The process of "two or more people or organizations working together toward a common goal"
is the definition of which of the following terms? 1 - Answer Collaboration
A business analyst wants to describe the interaction between a user and a system application.
Which technique would the business analyst use to document this interaction? 1 - Answer Use
case description
A use case description documents the "conversation" or interaction between a user and a
system application.
A business analyst wants to model the "why" of a change. Which technique would be used to
accomplish this task? 1 - Answer Scope Modeling
Which of the following are ways that business analysts collaborate with other stakeholders to
effectively address or "treat" risks? - Answer a. Mitigating the consequences, developing a
contingency plan.
b. Removing the source of the risk, developing a contingency plan.
c. Avoiding the risk, developing a contingency plan.
d. Removing the source of the risk, mitigating the consequences.
answer is d
Which type of stakeholder is an organizational change consultant and a trainer? 1 - Answer
Implementation subject matter experts
Implementation SME refers to any stakeholder who has specialized knowledge regarding the
implementation of one or more solution components.
Which of the following is true about reviews? - Answer a. Objectives, techniques, and
participants are the three dimensions of reviews.
, b. Each review is focused on the skills or actions of the participants and not on the work
product.
c. Reviews and workshops are synonymous.
d. Each review is tailored to the needs of the participants and business analyst.
answer is a
A business analyst is eliciting data requirements by discussing how two systems currently
exchange data and services. What non-functional a requirement is being discussed? 1 - Answer
Interoperability
Interoperability is the ability of systems to communicate by exchanging data or services.
A business analyst is conducting a workshop to come up with ideas on how to solve the issue of
delays in the billing process. Which one of the following would be a suggested starting point? -
Answer a. Describe the current process.
b. Draw a diagram of the process.
c. Identify potential root causes for the delays.
d. Brainstorm potential solutions.
answer is b
The specify and model requirements task can result in a requirement or a design. What is the
difference? - Answer a. They are used interchangeably.
b. When the focus is on the need, the output is a design. When the focus is on solution, the
output is a requirement.
c. The BA can only specify and model a design.
d. When the focus is on the need, the output is a requirement. When the focus is on the
solution, the output is a design.