Contractor Practice Exam |
Questions, Verified Answers &
Detailed Rationales |
Complete Contractor License
Exam Prep Study Guide |
Updated 2026
1. What is the primary purpose of a site excavation plan?
A. To determine the colour of the building
B. To establish excavation limits, grades, utilities, access, and
safety requirements
C. To calculate the contractor’s tax liability
D. To select interior finishes
Answer: To establish excavation limits, grades, utilities,
access, and safety requirements
Rationale: A properly prepared excavation plan
establishes the scope and limits of earthwork while
helping coordinate grades, utilities, equipment access,
drainage, and worker safety.
2. Before excavating, what should a contractor do regarding
underground utilities?
A. Begin digging and watch for warning signs
B. Assume utilities are at least 5 feet deep
C. Contact the appropriate utility-locating service and verify
markings
D. Only check the property survey
Answer: Contact the appropriate utility-locating service
and verify markings
,Rationale: Underground utilities must be located before
excavation begins. A contractor should not rely solely
on assumptions or visible evidence.
3. What does a benchmark provide on a construction site?
A. A permanent reference elevation
B. The location of all property corners
C. The soil classification
D. The contractor's license number
Answer: A permanent reference elevation
Rationale: A benchmark provides a known elevation
used by surveyors and contractors to establish grades
and elevations throughout a project.
4. What is the purpose of a trench protective system?
A. To increase equipment speed
B. To prevent cave-ins and protect workers
C. To reduce fuel consumption
D. To improve concrete strength
Answer: To prevent cave-ins and protect workers
Rationale: Protective systems such as sloping,
benching, shoring, and trench shields are used to
protect workers from trench-wall collapse and related
hazards.
5. Which soil condition generally presents the greatest cave-
in hazard?
A. Stable, undisturbed rock
B. Dense, dry material
C. Loose or saturated soil
D. Freshly compacted aggregate
Answer: Loose or saturated soil
Rationale: Loose and saturated soils can lose stability
quickly and are particularly susceptible to collapse.
, 6. What is the purpose of sloping the sides of a trench?
A. To make the trench deeper
B. To reduce the likelihood of a cave-in
C. To eliminate the need for utility locating
D. To increase groundwater pressure
Answer: To reduce the likelihood of a cave-in
Rationale: Sloping reduces the vertical loading and
instability of trench walls, helping protect workers from
cave-ins.
7. What is benching?
A. Installing concrete benches at a jobsite
B. Cutting the sides of an excavation into a series of horizontal
levels
C. Compacting soil in one pass
D. Measuring property boundaries
Answer: Cutting the sides of an excavation into a series
of horizontal levels
Rationale: Benching creates stepped levels in suitable
soil conditions and can reduce the risk of excavation-
wall collapse.
8. What is shoring designed to do?
A. Support excavation walls
B. Increase soil moisture
C. Replace all excavation equipment
D. Establish property lines
Answer: Support excavation walls
Rationale: Shoring systems provide structural support
to excavation walls and help prevent soil from moving
into the excavation.
9. What is a trench shield commonly called?
, A. A trench box
B. A grade rod
C. A spreader bar
D. A compactor
Answer: A trench box
Rationale: A trench box is a protective system designed
to protect workers inside a trench from cave-in hazards.
10. Why should excavated material generally be kept
away from the edge of a trench?
A. It makes the material harder to load
B. It can add surcharge pressure and contribute to a cave-in
C. It changes the soil color
D. It prevents surveying
Answer: It can add surcharge pressure and contribute to
a cave-in
Rationale: Spoil piles and equipment near an excavation
edge can increase the load on the trench wall and
contribute to instability.
11. What is the main purpose of a compaction test?
A. To determine paint thickness
B. To determine whether soil has been compacted to the
required density
C. To determine concrete color
D. To locate underground electrical lines
Answer: To determine whether soil has been compacted
to the required density
Rationale: Compaction testing verifies that placed fill
achieves the density required by the project
specifications or applicable code.
12. What equipment is commonly used for compacting
granular soil?