Asbestos Practice Exam 2 Questions
With Correct Answers
ACM stands for - CORRECT ANSWER✔✔-Asbestos Containing Material
| | | | | | |
The operating agency for each public school building in which fraible
| | | | | | | | | | |
asbestos containing materials have been identified shall monitor
| | | | | | | |
airborne asbestos levels in each sampling area. For at least how many
| | | | | | | | | | | |
hours during a period of normal activity must this monitoring be done? -
| | | | | | | | | | | |
CORRECT ANSWER✔✔-it must be done for 8 hours
| | | | | | | |
What portion of insurance coverage for medical exams and monitoring
| | | | | | | | | |
as required by law must the contractor provide? - CORRECT
| | | | | | | | | |
ANSWER✔✔-all of the cost | | |
Responsibility for ACM control in a building is primarily that of the -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-owner |
The category least suspected of releasing asbestos fibers into the air
| | | | | | | | | | |
because of friability is - CORRECT ANSWER✔✔-miscellaneous products
| | | | | | |
,The program manager can speed up the sampling process when
| | | | | | | | | |
preparing for a building inspection for asbestos by revealing ACM in the
| | | | | | | | | | |
- CORRECT ANSWER✔✔-blueprints
| | |
Before plastic barriers are set up, the work area should be - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-wet cleaned |
What percentage of Federal, commercial, and residential construction
| | | | | | | |
before 1970 contained asbestos in pipe or boiler insulation? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-20%
The efficiency of the negative air pressure unit or cabinet is determined
| | | | | | | | | | | |
by the - CORRECT ANSWER✔✔-Magnehelic guage and the manometer
| | | | | | | |
Disposal bags are primarily made of which type of plastic? - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-A minimum of 6 mil | | | |
A contractor must sign the contract and execute the bonds _____ days
| | | | | | | | | | | |
after being awarded the bid - CORRECT ANSWER✔✔-5 days
| | | | | | | |
What should be posted "in plain view" of workers at teh jobsite to
| | | | | | | | | | | | |
ensure safety? - CORRECT ANSWER✔✔-Emergency telephone numbers
| | | | | |
, For a negative air pressure unit or cabinet, what volt-power supply is
| | | | | | | | | | | |
needed? - CORRECT ANSWER✔✔-115 volt
| | | |
Assembly Bill 2040 requires warning signs to state - CORRECT
| | | | | | | | | |
ANSWER✔✔-Danger- asbestos cancer and lung hazard- keep out! | | | | | | |
Mesothelioma is a cancer of - CORRECT ANSWER✔✔-the lining of the
| | | | | | | | | | |
lungs
These are all true - CORRECT ANSWER✔✔-During removal, asbestos
| | | | | | | | |
must be wetted to keep down airborne fibers and there must be no
| | | | | | | | | | | | |
visible emission to the outside air.
| | | | |
After removal, asbestos must be kept wet, placed in leak tight
| | | | | | | | | | |
containers with warning labels, and transported to a State approved
| | | | | | | | | |
waste disposal site.
| |
Proper work practices must be followed in renovation or demolition
| | | | | | | | | |
jobs involving at least 260 lf of asbestos on pipes and at least 160sf on
| | | | | | | | | | | | | | |
flat surfaces.
|
Asbestos may not be dropped on the ground, even if wetted
| | | | | | | | | |
With Correct Answers
ACM stands for - CORRECT ANSWER✔✔-Asbestos Containing Material
| | | | | | |
The operating agency for each public school building in which fraible
| | | | | | | | | | |
asbestos containing materials have been identified shall monitor
| | | | | | | |
airborne asbestos levels in each sampling area. For at least how many
| | | | | | | | | | | |
hours during a period of normal activity must this monitoring be done? -
| | | | | | | | | | | |
CORRECT ANSWER✔✔-it must be done for 8 hours
| | | | | | | |
What portion of insurance coverage for medical exams and monitoring
| | | | | | | | | |
as required by law must the contractor provide? - CORRECT
| | | | | | | | | |
ANSWER✔✔-all of the cost | | |
Responsibility for ACM control in a building is primarily that of the -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-owner |
The category least suspected of releasing asbestos fibers into the air
| | | | | | | | | | |
because of friability is - CORRECT ANSWER✔✔-miscellaneous products
| | | | | | |
,The program manager can speed up the sampling process when
| | | | | | | | | |
preparing for a building inspection for asbestos by revealing ACM in the
| | | | | | | | | | |
- CORRECT ANSWER✔✔-blueprints
| | |
Before plastic barriers are set up, the work area should be - CORRECT
| | | | | | | | | | | | |
ANSWER✔✔-wet cleaned |
What percentage of Federal, commercial, and residential construction
| | | | | | | |
before 1970 contained asbestos in pipe or boiler insulation? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-20%
The efficiency of the negative air pressure unit or cabinet is determined
| | | | | | | | | | | |
by the - CORRECT ANSWER✔✔-Magnehelic guage and the manometer
| | | | | | | |
Disposal bags are primarily made of which type of plastic? - CORRECT
| | | | | | | | | | | |
ANSWER✔✔-A minimum of 6 mil | | | |
A contractor must sign the contract and execute the bonds _____ days
| | | | | | | | | | | |
after being awarded the bid - CORRECT ANSWER✔✔-5 days
| | | | | | | |
What should be posted "in plain view" of workers at teh jobsite to
| | | | | | | | | | | | |
ensure safety? - CORRECT ANSWER✔✔-Emergency telephone numbers
| | | | | |
, For a negative air pressure unit or cabinet, what volt-power supply is
| | | | | | | | | | | |
needed? - CORRECT ANSWER✔✔-115 volt
| | | |
Assembly Bill 2040 requires warning signs to state - CORRECT
| | | | | | | | | |
ANSWER✔✔-Danger- asbestos cancer and lung hazard- keep out! | | | | | | |
Mesothelioma is a cancer of - CORRECT ANSWER✔✔-the lining of the
| | | | | | | | | | |
lungs
These are all true - CORRECT ANSWER✔✔-During removal, asbestos
| | | | | | | | |
must be wetted to keep down airborne fibers and there must be no
| | | | | | | | | | | | |
visible emission to the outside air.
| | | | |
After removal, asbestos must be kept wet, placed in leak tight
| | | | | | | | | | |
containers with warning labels, and transported to a State approved
| | | | | | | | | |
waste disposal site.
| |
Proper work practices must be followed in renovation or demolition
| | | | | | | | | |
jobs involving at least 260 lf of asbestos on pipes and at least 160sf on
| | | | | | | | | | | | | | |
flat surfaces.
|
Asbestos may not be dropped on the ground, even if wetted
| | | | | | | | | |