WGU C722 |PROJECT MANAGEMENT| PA |PRE-ASSESSMENT |EXAM QUESTIONS AND ANSWERS| FULLY SOLVED

Document preview thumbnail
Preview 4 out of 64 pages

WGU C722 |PROJECT MANAGEMENT| PA |PRE-ASSESSMENT |EXAM QUESTIONS AND ANSWERS| FULLY SOLVED

Content preview

WGU C722 PROJECT MANAGEMENT |PA| |PRE-ASSESSMENT | EXAM
QUESTIONS AND ANSWERS



Correct

Incorrect




1 of 70

Term



which activity is accomplished as part of the planning process of a
project?



Give this one a try later!



a) initiating
b) executing*
c) operating
d) closing
e) planning*




a) recognizing and rewarding performance
b) drafting the project charter*
c) assessing project quality
d) completing the project documentation




2) Developing the work breakdown structure
5) Capturing lessons learned

, 3) Working to produce project deliverables
1) Collecting customer requirements
4) Customers evaluating the project outcomes



a) reconciling the vendor accounts
b) finalizing the project budget*
c) documenting any requested changes to scope
d) reviewing the lessons learned in the project


Don't know?




2 of 70

Term



Which PMBOK process group is described as the delivery part of
project management where the main activity happens?



Give this one a try later!



Deliverable Executing




Planning deliverable


Don't know?




3 of 70

Term


A general contractor is managing a highway construction project
that will repair a flood-damaged road. The project was documented

,in a cost-plus-incentive fee contract that specified a completion
date of June 30. The Dept of Transportation has offered an incentive
for early completion of repairs.
Which triple-constraint baseline remained unchanged by the effects
of the incentive?


Give this one a try later!



a) managing the change a) price
b) reinforcing the change* b) cost
c) preparing for the change c) scope*
d) upgrading the change d) time




a) 15 a) time*
b) 23* b) penalties
c) 30 c) cost
d) 35 d) incentives


Don't know?




4 of 70

Term


A project manager is working on a large two-year IT project. At the
end of the first year, the project is two months behind schedule
because the interface programming is taking longer than planned.
The sponsor will not extend the deadline or the budget but is willing
to eliminate the interface.
Which schedule compression technique can the project manager
use?

, Give this one a try later!


a) reinforce the change a) sacred cow
b) upgrading the change b) operating necessity
c) managing the change c) competitive necessity*
d) preparing for the change* d) checklists




a) scope reduction* a) reduced quality of deliverables*
b) determining the critical path b) reduction in rework
c) resource leveling c) less overtime
d) fast-tracking d) use of fewer resources


Don't know?




5 of 70

Term



What is the purpose of the cost performance index (CPI)?



Give this one a try later!



a) the concept that a dollar today Is worth a dollar, but a dollar in a year will be
worth less than a dollar*
b) the measure in time in which total cash received is equal to, or exceeds, total
costs
c) the value of what you are giving up when you select one of two projects
d) the discount amount when present value of cash intake equals the original
investment




a) assigning project team members to new projects
b) coaching team members
c) verifying that the deliverables meet the required scope
d) reconciling the vendor accounts*

Document information

Uploaded on
August 25, 2026
Number of pages
64
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$16.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
millyphilip
3.6
(555)
Sold
2967
Followers
1963
Items
46086
Last sold
11 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions