1. What is the primary responsibility of a special inspector during construction?
A. Direct the contractor's employees
B. Approve all construction means and methods
C. Verify that inspected work conforms to approved construction documents and
applicable requirements
D. Assume responsibility for the contractor's quality-control program
Answer: C. Verify that inspected work conforms to approved construction
documents and applicable requirements
Rationale: A special inspector provides independent verification of designated
work. The inspector does not direct the contractor's workforce or assume the
contractor's responsibility for construction means, methods, or overall quality
control.
,2. During inspection, a special inspector discovers that installed reinforcing steel
differs from the approved structural drawings. What should the inspector do
first?
A. Direct the ironworkers to remove it
B. Ignore the discrepancy if the difference appears minor
C. Document and report the discrepancy through the established inspection and
reporting process
D. Approve it if the concrete supplier agrees it is adequate
Answer: C. Document and report the discrepancy through the established
inspection and reporting process
Rationale: The special inspector should identify, document, and communicate
nonconforming work. The inspector should not independently authorize
structural design changes unless specifically empowered by the responsible
design authority.
3. Which document normally establishes the required scope of special
inspections for a project?
A. Contractor's daily log
B. Statement of special inspections
C. Material delivery ticket
D. Equipment maintenance record
Answer: B. Statement of special inspections
Rationale: The statement of special inspections identifies the work requiring
special inspection and testing and establishes the applicable inspection
responsibilities.
4. A special inspector observes a potentially serious structural deficiency that
could compromise life safety. What is the most appropriate action?
A. Wait until the end of the project to mention it
B. Immediately communicate the condition to the appropriate responsible parties
,and document it
C. Correct the deficiency personally
D. Delete the observation from the inspection report
Answer: B. Immediately communicate the condition to the appropriate
responsible parties and document it
Rationale: Significant safety-related deficiencies require prompt notification and
documentation. The inspector's role is to identify and report rather than
personally perform corrective construction.
5. Which condition is most important to verify before concrete placement?
A. The contractor's lunch schedule
B. Reinforcement size, spacing, placement, support, and required cover
C. The color of the concrete truck
D. The brand of the contractor's tools
Answer: B. Reinforcement size, spacing, placement, support, and required cover
Rationale: Reinforcement must be properly positioned and supported before
concrete placement because later correction is difficult or impossible.
6. What is the principal purpose of concrete consolidation?
A. Increase water content
B. Remove entrapped air and ensure concrete surrounds reinforcement and
embedded items
C. Reduce cement content
D. Delay setting
Answer: B. Remove entrapped air and ensure concrete surrounds reinforcement
and embedded items
Rationale: Proper consolidation reduces voids and honeycombing and improves
contact between concrete, reinforcement, and embedded components.
, 7. A concrete batch arrives at the site with excessive slump. What should the
inspector primarily verify?
A. Whether unauthorized water was added
B. Whether the driver has a valid license
C. Whether the truck is painted correctly
D. Whether the concrete is delivered before noon
Answer: A. Whether unauthorized water was added
Rationale: Excessive water can adversely affect strength, durability, and other
concrete properties. Any adjustment must comply with the approved mixture
and applicable requirements.
8. Which test is commonly used to evaluate the consistency or workability of
freshly mixed concrete?
A. Slump test
B. Tensile test
C. Ultrasonic thickness test
D. Bend test
Answer: A. Slump test
Rationale: The slump test provides an indication of the consistency of freshly
mixed concrete and is widely used for field quality control and acceptance
procedures.
9. What is the purpose of concrete cylinders made during construction?
A. Determine reinforcing bar diameter
B. Evaluate compressive strength of the concrete
C. Determine soil density
D. Measure steel weld penetration
Answer: B. Evaluate compressive strength of the concrete