Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 42 pages
Exam (elaborations)

FE Civil Construction Engineering Practice Exam 2026–2027 | Full-Length Questions with Correct Answers & Detailed Rationales

Document preview thumbnail
Preview 4 out of 42 pages

Prepare for the FE Civil Construction Engineering Exam 2026–2027 with this comprehensive practice exam designed to strengthen your understanding of essential construction engineering concepts. This full-length resource features challenging, exam-style questions covering important areas of construction engineering, including project planning, scheduling, estimating, productivity, equipment, materials, construction methods, safety, and project management. Every question includes the correct answer and detailed rationale to support effective learning and review. Ideal for FE Civil candidates who want to assess their knowledge, identify weak areas, improve problem-solving skills, and build confidence before the examination. A valuable 2026–2027 FE Civil study and practice resource for serious exam preparation.

Content preview

___________________________________________________________________


FE Civil Construction Engineering
Practice Exam 2026–2027 | Full-Length
Questions, Answers & Detailed
Rationales

1. A contractor has an activity with an original duration of 12 days and a normal
direct cost of $18,000. The crash duration is 8 days with a crash direct cost of
$24,000. Assuming a linear cost-duration relationship, what is the cost slope?

A. $750/day
B. $1,000/day
C. $1,500/day
D. $2,000/day

Answer: $1,500/day

Rationale: The cost slope is (Crash Cost − Normal Cost)/(Normal Duration −
Crash Duration) = ($24,000 − $18,000)/(12 − 8) = $1,500 per day.



2. A construction project has an optimistic activity duration of 6 days, most likely
duration of 9 days, and pessimistic duration of 18 days. Using the PERT expected-
duration equation, what is the expected duration?

,A. 9.0 days
B. 9.5 days
C. 10.0 days
D. 11.0 days

Answer: 10.0 days

Rationale: PERT expected duration is te = (a + 4m + b)/6 = (6 + 4(9) + 18)/6 =
60/6 = 10 days.



3. An excavation requires 4,800 bank cubic yards of soil to be hauled. The soil has
a swell factor of 20%. How many loose cubic yards must be hauled?

A. 4,000 yd³
B. 4,800 yd³
C. 5,760 yd³
D. 6,000 yd³

Answer: 5,760 yd³

Rationale: A 20% swell means loose volume = bank volume × 1.20 = 4,800 × 1.20
= 5,760 yd³.



4. A contractor owns a piece of equipment with a purchase price of $180,000,
estimated salvage value of $30,000, and useful life of 6,000 operating hours.
Using straight-line depreciation based on operating hours, what is the
depreciation cost per operating hour?

A. $20/hr
B. $25/hr
C. $30/hr
D. $35/hr

Answer: $25/hr

,Rationale: Depreciable value = $180,000 − $30,000 = $150,000. Dividing by 6,000
hours gives $25/hr.



5. A crawler excavator has a bucket capacity of 2.0 bank yd³. The bucket fill factor
is 0.90, and the excavator completes 30 cycles per hour. What is the estimated
production?

A. 45 bank yd³/hr
B. 54 bank yd³/hr
C. 60 bank yd³/hr
D. 67 bank yd³/hr

Answer: 54 bank yd³/hr

Rationale: Production = bucket capacity × fill factor × cycles/hr = 2.0 × 0.90 × 30
= 54 bank yd³/hr.



6. A haul truck travels 2.5 miles loaded at 20 mph and returns empty at 30 mph. If
loading and dumping together require 6 minutes, what is the approximate cycle
time?

A. 12 min
B. 15 min
C. 18 min
D. 21 min

Answer: 18 minutes

Rationale: Loaded travel = 2.5/20 × 60 = 7.5 min. Empty travel = 2.5/30 × 60 =
5.0 min. Adding 6 minutes gives an 18.5-minute cycle, approximately 18–19
minutes.

, 7. In a CPM network, an activity has an early start of day 12, early finish of day 18,
late start of day 15, and late finish of day 21. What is the total float?

A. 0 days
B. 3 days
C. 6 days
D. 9 days

Answer: 3 days

Rationale: Total float = LS − ES = 15 − 12 = 3 days, equivalently LF − EF = 21 − 18 =
3 days.



8. Which activity is most directly associated with determining the project's critical
path?

A. Activity with the highest direct cost
B. Activity with the greatest resource requirement
C. Activity with zero total float
D. Activity with the longest individual duration

Answer: Activity with zero total float

Rationale: Critical-path activities generally have zero total float under the
standard CPM convention. A long individual duration does not necessarily make
an activity critical.



9. A concrete placement requires 120 yd³. The contractor's concrete pump can
place 30 yd³/hr, while concrete trucks can supply 45 yd³/hr. Ignoring setup and
interruptions, what controls the placement rate?

A. Truck supply
B. Pump capacity

Document information

Uploaded on
August 29, 2026
Number of pages
42
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$27.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
mml1030
2.6
(5)
Sold
8
Followers
0
Items
1207
Last sold
5 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions