SECTION 1: ALTERNATIVE ENERGY SYSTEM FUNDAMENTALS (Questions 1-40)
1. What is the primary purpose of an alternative energy system as defined by the
U.S. Department of Veterans Affairs?
A) To provide backup power during grid outages
B) To generate energy from renewable sources that reduce dependence on fossil
fuels
C) To replace all existing electrical infrastructure
D) To increase the facility's overall energy consumption
Answer: B
Rationale: The VA defines alternative energy systems as technologies that
generate energy from renewable sources (solar, wind, geothermal, biomass) to
reduce dependence on fossil fuels, lower greenhouse gas emissions, and support
federal sustainability mandates.
2. Which of the following is classified as an alternative energy source under
federal contracting guidelines?
A) Natural gas
B) Coal
C) Solar photovoltaic (PV)
D) Nuclear power
Answer: C
Rationale: Solar photovoltaic (PV) is classified as a renewable alternative energy
source under federal guidelines. Natural gas, coal, and nuclear are conventional
energy sources, not alternative/renewable.
3. Under the Energy Policy Act of 2005, federal agencies are required to ensure
that renewable energy accounts for what percentage of their total electricity
consumption?
1
,A) 5%
B) 7.5%
C) 10%
D) 15%
Answer: B
Rationale: The Energy Policy Act of 2005 established a requirement that federal
agencies obtain at least 7.5% of their electricity from renewable sources. This
mandate applies to VA facilities and drives the need for alternative energy system
contracting.
4. What is the most common type of alternative energy system installed at VA
facilities?
A) Wind turbines
B) Solar photovoltaic (PV) arrays
C) Geothermal heat pumps
D) Biomass combustion systems
Answer: B
Rationale: Solar photovoltaic (PV) arrays are the most common alternative energy
system installed at VA facilities due to their decreasing costs, scalability, and
compatibility with existing infrastructure.
5. The VA Energy, Environment, and Fleet (EEF) Program Service is responsible for:
A) Managing all construction contracts
B) Facilitating VA's compliance with federal energy and water mandates
C) Issuing contractor licenses
D) Approving all project budgets
Answer: B
Rationale: The EEF Program Service facilitates VA's efforts to comply with federal
mandates related to energy and water efficiency, renewable energy, and
environmental sustainability[reference:0].
2
,6. Which federal law requires federal agencies to reduce energy intensity by 30%
by 2015 (and subsequent targets)?
A) The Clean Air Act
B) The Energy Policy Act of 2005
C) The Energy Independence and Security Act of 2007
D) Executive Order 13423
Answer: D
Rationale: Executive Order 13423 (2007) required federal agencies to reduce
energy intensity by 30% by 2015. Subsequent executive orders have established
additional targets for energy efficiency and renewable energy.
7. What is the primary difference between an Energy Savings Performance
Contract (ESPC) and a Utility Energy Services Contract (UESC)?
A) ESPC is with an ESCO; UESC is with a utility provider
B) ESPC is for new construction; UESC is for renovations
C) ESPC requires upfront payment; UESC is financed through utility bills
D) There is no difference
Answer: A
Rationale: ESPCs are contracts with Energy Service Companies (ESCOs) that
design, install, and finance energy efficiency and renewable energy
projects[reference:1]. UESCs are partnerships with utility providers (gas, water,
electric) to implement similar measures[reference:2].
8. Under a typical Energy Savings Performance Contract (ESPC), the contractor's
payment is:
A) Paid upfront in full
B) Contingent on achieving guaranteed energy savings
C) Paid only after project completion
D) Based on the number of solar panels installed
Answer: B
3
, Rationale: In an ESPC, the contractor's payment is contingent on achieving the
guaranteed energy savings specified in the contract[reference:3]. This
performance-based model aligns the contractor's interests with the agency's
energy goals.
9. Which of the following is NOT a typical energy conservation measure (ECM) in a
VA ESPC?
A) LED lighting retrofits
B) HVAC system upgrades
C) Solar PV installation
D) Building demolition
Answer: D
Rationale: Typical ECMs include LED lighting, HVAC upgrades, and solar PV
installation[reference:4]. Building demolition is not an energy conservation
measure; it is a separate construction activity.
10. What is the role of the Measurement and Verification (M&V) plan in an ESPC?
A) To ensure the contractor is paid correctly
B) To verify that the guaranteed energy savings are achieved
C) To document the project's environmental impact
D) To track the project's construction timeline
Answer: B
Rationale: The M&V plan is a critical component of an ESPC that establishes the
methodology for verifying that the guaranteed energy savings are achieved. This
ensures the performance-based payment model works as intended.
11. Under the Federal Acquisition Regulation (FAR), which part addresses
contracting for energy services?
A) FAR Part 7
B) FAR Part 23
C) FAR Part 36
D) FAR Part 42