• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 33 pages
Exam (elaborations)

Final Construction Management Exam Practice Questions with Correct Answers and Detailed Rationales

Document preview thumbnail
Preview 4 out of 33 pages

Final Construction Management Exam Practice Questions with Correct Answers and Detailed Rationales

Content preview

Final Construction Management
Exam Practice Questions with Correct
Answers and Detailed Rationales

This comprehensive practice exam is designed to help students prepare for a
Construction Management final examination. It covers key domains including Project
Delivery Methods, Scheduling & Critical Path Method (CPM), Cost Estimation & Control,
Contract Administration & Law, Risk Management, Safety & Quality Control, and
Sustainable Construction Practices.




SECTION 1: PROJECT DELIVERY & CONTRACT TYPES
(Questions 1-15)


Question 1​
A project owner hires an architect to design the project and then separately hires a
contractor to build it after the design is complete. This project delivery method is known
as:

A. Design-Build​
B. Construction Manager at Risk (CMAR)​
C. Design-Bid-Build (DBB)​
D. Integrated Project Delivery (IPD)

Correct Answer: C. Design-Bid-Build (DBB)

Rationale: DBB is the traditional method where design and construction are sequential
and contracted separately. The owner first hires a designer, then puts the completed
design out for competitive bids, and finally awards a construction contract to the lowest
responsible bidder.

,Question 2​
In a Construction Manager at Risk (CMAR) delivery method, the construction manager
provides the owner with a:

A. Guaranteed Maximum Price (GMP)​
B. Fixed hourly rate​
C. Cost-plus-percentage fee​
D. Unit price contract

Correct Answer: A. Guaranteed Maximum Price (GMP)

Rationale: In CMAR, the construction manager acts as a consultant during design and
then provides a GMP for construction. The CM bears the risk for any cost overruns
above the GMP, while savings below the GMP are typically shared with the owner.



Question 3​
Given that the scope of the construction work is well-defined with all its drawings,
specifications, quantities and estimates, which type of contract would be most
preferred?

A. EPC contract​
B. Percentage rate contract​
C. Item rate contract​
D. Lump sum contract

Correct Answer: D. Lump sum contract

Rationale: In a lump sum contract, a contractor is required to quote a fixed sum for
execution of work complete in all respects in the stipulated time according to the
drawings, design, and specification. This type is most preferred when the scope is
well-defined.



Question 4​
A contract that reimburses the contractor for all allowable direct costs plus an
additional fixed fee regardless of final cost is called:

A. Lump sum contract​
B. Cost-plus-fixed-fee contract​

,C. Time and materials contract​
D. Unit price contract

Correct Answer: B. Cost-plus-fixed-fee contract

Rationale: In a cost-plus-fixed-fee contract, the contractor receives reimbursement for
all actual allowable costs plus a predetermined fixed fee that does not change with final
project cost. This arrangement provides stability for the contractor while allowing the
owner to adjust scope.



Question 5​
Which contract type would be best if the scope of work cannot be clearly defined?

A. Lump sum contract​
B. Unit price contract​
C. Cost plus a fee contract​
D. Fixed fee with GMP

Correct Answer: C. Cost plus a fee contract

Rationale: Cost plus a fee contract is appropriate when the scope of work cannot be
defined. The contractor is reimbursed for construction costs as defined in the
agreement. This provides flexibility for projects with uncertain scope.



Question 6​
In a unit price contract, the contractor bases the bid on:

A. A fixed total price​
B. Estimated quantities of work​
C. Actual quantities of work only​
D. Time and materials used

Correct Answer: B. Estimated quantities of work

Rationale: In a unit price contract, the contractor bases the bid on estimated quantities
of work. Final payment is based on actual measured quantities, making this contract
type ideal when quantities are uncertain but the type of work is defined.

, Question 7​
Which contract type places the highest risk on the contractor?

A. Cost plus a fee​
B. Time and materials​
C. Lump sum (fixed price)​
D. Guaranteed Maximum Price (GMP)

Correct Answer: C. Lump sum (fixed price)

Rationale: Lump sum contracts require the contractor to absorb all cost overruns.
Cost-plus shifts risk to the owner; Time and Materials reimburses costs; GMP caps
owner risk.



Question 8​
Which project delivery method involves only one firm being contracted for both design
and construction?

A. Design-Bid-Build (DBB)​
B. Construction Manager at Risk (CMAR)​
C. Design-Build (DB)​
D. Integrated Project Delivery (IPD)

Correct Answer: C. Design-Build (DB)

Rationale: Design-Build is the project delivery method in which only one firm is
contracted for both design and construction of the project. This approach fosters good
communication and coordination between designers and builders.



Question 9​
What project delivery method is best used if the project is highly technical and requires
good communication between designers and builders?

A. Design-Bid-Build (DBB)​
B. Construction Manager at Risk (CMAR)​
C. Design-Build (DB)​
D. Multi-prime contracting

Document information

Uploaded on
August 24, 2026
Number of pages
33
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$30.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
martinezmartinez
4.9
(260)
Sold
103
Followers
44
Items
4698
Last sold
2 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions