◍ True or FalseThe subcontractor ordinarily provides labor and services. The
general contractor and subcontractor enter into a subcontract. The owner is
not a party to the subcontract. Therefore. the subcontractor must look only
to the general contractor in the event of a breach. (The subcontractor may,
however, have lien rights)..
Answer: True
◍ The Notice of Right to a Lien may be given at any time during the
construction. Is should be delivered in person or sent by registered or
certified mail. The notice only covers labor, materials or equipment rental
for ________ or fewer working days before the notice is given. To protect
all rights to file a lien, the notice should be given within ____________
working days of the start date of the work or the first delivery date of the
materials or equipment..
Answer: eight and eight
◍ Corporation forms considered for small businesses include types:.
Answer: "C" and "S"
◍ Oregon law permits a buyer to cancel a home solicitation sale contract on
_____ notice..
Answer: three days'
◍ An owner-seller may comply with the Homebuyers Protection Act (HPA)
by:- Doing any of these- Purchasing title insurance that does not exclude
filed or unfiled claims of lien,- Obtaining lien waivers or releases- Retaining
at least 25% of the sales price in escrow.
, Answer: - Doing any of these- Purchasing title insurance that does not
exclude filed or unfiled claims of lien,- Obtaining lien waivers or releases-
Retaining at least 25% of the sales price in escrow
◍ Posting Transaction. Posting is the process of transferring the transaction
recorded in the journals to the appropriate accounts. Most companies use
_______ basic types of accounts..
Answer: five
◍ _______ is a simple method and can be done on a regular desk calendar.
The primary advantage to this method is that you can link project tasks to
specific dates. such as: - dates of other projects, - delivery dates of materials,
- payment schedule, and - employee vacation and holidays..
Answer: Calendar Scheduling
◍ A project manager can be involved in more than one construction project at
the same time..
Answer: True
◍ True or FalseIndemnification absolves the indemnified party from any
payment for losses and damages incurred by a third party..
Answer: True
◍ Project includes everything but:.
Answer: Annual office staff salaries
◍ Compliance with environmental regulations can protect a contractor from:-
All of these are correct- Private party lawsuits- Criminal and civil penalties-
Liability claims.
Answer: - All of these are correct- Private party lawsuits- Criminal and civil
penalties- Liability claims
◍ True or FalseIn many states, the employee is considered an employment
contract..
Answer: True
◍ In ______, the parties themselves set forth conditions of any agreement with
, dialogue facilitated by an independent, third party mediator..
Answer: mediation
◍ The Equal Pay Act of 1963 prohibits employers from paying different wages
to ______ who perform essentially the same work under similar conditions..
Answer: men and women
◍ True or FalseSince legal language is often difficult to understand, it is
recommended that you consult with a knowledgeable construction attorney
when drafting and/or interpreting these provisions..
Answer: True
◍ True or FalseMost major population areas promote open burning of
construction or demolition debris..
Answer: False
◍ Employee Rights. The safety law grants employees several important rights.
Among them are the right too:.
Answer: - File a complaint with Oregon OSHA about unsafe or unhealthy
conditions in the workplace and, in some cases, to have their identities kept
confidential from their employer- contest the amount of time OSHA allows
for correcting violations of standards- participate in OSHA workplace
inspections- Employees who exercise their rights under the whistle-blower
law may be protected against employer reprisal
◍ Contractors can avoid pollution by: _____________..
Answer: - Never directing wash water into surface water, storm sewers or
any injection system - using biodegradable washing detergent and avoiding
soaps and chemicals - sweeping, rather than washing, paved areas
◍ True or FalseCheck periodically that all subcontractors have a properly
endorsed CCB license..
Answer: True
◍ If a licensed contractor knowingly uses an unlicensed subcontractor to work
on a job, the CCB may ________..
