MAN 4583 EXAM 2 UPDATED ACTUAL QUESTIONS AND
CORRECT ANSWERS
Question:
Which of the following represents an activity on an AON
project network?
Answer:
A node
Question:
When translated into a project network, a work package
will become
Answer:
one or more activities
Question:
Which of the following is provided by both the project
network and the work breakdown structure?
Answer:
activity duration
Question:
On a project network, the activity times are derived from
the
Answer:
work package
Question:
An activity that has more than one dependency arrow
flowing into it is termed a
Answer:
merge activity
Question:
Which of the following can be used without coordinating
with managers of succeeding activities?
Answer:
free slack
Question:
Activities which can take place at the same time are
termed
Answer:
parallel activity
Question:
, Bill is building a project network that involves testing a
prototype. He must design the prototype (activity 1), build
the prototype (activity 2), and test the prototype (activity
3). Activity one is the predecessor for activity 2 and
activity 2 is the predecessor for activity 3. If the
prototype fails testing, Bill must redesign the prototype;
therefore, activity 3 is a predecessor for activity 1. This is
an example of
Answer:
Looping
Question:
________ activities must be completed immediately before a
particular activity.
Answer:
Predecessor
Question:
How soon the project will be finished
Answer:
The forward pass in project network calculations
determines all of the following EXCEPT
Question:
Which of the following correctly calculates the late start
for an activity?
Answer:
Late finish - duration
Question:
Which of the following will correctly calculate the total
slack in an activity?
Answer:
Either late start - early start or late finish - early finish
Question:
If, for some reason, the project must be expedited to
meet an earlier date, which of the following actions
would the project manager take first?
Answer:
Check to see which activities are on the critical path
Question:
If a project has more than one activity that can begin
when the project is to start a common start node should
be used to indicate a clear project beginning on the
network. Without a common start node, each path is a
Answer:
CORRECT ANSWERS
Question:
Which of the following represents an activity on an AON
project network?
Answer:
A node
Question:
When translated into a project network, a work package
will become
Answer:
one or more activities
Question:
Which of the following is provided by both the project
network and the work breakdown structure?
Answer:
activity duration
Question:
On a project network, the activity times are derived from
the
Answer:
work package
Question:
An activity that has more than one dependency arrow
flowing into it is termed a
Answer:
merge activity
Question:
Which of the following can be used without coordinating
with managers of succeeding activities?
Answer:
free slack
Question:
Activities which can take place at the same time are
termed
Answer:
parallel activity
Question:
, Bill is building a project network that involves testing a
prototype. He must design the prototype (activity 1), build
the prototype (activity 2), and test the prototype (activity
3). Activity one is the predecessor for activity 2 and
activity 2 is the predecessor for activity 3. If the
prototype fails testing, Bill must redesign the prototype;
therefore, activity 3 is a predecessor for activity 1. This is
an example of
Answer:
Looping
Question:
________ activities must be completed immediately before a
particular activity.
Answer:
Predecessor
Question:
How soon the project will be finished
Answer:
The forward pass in project network calculations
determines all of the following EXCEPT
Question:
Which of the following correctly calculates the late start
for an activity?
Answer:
Late finish - duration
Question:
Which of the following will correctly calculate the total
slack in an activity?
Answer:
Either late start - early start or late finish - early finish
Question:
If, for some reason, the project must be expedited to
meet an earlier date, which of the following actions
would the project manager take first?
Answer:
Check to see which activities are on the critical path
Question:
If a project has more than one activity that can begin
when the project is to start a common start node should
be used to indicate a clear project beginning on the
network. Without a common start node, each path is a
Answer: