Question 1.
During the contact administration phase, which functions are the responsibility of facility
engineers with reference to contract modifications? select two that apply.
Correct Answer: Provide technical recommendations to support requests for
subcontract consent & Participate in formal and informal design reviews and vendor
conferences
Question 2.
The environmental Protection Agency uses the Hazard Ranking System to assess the
relative threat associated with actual or potential releases of hazardous substances and is
the primary screening tool for determining if a site is included on the National Priorities List.
Correct Answer: True
Question 3.
If you are planning an installation custodial contract, which contract format would you expect
the contract- ing officer to use for the solicitation and contract?
Correct Answer: Uniform Contract Format
Question 4.
When responding to protests of the final award decision, which function is NOT normally
performed by contracting personnel?
Correct Answer: Provide technical evaluation of protests to support government
positions
Question 5.
Commitment accounting is required for Operations & Maintenance accounts.
Correct Answer: False
Question 6.
If your installation's training ranges include habitat of endangered species, as part of
Sustainable Range Management you are required to minimize the effects of operations on
the habitat.
Correct Answer: True
,Question 7.
The Federal Facilities Compliance Act does not exempt agents, employees, and officers of
the U.S. from personal liability for any civil penalty arisign from acts or omissions within the
scope of their official duties.
Correct Answer: False
Question 8.
Which decision making support system translates user needs into a weapons system or
automated information system.
Correct Answer: Defense Acquisition System
Question 9.
When compiling the list of submittals to be requires in the contract, which functions should
be performed by the facility engineers?
Correct Answer: -NOT- Review submittals to determine if the reports are necessary
and if the number of reports is appropriate -NOT- Ensure approved submittals are
referenced in the specifications
Question 10.
Which phase of the PPBE process has a primary purpose to develop affordable Component
resource packages (programs) that cover 5 or 6 years and describe the levels of forces,
personnel, and money re- quired to execute the DoD strategy?
Correct Answer: Programming Phase
Question 11.
As the scope of waste management has come into focus, it has become clear that the
preferred manner of managing waste is to not generate it in the first place.
Correct Answer: True
Question 12.
Which of the following appropriations is not associated with the Annual Funding Policy?
Correct Answer: Military Construction
Question 13.
Which of the following is not one of the eight critical issues, as defined by DoD, that present
challenges to sustainable range management?
Correct Answer: Growth in size of military ranges
, Question 14.
You are working at a U.S. Army Corps of Engineers civil works facility that requires
remediation. What funds would you request to accomplish the remediation?
Correct Answer: -NOT- Civil Works Appropriation
Question 15.
Federal agencies open themselves to lawsuits for improperly implementing proposed
mitigations designed to reduce environmental impacts
Correct Answer: True
Question 16.
What installation document would you consult if you were looking for an inventory of cultural
re- sources, historic contexts, cultural resource management strategies, and mission
requirements?
Correct Answer: Integrated Cultural Re- source Management Plan
Question 17.
If you are working at a U.S. Army Corps of Engineers civil works facility, you would request
environmental restoration funds from the Defense Environmental Restoration Program to
remediate hazardous substance sites.
Correct Answer: False
Question 18.
When ensuring competition requirements are met, which function should be performed by
contracting personnel?
Correct Answer: -NOT- Assess past performance histories of potential suppliers
-NOT- Determine qualifications of outside vendors not on the Qualified Bidders List
Question 19.
Identify which one of the following questions that you would expect an expert in the
functional area of Environmental to assist in answering:
Correct Answer: What level of NEPA documentation is required for this project?
Question 20.
When closing out a contract, which function is the responsibility of facilities engineers?
Correct Answer: Verify the contract is physically complete
Support Functions comprehensive Questions and
Answers with 100% Correct Answers | Latest Version
Question 1.
During the contact administration phase, which functions are the responsibility of facility
engineers with reference to contract modifications? select two that apply.
Correct Answer: Provide technical recommendations to support requests for
subcontract consent & Participate in formal and informal design reviews and vendor
conferences
Question 2.
The environmental Protection Agency uses the Hazard Ranking System to assess the
relative threat associated with actual or potential releases of hazardous substances and is
the primary screening tool for determining if a site is included on the National Priorities List.
Correct Answer: True
Question 3.
If you are planning an installation custodial contract, which contract format would you expect
the contract- ing officer to use for the solicitation and contract?
Correct Answer: Uniform Contract Format
Question 4.
When responding to protests of the final award decision, which function is NOT normally
performed by contracting personnel?
Correct Answer: Provide technical evaluation of protests to support government
positions
Question 5.
Commitment accounting is required for Operations & Maintenance accounts.
Correct Answer: False
Question 6.
If your installation's training ranges include habitat of endangered species, as part of
Sustainable Range Management you are required to minimize the effects of operations on
the habitat.
Correct Answer: True
,Question 7.
The Federal Facilities Compliance Act does not exempt agents, employees, and officers of
the U.S. from personal liability for any civil penalty arisign from acts or omissions within the
scope of their official duties.
Correct Answer: False
Question 8.
Which decision making support system translates user needs into a weapons system or
automated information system.
Correct Answer: Defense Acquisition System
Question 9.
When compiling the list of submittals to be requires in the contract, which functions should
be performed by the facility engineers?
Correct Answer: -NOT- Review submittals to determine if the reports are necessary
and if the number of reports is appropriate -NOT- Ensure approved submittals are
referenced in the specifications
Question 10.
Which phase of the PPBE process has a primary purpose to develop affordable Component
resource packages (programs) that cover 5 or 6 years and describe the levels of forces,
personnel, and money re- quired to execute the DoD strategy?
Correct Answer: Programming Phase
Question 11.
As the scope of waste management has come into focus, it has become clear that the
preferred manner of managing waste is to not generate it in the first place.
Correct Answer: True
Question 12.
Which of the following appropriations is not associated with the Annual Funding Policy?
Correct Answer: Military Construction
Question 13.
Which of the following is not one of the eight critical issues, as defined by DoD, that present
challenges to sustainable range management?
Correct Answer: Growth in size of military ranges
, Question 14.
You are working at a U.S. Army Corps of Engineers civil works facility that requires
remediation. What funds would you request to accomplish the remediation?
Correct Answer: -NOT- Civil Works Appropriation
Question 15.
Federal agencies open themselves to lawsuits for improperly implementing proposed
mitigations designed to reduce environmental impacts
Correct Answer: True
Question 16.
What installation document would you consult if you were looking for an inventory of cultural
re- sources, historic contexts, cultural resource management strategies, and mission
requirements?
Correct Answer: Integrated Cultural Re- source Management Plan
Question 17.
If you are working at a U.S. Army Corps of Engineers civil works facility, you would request
environmental restoration funds from the Defense Environmental Restoration Program to
remediate hazardous substance sites.
Correct Answer: False
Question 18.
When ensuring competition requirements are met, which function should be performed by
contracting personnel?
Correct Answer: -NOT- Assess past performance histories of potential suppliers
-NOT- Determine qualifications of outside vendors not on the Qualified Bidders List
Question 19.
Identify which one of the following questions that you would expect an expert in the
functional area of Environmental to assist in answering:
Correct Answer: What level of NEPA documentation is required for this project?
Question 20.
When closing out a contract, which function is the responsibility of facilities engineers?
Correct Answer: Verify the contract is physically complete