Question 1
Where can you define which daily logs are visible as well as change the order in which
they're listed?
a. On the Project Dashboard (Home tab)
b. In the tool's advanced configuration settings page
c. In the Project level toolbox
d. In the Company level settings page
CORRECT ANSWER
b. In the tool's advanced configuration settings page
Question 2
Which permission level should you give to a project's superintendent if you would like
him/her to manage the project's daily log?
a. None
b. Read-only
c. Standard
d. Admin
CORRECT ANSWER
d. Admin
Question 3
True or False: You can add log information for a date in the future.
1
@https://www.stuvia.com/user/thestudyvault
, CORRECT ANSWER
False
Question 4
True or False: When you create a new daily log entry by copying one from a previous day,
you will still be allowed to edit its information.
CORRECT ANSWER
True
Question 5
True or False: Procore recommends you give your collaborators 'Admin' level permissions
to the project's Daily Log tool so your superintendent can "crowd source" the Daily Log.
CORRECT ANSWER
False
Question 6
True or False: With Collaborator Daily Logs enabled, you will be able to approve
collaborator-submitted daily logs before they become visible in the project's Daily Log.
CORRECT ANSWER
True
Question 7
How can you give someone who has 'Standard' or 'Read-only' permissions on the Incidents
tool access to an incident that's marked as private?
2
@https://www.stuvia.com/user/thestudyvault
Where can you define which daily logs are visible as well as change the order in which
they're listed?
a. On the Project Dashboard (Home tab)
b. In the tool's advanced configuration settings page
c. In the Project level toolbox
d. In the Company level settings page
CORRECT ANSWER
b. In the tool's advanced configuration settings page
Question 2
Which permission level should you give to a project's superintendent if you would like
him/her to manage the project's daily log?
a. None
b. Read-only
c. Standard
d. Admin
CORRECT ANSWER
d. Admin
Question 3
True or False: You can add log information for a date in the future.
1
@https://www.stuvia.com/user/thestudyvault
, CORRECT ANSWER
False
Question 4
True or False: When you create a new daily log entry by copying one from a previous day,
you will still be allowed to edit its information.
CORRECT ANSWER
True
Question 5
True or False: Procore recommends you give your collaborators 'Admin' level permissions
to the project's Daily Log tool so your superintendent can "crowd source" the Daily Log.
CORRECT ANSWER
False
Question 6
True or False: With Collaborator Daily Logs enabled, you will be able to approve
collaborator-submitted daily logs before they become visible in the project's Daily Log.
CORRECT ANSWER
True
Question 7
How can you give someone who has 'Standard' or 'Read-only' permissions on the Incidents
tool access to an incident that's marked as private?
2