WGU C722 |PA|PRE-ASSESSMENT SECTION 5 |EXAM QUESTIONS AND ANSWERS
Correct
Incorrect
1 of 34
Term
What is true about bottom-up estimating?
Give this one a try later!
Bottom-up estimates are early approximations of cost.
A bottom-up estimate must be created before the WBS is available.
Bottom-up estimates are done early in a project's life cycle when the
organization is determining how the project will meet a business need.
Creating a bottom-up estimate requires people with expertise to do the
work estimate of the labor, supplies, materials, equipment, and any other
resources needed to complete each individual work activity.
, Don't know?
2 of 34
Term
Which tool is commonly used for building a resource plan
Give this one a try later!
WBS number The project charter
Gantt chart
Don't know?
3 of 34
Term
What has to be created first before a bottom-up estimate can be
generated?
Give this one a try later!
WBS Project charter
Gantt chart
, Don't know?
4 of 34
Term
The task and activity information from the WBS assists in achieving
which goal?
Give this one a try later!
Avoiding missing parts to project
Budgeting
scope
Identifying quality points
Don't know?
5 of 34
Term
What is developed from the project scope and statement of work?
Give this one a try later!
the project charter Gantt chart
the work breakdown structure
Correct
Incorrect
1 of 34
Term
What is true about bottom-up estimating?
Give this one a try later!
Bottom-up estimates are early approximations of cost.
A bottom-up estimate must be created before the WBS is available.
Bottom-up estimates are done early in a project's life cycle when the
organization is determining how the project will meet a business need.
Creating a bottom-up estimate requires people with expertise to do the
work estimate of the labor, supplies, materials, equipment, and any other
resources needed to complete each individual work activity.
, Don't know?
2 of 34
Term
Which tool is commonly used for building a resource plan
Give this one a try later!
WBS number The project charter
Gantt chart
Don't know?
3 of 34
Term
What has to be created first before a bottom-up estimate can be
generated?
Give this one a try later!
WBS Project charter
Gantt chart
, Don't know?
4 of 34
Term
The task and activity information from the WBS assists in achieving
which goal?
Give this one a try later!
Avoiding missing parts to project
Budgeting
scope
Identifying quality points
Don't know?
5 of 34
Term
What is developed from the project scope and statement of work?
Give this one a try later!
the project charter Gantt chart
the work breakdown structure