1. What does the Arkansas Heavy Construction (HC)
classification generally authorize a licensed contractor
to perform?
A. Only residential remodelling
B. Only highway paving
C. Work within the heavy-construction classification and
its associated specialties
D. Only electrical work
Correct Answer: Heavy-construction work within the HC
classification and its associated specialties
Rationale: The Arkansas rules provide that a contractor
licensed under a major classification such as HC is
authorized to perform the specialties associated with
that classification, subject to the applicable licensing
requirements.
2. Which of the following is specifically associated with
Arkansas Heavy Construction?
A. Carpet installation
B. Residential roofing only
,C. Dam construction
D. Residential appliance repair
Correct Answer: Dam construction
Rationale: Dam construction is specifically listed among
the specialties included within the Heavy Construction
classification.
3. Which activity is included in heavy construction?
A. Residential painting
B. Boring
C. Residential landscaping only
D. Window cleaning
Correct Answer: Boring
Rationale: Boring is expressly identified as a heavy-
construction specialty.
4. Which document normally establishes the technical
requirements of a construction project?
A. Employee handbook
B. Equipment rental receipt
C. Project specifications
D. Payroll register
Correct Answer: Project specifications
Rationale: Specifications establish material,
workmanship, testing, quality, and other technical
requirements that supplement the drawings.
5. What is the primary purpose of construction
drawings?
A. To calculate payroll taxes
B. To graphically communicate the design and required
,construction
C. To establish employee benefits
D. To replace all contract provisions
Correct Answer: To graphically communicate the design
and required construction
Rationale: Drawings communicate dimensions,
locations, details, elevations, and relationships among
project components.
6. Before beginning major excavation, what should
generally be established first?
A. Paint colors
B. Final landscaping
C. Site control, utility information, limits of excavation,
and required permits
D. Interior finishes
Correct Answer: Site control, utility information, limits
of excavation, and required permits
Rationale: Proper preconstruction planning reduces the
risks of utility strikes, incorrect excavation, property
damage, and regulatory violations.
7. What is the purpose of a benchmark on a construction
site?
A. To identify the property owner
B. To measure concrete strength
C. To provide a known elevation reference
D. To establish insurance limits
Correct Answer: To provide a known elevation reference
Rationale: Benchmarks provide known elevations from
which construction elevations can be established and
checked.
, 8. What does a topographic survey primarily show?
A. Employee classifications
B. Existing ground elevations and site features
C. Contractor profit
D. Concrete mix proportions only
Correct Answer: Existing ground elevations and site
features
Rationale: Topographic surveys provide information
about terrain, elevations, drainage features, structures,
utilities, and other existing site conditions.
9. A cut-and-fill operation is primarily used to:
A. Test concrete cylinders
B. Install electrical panels
C. Balance or move earth to achieve required grades
D. Calculate payroll
Correct Answer: Balance or move earth to achieve
required grades
Rationale: Cut removes material from higher areas and
fill places suitable material in lower areas to achieve
design elevations.
10. What is the primary purpose of soil compaction?
A. Increase soil moisture indefinitely
B. Eliminate all groundwater
C. Increase soil density and improve its engineering
properties
D. Reduce concrete strength
Correct Answer: Increase soil density and improve its
engineering properties