2/13/25, 2:54 PM 6-3 Quiz: Modules Five and Six - QSO-645-10246-M01 Project Mgmt for PMP Cert 2025 D-1 (Jan - Mar)




6-3 Quiz: Modules Five and Six


1




2




Your work has been saved and submitted
Written Feb 13, 2025 2:44 PM - Feb 13, 2025 2:53 PMAttempt 1 of 2




Attempt Score -
Overall Grade (Highest Attempt) -




Question 1 points

Project team members are busier than usual. They indicate that they do not have the time to
update the lessons learned because of other project responsibilities.

How should the project manager respond to this issue? Select one.

Ensure there is an agenda item for discussion of lessons learned from project activities as part of all project
meetings.
File a change request to the project management office (PMO) to change how often lessons learned is
collected.
Require submission of lessons learned documentation after each project deliverable is accepted by the
customer.

Bring in a consultant to assist with collecting lessons learned to help reduce the burden on project team.


Hide question 1 feedback

Feedback
The lessons learned collection must be present throughout the project, using different facilitating techniques.




Question 2 points

A large, valuable sculpture in a big city needs to be moved safely from one location to another.
This is project A, which must be done before project B, the city's largest infrastructure project,
can begin. After a 2-week delay, the project managers meet. Project manager A announces
another 6 months and US$900,000 will be needed to remove the sculpture and success cannot
https://learn.snhu.edu/d2l/le/content/1807581/viewContent/38354195/View 1/6

, 2/13/25, 2:54 PM 6-3 Quiz: Modules Five and Six - QSO-645-10246-M01 Project Mgmt for PMP Cert 2025 D-1 (Jan - Mar)

be guaranteed.

What should project manager B do?

Cancel the project and disband the team until the roadmap for project A can be fixed.

Perform a Monte Carlo simulation on the possible outcomes.

Prepare a risk assessment on project A using a Stacey matrix.

Brainstorm an alternative solution with the stakeholders of both projects.


Hide question 2 feedback

Feedback
The dependencies between these two projects present a great challenge to the project B's team. They need to
balance their internal priorities and the stakeholders' priorities as well as the priorities of the owners of project B,
who are also stakeholders. The only way to do this is to prioritize positive project outcomes.




Question 3 points

A project has the following budgetary features:

Total budget of US$3 million
Planned cost of US$630,000
Actual cost of US$650,000
Earned value of US$540,000

Which statement is true about this project? Select one.

It is under budget and behind schedule.
It is under budget and ahead of schedule.

It is over budget and ahead of schedule.
It is over budget and behind schedule.


Hide question 3 feedback

Feedback
CPI = EV/AC = $540,000/$650,000 = less than 1 = over budget

SPI = EV/PV = $540,000/$630,000 = less than 1 = behind schedule




Question 4 points

Both the project sponsor and project team assure a project manager that the new project has a
realistic schedule and an adequate budget. The project manager worries that unplanned events
could threaten the project's success.


https://learn.snhu.edu/d2l/le/content/1807581/viewContent/38354195/View 2/6

Document information

Uploaded on
August 24, 2026
Number of pages
6
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$15.58

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
wisenurse
5.0
(1)
Sold
39
Followers
2
Items
1080
Last sold
6 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions