⩥ OSHA specification which apply to wire rope used in construction
rigging.
Answer: -no more than three tucks ina wire rope
-wire ropes used for hoisting or lowering be continuous length of rope
without knot or splice except for eye splices at the end
-eyes in wire rope slings or bridles not to be compromised of wire rope
clips or knots
-no more than 10% visible broken wires
⩥ concerns of 'system safety analysis'.
Answer: analytical stufy of the interacting components of a process.
⩥ 'gas chromatography'.
Answer: -measure environmental toxins in the air
-separates and isolates components of a mixture of gases
,-combine with mass spectometer
⩥ employee benefits of JSA.
Answer: -supervisor meets with employees
-train in productive and safe operations
-supervisor communicates and apply safety techniques
⩥ Footcandles for Gen Constr. concrete placement, excavation, loading
platforms, refueling, field maintenance areas.
Answer: 5
⩥ Footcandles for Indoor warehouses, corridors, hallways, and exit
ways.
Answer: 5
⩥ Footcandles for tunnels, shafts and general underground work areas.
Answer: 5
⩥ Footcandles for construction plant and shops, mechanical and
electrical equipment rooms, carpenter shops, rigging lofts and active
storerooms.
Answer: 10
, ⩥ Footcandles for Underground operations involving work at a heading
involving drilling, mucking, and scaling.
Answer: 10
⩥ Footcandles for First-aid, stations, infirmaries, and offices.
Answer: 30
⩥ Permissible Noise Exposure for 8 hour day.
Answer: 90
⩥ Permissible Noise Exposure for 1/4 hour.
Answer: 115
⩥ Permissible Noise Exposure for 4 hours.
Answer: 95
⩥ Permissible Noise Exposure for 2 hours.
Answer: 100
⩥ CFR
10, 16, 23, 29, 40, 42, 49.
Answer: 10-Energy
SAFETY TECHNICIAN EXAM END OF
COURSE STUDY GUIDE LATEST UPDATED
ACTUAL TESTED QUESTIONS AND
CORRECT ANSWERS
⩥ OSHA specification which apply to wire rope used in construction
rigging.
Answer: -no more than three tucks ina wire rope
-wire ropes used for hoisting or lowering be continuous length of rope
without knot or splice except for eye splices at the end
-eyes in wire rope slings or bridles not to be compromised of wire rope
clips or knots
-no more than 10% visible broken wires
⩥ concerns of 'system safety analysis'.
Answer: analytical stufy of the interacting components of a process.
⩥ 'gas chromatography'.
Answer: -measure environmental toxins in the air
-separates and isolates components of a mixture of gases
,-combine with mass spectometer
⩥ employee benefits of JSA.
Answer: -supervisor meets with employees
-train in productive and safe operations
-supervisor communicates and apply safety techniques
⩥ Footcandles for Gen Constr. concrete placement, excavation, loading
platforms, refueling, field maintenance areas.
Answer: 5
⩥ Footcandles for Indoor warehouses, corridors, hallways, and exit
ways.
Answer: 5
⩥ Footcandles for tunnels, shafts and general underground work areas.
Answer: 5
⩥ Footcandles for construction plant and shops, mechanical and
electrical equipment rooms, carpenter shops, rigging lofts and active
storerooms.
Answer: 10
, ⩥ Footcandles for Underground operations involving work at a heading
involving drilling, mucking, and scaling.
Answer: 10
⩥ Footcandles for First-aid, stations, infirmaries, and offices.
Answer: 30
⩥ Permissible Noise Exposure for 8 hour day.
Answer: 90
⩥ Permissible Noise Exposure for 1/4 hour.
Answer: 115
⩥ Permissible Noise Exposure for 4 hours.
Answer: 95
⩥ Permissible Noise Exposure for 2 hours.
Answer: 100
⩥ CFR
10, 16, 23, 29, 40, 42, 49.
Answer: 10-Energy