Question 1
1 out of 1 points
All of the following statements about project management process groups are correct
EXCEPT:
Selected
Answer: Project management process groups are often performed only once in each
phase.
Correct Answer:
Project management process groups are often performed only once in each
phase.
Response Feedback: Good work
Question 2
1 out of 1 points
Control Schedule is part of which project management process group?
Selected Answer:
Monitoring and Controlling
Correct Answer:
Monitoring and Controlling
Response Feedback: Good work
Question 3
1 out of 1 points
You are working on an upgrade to a call distribution system for a call center; however, you are
finding it extremely difficult to get the proper resources assigned and tasks completed because
the call center manager is in control of the budget. You have just realized that you work in
what type of an organization?
, Selected Answer:
Functional
Correct Answer:
Functional
Response Feedback: Good work
Question 4
1 out of 1 points
Which of the following statements is incorrect?
Selected Answer:
A project cannot be terminated before the deadline.
Correct Answer:
A project cannot be terminated before the deadline.
Response Feedback: Good work
Question 5
1 out of 1 points
Lori is managing a project in a functional organization. In this organization, she can expect to
find that:
Selected
Answer: Management systems are not designed to support project needs efficiently,
and project management is difficult.
Correct
Answer: Management systems are not designed to support project needs efficiently,
and project management is difficult.
Response Feedback: Good work
Question 6
0 out of 1 points
, A manager asks you to evaluate four new projects that he has suggested for next year. You
review the projects and notice that one is not really a project, but more an operational task.
Which of these is not a project?
Selected
Answer: Respond to a customer request for different product packaging
Correct Answer:
Manage a set of people for the next year to deliver the desired productivity
results
Response That's not correct
Feedback:
Answer: Managing an operating team does not meet the project definition
because it is not temporary or unique.
Question 7
1 out of 1 points
Dan is a project manager in an organization and conducts a workshop on project management.
Which of the following statements made by him about projects is incorrect?
Selected Answer:
Projects exist within an organization and operate as a closed system.
Correct Answer:
Projects exist within an organization and operate as a closed system.
Response Feedback: Good work
Question 8
0 out of 1 points
Which of the following process groups involves people and resources coordination,
stakeholder management, as well as integrating and performing the activities of the project in
accordance with the project management plan?