1. A Permit Technician in Texas is primarily responsible for:
A. Designing structural systems for commercial buildings
B. Interpreting approved codes, processing permit applications, and
assisting the public with permit requirements
C. Performing structural engineering calculations for bridges
D. Conducting criminal investigations involving contractors
Answer: B
Rationale: Permit Technicians serve as the first point of contact in most
building departments. Their duties include reviewing permit
applications for completeness, explaining code requirements,
coordinating plan reviews, collecting fees, issuing permits, maintaining
records, and providing customer service. They do not perform
engineering design or criminal investigations.
2. The primary purpose of a building permit is to:
A. Increase property taxes
B. Ensure construction complies with adopted codes and public safety
standards
C. Guarantee contractor profits
D. Eliminate inspections
Answer: B
1
,Rationale: Building permits help ensure construction complies with
adopted building, fire, plumbing, mechanical, electrical, energy, and
accessibility codes, thereby protecting public health, safety, and welfare.
3. Which Texas governmental entity typically adopts and enforces
building codes within its jurisdiction?
A. Federal Bureau of Investigation
B. Local city or county authority having jurisdiction (AHJ)
C. Internal Revenue Service
D. U.S. Supreme Court
Answer: B
Rationale: Building code adoption and enforcement generally occur at
the local government level through municipalities or counties acting as
the Authority Having Jurisdiction (AHJ).
4. Which document generally provides detailed construction
information reviewed before permit issuance?
A. Warranty certificate
B. Construction plans and specifications
C. Mortgage agreement
D. Utility bill
Answer: B
Rationale: Construction plans, specifications, engineering reports, and
supporting documents provide the technical information required to
evaluate compliance with applicable codes.
2
, 5. Which occupancy classification typically involves office
buildings?
A. Group A
B. Group B
C. Group H
D. Group S-2
Answer: B
Rationale: Business occupancies include offices, banks, administrative
facilities, and professional service buildings where business activities
occur.
6. A complete permit application generally includes:
A. Construction documents, application forms, contractor information,
and required fees
B. Only contractor advertisements
C. Vehicle registration
D. Personal tax returns
Answer: A
Rationale: Permit issuance requires sufficient documentation to
establish project scope, responsible parties, code compliance, and
payment of applicable fees.
7. Why is project valuation important during permit processing?
A. It determines election eligibility.
B. It often serves as the basis for calculating permit fees.
C. It replaces inspections.
D. It determines zoning districts.
3
, Answer: B
Rationale: Many jurisdictions calculate permit fees using project
valuation or construction cost schedules established by ordinance.
8. Which code primarily regulates plumbing systems?
A. International Plumbing Code
B. National Electrical Code
C. International Fire Code only
D. International Fuel Gas Code exclusively
Answer: A
Rationale: The International Plumbing Code governs plumbing
installations unless another plumbing code has been adopted by the
jurisdiction.
9. During permit intake, the Permit Technician discovers missing
structural drawings. The technician should:
A. Issue the permit immediately
B. Request the missing documents before processing
C. Ignore the deficiency
D. Perform structural calculations personally
Answer: B
Rationale: Incomplete applications should not proceed to review until
required documentation has been submitted.
10. Which professional generally seals structural engineering
documents?
4