Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 109 pages
Exam (elaborations)

MCPPO 2 Design and Construction Contracting Comprehensive Exam – Massachusetts Certified Public Purchasing Official (MCPPO) | Comprehensive Practice Questions & Answers | Design, Construction Contracting & Public Procurement

Document preview thumbnail
Preview 4 out of 109 pages

MCPPO 2 Design and Construction Contracting Comprehensive Exam – Massachusetts Certified Public Purchasing Official (MCPPO) | Comprehensive Practice Questions & Answers | Design, Construction Contracting & Public Procurement

Content preview

1|Page


MCPPO 2 Design and Construction Contracting
Comprehensive Exam – Massachusetts Certified
Public Purchasing Official (MCPPO) | Comprehensive
Practice Questions & Answers | Design, Construction
Contracting & Public Procurement



Description: This comprehensive examination is designed for public
officials seeking MCPPO certification in Design and Construction
Contracting. The exam covers the legal framework of public
construction procurement in Massachusetts under M.G.L. c. 149 and
M.G.L. c. 30, §39M, including prequalification, filed sub-bidding,
bidding procedures, contract administration, change orders, delays,
disputes, prevailing wage compliance, and alternative delivery methods.
Based on the official MCPPO curriculum, this assessment tests both
recall and application-level reasoning expected of competent public
procurement officials .


---


SECTION 1: QUESTIONS 1-50


Question 1
The three distinct stages of the public construction project lifecycle
under Massachusetts procurement law are:

,2|Page


A) Conception, Design, and Construction
B) Planning, Design, and Construction
C) Pre-bid, Bid, and Post-bid
D) Feasibility, Procurement, and Closeout


Answer: B


Rationale: The public construction project lifecycle consists of three
distinct stages: Planning, Design, and Construction. The planning stage
involves defining the project scope, budget, and schedule. The design
stage results in a complete set of plans and specifications. The
construction stage involves the physical building of the project .


---


Question 2
Under M.G.L. c. 149, for building construction projects, you must solicit
filed sub-bids when the work in a filed sub-bid category is estimated to
cost more than:


A) $10,000
B) $25,000
C) $50,000
D) $100,000

,3|Page


Answer: B


Rationale: M.G.L. c. 149 identifies 18 filed sub-bid categories of work.
You must solicit filed sub-bids when the work in a filed sub-bid category
is estimated to cost more than $25,000 .


---


Question 3
Sealed sub-bids must be filed with the awarding authority at least how
many business days before the general bid opening?


A) Two business days
B) Three business days
C) Four and one-half business days
D) Five business days


Answer: C


Rationale: Sealed sub-bids must be filed with the awarding authority at
least four and one-half business days before the general bid opening.
This timing allows for proper review and processing of sub-bids before
the general bid opening .


---

, 4|Page




Question 4
Which of the following MUST be included in an Invitation for Bids
(IFB) under M.G.L. c. 149?


A) Form for General Bid only
B) Complete set of specifications and plans drawn to minimum scale
referencing the required category of work
C) Contractor insurance requirements only
D) Project timeline without specifications


Answer: B


Rationale: Under M.G.L. c. 149, the IFB must include the following:
Form for General Bid, Form for Sub-Bid, complete set of specifications
and plans drawn to minimum scale referencing the required category of
work in which general bidders must be certified by DCAMM, Update
Statement forms, and appropriate reference to the payment of prevailing
wages .


---


Question 5
According to the Attorney General's Office, the minimum notice
required for changes to an IFB (addenda) should be considered as:

Document information

Uploaded on
August 17, 2026
Number of pages
109
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$26.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Sold
12
Followers
0
Items
786
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions