QSP TWO FINAL STUDY GUIDE 2026
TESTED SOLUTIONS GRADED A+
⩥ Once identified, dischargers shall begin implementing repairs or
design changes to BMPs:
a. Immediately
b. Within24 hours
c. Within48 hours
d. ASAP, but not more than 72 hours
Answer: D
⩥ The discharger shall ensure a QSP develop a Rain Event Action Plan
(REAP) __ hours prior to any likely precipitation event.
a. Immediately
b. 24 hours
c. 48 hours
d. ASAP but not more than 72 hours
Answer: C
⩥ A likely precipitation event is any weather pattern that is forecasted to
have a __% or greater probability of producing precipitation in the
project area.
a. 10
, b. 25
c. 50
d. 75
e. 99
Answer: C
⩥ TRUE OR FALSE: At Risk Level 2 & 3 sites, receiving water
monitoring is required if the receiving water monitoring trigger
exceeded pH, turbidity and SSC. Bioassessment for sites 30 acres or
larger.
Answer: False (Risk level 3 only)
⩥ Visual monitoring is required for non-storm water, pre-rain and post-
rain at what Risk Levels?
a. Risk Level 1
b. Risk Level 2
c. Risk Level 3
d. All of the above
e. Risk Level 1 & 2
Answer: D
⩥ A storm that produces ½ inch or more of precipitation, with a 48 hour
or greater period between rain events is a/an...
TESTED SOLUTIONS GRADED A+
⩥ Once identified, dischargers shall begin implementing repairs or
design changes to BMPs:
a. Immediately
b. Within24 hours
c. Within48 hours
d. ASAP, but not more than 72 hours
Answer: D
⩥ The discharger shall ensure a QSP develop a Rain Event Action Plan
(REAP) __ hours prior to any likely precipitation event.
a. Immediately
b. 24 hours
c. 48 hours
d. ASAP but not more than 72 hours
Answer: C
⩥ A likely precipitation event is any weather pattern that is forecasted to
have a __% or greater probability of producing precipitation in the
project area.
a. 10
, b. 25
c. 50
d. 75
e. 99
Answer: C
⩥ TRUE OR FALSE: At Risk Level 2 & 3 sites, receiving water
monitoring is required if the receiving water monitoring trigger
exceeded pH, turbidity and SSC. Bioassessment for sites 30 acres or
larger.
Answer: False (Risk level 3 only)
⩥ Visual monitoring is required for non-storm water, pre-rain and post-
rain at what Risk Levels?
a. Risk Level 1
b. Risk Level 2
c. Risk Level 3
d. All of the above
e. Risk Level 1 & 2
Answer: D
⩥ A storm that produces ½ inch or more of precipitation, with a 48 hour
or greater period between rain events is a/an...