Answer: - impose a civil penalty (fine)- suspend the contractor's license
EXAMINATION 2026 QUESTIONS
WITH ANSWERS GRADED A+
◍ True or FalseThe subcontractor ordinarily provides labor and services. The
general contractor and subcontractor enter into a subcontract. The owner is
not a party to the subcontract. Therefore. the subcontractor must look only
to the general contractor in the event of a breach. (The subcontractor may,
however, have lien rights)..
Answer: True
◍ The Notice of Right to a Lien may be given at any time during the
construction. Is should be delivered in person or sent by registered or
certified mail. The notice only covers labor, materials or equipment rental
for ________ or fewer working days before the notice is given. To protect
all rights to file a lien, the notice should be given within ____________
working days of the start date of the work or the first delivery date of the
materials or equipment..
Answer: eight and eight
◍ Corporation forms considered for small businesses include types:.
Answer: "C" and "S"
◍ Oregon law permits a buyer to cancel a home solicitation sale contract on
_____ notice..
Answer: three days'
◍ An owner-seller may comply with the Homebuyers Protection Act (HPA)
by:- Doing any of these- Purchasing title insurance that does not exclude
filed or unfiled claims of lien,- Obtaining lien waivers or releases- Retaining
at least 25% of the sales price in escrow.
, Answer: - Doing any of these- Purchasing title insurance that does not
exclude filed or unfiled claims of lien,- Obtaining lien waivers or releases-
Retaining at least 25% of the sales price in escrow
◍ Posting Transaction. Posting is the process of transferring the transaction
recorded in the journals to the appropriate accounts. Most companies use
_______ basic types of accounts..
Answer: five
◍ _______ is a simple method and can be done on a regular desk calendar.
The primary advantage to this method is that you can link project tasks to
specific dates. such as: - dates of other projects, - delivery dates of materials,
- payment schedule, and - employee vacation and holidays..
Answer: Calendar Scheduling
◍ A project manager can be involved in more than one construction project at
the same time..
Answer: True
◍ True or FalseIndemnification absolves the indemnified party from any
payment for losses and damages incurred by a third party..
Answer: True
◍ Project includes everything but:.
Answer: Annual office staff salaries
◍ Compliance with environmental regulations can protect a contractor from:-
All of these are correct- Private party lawsuits- Criminal and civil penalties-
Liability claims.
Answer: - All of these are correct- Private party lawsuits- Criminal and civil
penalties- Liability claims
◍ True or FalseIn many states, the employee is considered an employment
contract..
Answer: True
◍ In ______, the parties themselves set forth conditions of any agreement with
, dialogue facilitated by an independent, third party mediator..
Answer: mediation
◍ The Equal Pay Act of 1963 prohibits employers from paying different wages
to ______ who perform essentially the same work under similar conditions..
Answer: men and women
◍ True or FalseSince legal language is often difficult to understand, it is
recommended that you consult with a knowledgeable construction attorney
when drafting and/or interpreting these provisions..
Answer: True
◍ True or FalseMost major population areas promote open burning of
construction or demolition debris..
Answer: False
◍ Employee Rights. The safety law grants employees several important rights.
Among them are the right too:.
Answer: - File a complaint with Oregon OSHA about unsafe or unhealthy
conditions in the workplace and, in some cases, to have their identities kept
confidential from their employer- contest the amount of time OSHA allows
for correcting violations of standards- participate in OSHA workplace
inspections- Employees who exercise their rights under the whistle-blower
law may be protected against employer reprisal
◍ Contractors can avoid pollution by: _____________..
Answer: - Never directing wash water into surface water, storm sewers or
any injection system - using biodegradable washing detergent and avoiding
soaps and chemicals - sweeping, rather than washing, paved areas
◍ True or FalseCheck periodically that all subcontractors have a properly
endorsed CCB license..
Answer: True
◍ If a licensed contractor knowingly uses an unlicensed subcontractor to work
on a job, the CCB may ________..
Answer: - impose a civil penalty (fine)- suspend the contractor's license