ADVANCED PROJECT MANAGEMENT
EXAM 1 (PMT 3600V) QUESTIONS AND
ANSWERS



1. When calculating the Estimate at Completion (EAC) assuming the current budget rate will

continue for the remainder of the project, which formula is used?

A. EAC = AC + Bottom-up ETC


B. EAC = AC + (BAC - EV)


C. EAC = AC + [(BAC - EV) / (CPI * SPI)]


D. EAC = BAC / CPI


Answer: D


Conceptual Explanation: The formula EAC = BAC / CPI is used when the current

cumulative CPI is expected to continue until the end of the project.


2. In a weak matrix organization, who typically holds the most power and authority over the

project budget?

A. The Functional Manager


B. The Project Manager


C. The Project Coordinator

,D. The Project Expeditor


Answer: A


Conceptual Explanation: In a weak matrix, the functional manager maintains most of the

authority, including budget control, while the PM acts more as a coordinator or expeditor.


3. Which of the following best describes the ‘100% Rule’ in the context of a Work Breakdown

Structure (WBS)?

A. Every task must be completed 100% before the next begins.


B. The WBS must include 100% of the work defined by the project scope.


C. The project must have a 100% success rate for all deliverables.


D. Resources must be utilized at 100% capacity throughout the project.


Answer: B


Conceptual Explanation: The 100% Rule states that the WBS represents all product and

project work, including project management; the sum of the work at the child levels must

equal 100% of the work represented by the parent.


4. A project manager is using a technique to estimate activity duration by multiplying the

quantity of work by the labor rate. What is this technique called?

A. Analogous Estimating


B. Three-point Estimating


C. Parametric Estimating

, D. Bottom-up Estimating


Answer: C


Conceptual Explanation: Parametric estimating uses a statistical relationship between

historical data and other variables to calculate an estimate for activity parameters.


5. If an activity has an Early Start (ES) of day 5, a Late Start (LS) of day 10, and a duration of 4

days, what is its Total Float?

A. 1 day


B. 5 days


C. 4 days


D. 15 days


Answer: B


Conceptual Explanation: Total Float is calculated as LS - ES (10 - 5 = 5) or LF - EF.


6. Which quality management tool is specifically used to identify the ‘vital few’ problems

compared to the ‘useful many’?

A. Ishikawa Diagram


B. Control Chart


C. Scatter Diagram


D. Pareto Diagram

Document information

Uploaded on
August 19, 2026
Number of pages
24
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Thebright
3.6
(44)
Sold
234
Followers
6
Items
14496
Last sold
3 weeks ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions