before the return date of the summons, the court will
immediately order cancellation of the lien.
True
No lien provided by part 713.22 will continue for longer then ____ years after
the claim of lien has been recorded.
1 year
No lien provided by part 713.22 will continue for no longer then _______ years
after the recording of an amended claim of lien that shows a later date of final
furnishing of labor, services, or materials.
1 year
The lien of any lienor upon whom Notice of contest of Lien is served and who
fails to institute a suit to enforce his or her lien within ________ days after
service of such notice will be extinguished automatically.
60
, The payment bond is required to ______ an owner under s. 713.23 must be
furnished by the contractor in at least the amount of the original contract price
before commencing the construction of the improvement under the direct
contract.
exempt
A copy the payment bond must be attached to the Notice of Commencement
when it is _______.
recorded
Anyone who willfully files a fraudulent lien as defined in 713.31 commits a
felony of the ______ degree
third
When a construction project is "put out" for bid, the contractors are given the
plans and specifications for the project. If any deviations for these specifications
occur, who will be held responsible and may be required to correct them at their
own expense?
The contractor