Phase-Specific Questions & Answers
Q1: Which phase includes "Gap analysis, workflow interviews,
and technology selection" as key activities?
Answer: Analysis Phase
Rationale: The analysis phase encompasses gap analysis (4 days),
workflow process interviews (3 days), technology selection (5
days), and RFP development (3 days).
Q2: The milestone "Telehealth system selected" occurs at the
completion of which SDLC phase?
Answer: Analysis Phase
,Rationale: This milestone concludes the analysis phase after
technology selection, RFP development, and readiness assessment
are complete, marking the transition to design.
Q3: How many days are allocated for the implementation
phase?
Answer: 21 days
Rationale: The implementation phase takes 21 days, including
developing an implementation schedule, user training, and system
implementation.
Q4: Which phase includes "Designing workflow,
infrastructure/database design, and system testing"?
Answer: Design/Development Phase
Rationale: This phase includes workflow design, infrastructure
and database design (10 days), telehealth system testing (5 days),
and issue refinement (3 days).
Stakeholder & Task Ownership Questions
Q5: The subtask "Design Database (Logical/Physical)" in the
design/development phase is assigned to which stakeholders?
,Answer: Systems Analyst and IT Department
Rationale: Database architecture requires technical expertise in
logical and physical database design, which falls under the
Systems Analyst and IT Department's responsibilities.
Q6: The planning phase subtask "Defining the Project Scope"
is led by which stakeholders?
Answer: Chief Information Officer (CIO) and Nurse
Informaticist-Project Manager (PM)
Rationale: The CIO and Nurse Informaticist-PM collaborate to
establish core functionalities, define clear project objectives,
determine system size, and set parameters aligning with
organizational strategic goals.
Q7: Who is responsible for monitoring and controlling the
Gantt chart schedule, and taking corrective action?
Answer: Project Manager
Rationale: Monitoring the schedule and implementing corrective
actions is a primary responsibility of the Project Manager.
, Q8: Who is responsible for writing detailed functional
specifications for the telehealth system based on clinician
requirements?
Answer: Systems Analyst
Rationale: The Systems Analyst translates high-level
business/clinical requirements into detailed functional
specifications that the technical team uses for configuration or
development.
Timeline-Specific Questions
Q9: How many days are allocated for "Stakeholder
Involvement" in the planning phase?
Answer: 2 days
Rationale: Stakeholder involvement is allocated 2 days, with the
Project Manager (PM) as the task owner.
Q10: How long does the "Feasibility Study and SWOT
Analysis" subtask take in the planning phase?
Answer: 4 days
Rationale: The feasibility study and SWOT analysis are completed
within the planning phase, typically taking 4 days.
Management 2026/2027 –
Complete 200 Questions and 100%
Verified Answers with Rationales|–
Pass Guaranteed – Already Graded
A+
Phase-Specific Questions & Answers
Q1: Which phase includes "Gap analysis, workflow interviews,
and technology selection" as key activities?
Answer: Analysis Phase
Rationale: The analysis phase encompasses gap analysis (4 days),
workflow process interviews (3 days), technology selection (5
days), and RFP development (3 days).
Q2: The milestone "Telehealth system selected" occurs at the
completion of which SDLC phase?
Answer: Analysis Phase
,Rationale: This milestone concludes the analysis phase after
technology selection, RFP development, and readiness assessment
are complete, marking the transition to design.
Q3: How many days are allocated for the implementation
phase?
Answer: 21 days
Rationale: The implementation phase takes 21 days, including
developing an implementation schedule, user training, and system
implementation.
Q4: Which phase includes "Designing workflow,
infrastructure/database design, and system testing"?
Answer: Design/Development Phase
Rationale: This phase includes workflow design, infrastructure
and database design (10 days), telehealth system testing (5 days),
and issue refinement (3 days).
Stakeholder & Task Ownership Questions
Q5: The subtask "Design Database (Logical/Physical)" in the
design/development phase is assigned to which stakeholders?
,Answer: Systems Analyst and IT Department
Rationale: Database architecture requires technical expertise in
logical and physical database design, which falls under the
Systems Analyst and IT Department's responsibilities.
Q6: The planning phase subtask "Defining the Project Scope"
is led by which stakeholders?
Answer: Chief Information Officer (CIO) and Nurse
Informaticist-Project Manager (PM)
Rationale: The CIO and Nurse Informaticist-PM collaborate to
establish core functionalities, define clear project objectives,
determine system size, and set parameters aligning with
organizational strategic goals.
Q7: Who is responsible for monitoring and controlling the
Gantt chart schedule, and taking corrective action?
Answer: Project Manager
Rationale: Monitoring the schedule and implementing corrective
actions is a primary responsibility of the Project Manager.
, Q8: Who is responsible for writing detailed functional
specifications for the telehealth system based on clinician
requirements?
Answer: Systems Analyst
Rationale: The Systems Analyst translates high-level
business/clinical requirements into detailed functional
specifications that the technical team uses for configuration or
development.
Timeline-Specific Questions
Q9: How many days are allocated for "Stakeholder
Involvement" in the planning phase?
Answer: 2 days
Rationale: Stakeholder involvement is allocated 2 days, with the
Project Manager (PM) as the task owner.
Q10: How long does the "Feasibility Study and SWOT
Analysis" subtask take in the planning phase?
Answer: 4 days
Rationale: The feasibility study and SWOT analysis are completed
within the planning phase, typically taking 4 days.