CONSTRUCTION BUSINESS AND FINANCE (36-FL-CN) PRACTICE EXAM
ACTUAL EXAM QUESTIONS WITH CORRECT ANSWERS & EXPLANATIONS
99 QUESTIONS
TABLE OF CONTENTS
# TOPIC
1 Apply financial principles to construction project budgeting, cash flow, and cost control
2 Analyze risk and insurance requirements in the Florida construction environment
3 Evaluate legal and regulatory obligations, including liens, licensing, and safety standards
4 Integrate business strategy with project management for sustainable profitability
5 CN FL Construction Business and FinanceFlorida Construction Business and Finance
6 Practice Exam Actual Exam Questions with Correct Answers & Explanations Graded A+ Study Guide.
7 Foundations of Construction Business and Finance (Florida-specific)
8 Applied Construction Business and Finance (Florida-specific)
9 Advanced Construction Business and Finance (Florida-specific)
10 Construction Business and Finance (Florida-specific) Review
Page 1
,Q1 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A contractor in Florida is preparing a bid for a commercial project with a 24-month
schedule. The project requires a performance bond and a payment bond. The
contractor's surety has a required working capital of 5% of the contract price. The
contract price is $10,000,000. The contractor's current working capital is $400,000.
To meet the surety's requirement, the contractor must increase working capital by
at least:
A. $100,000 CORRECT
B. $200,000
C. $300,000
D. $500,000
RATIONALE: The surety requires working capital equal to 5% of contract price: $10,000,000 *
0.05 = $500,000. The contractor has $400,000, so the shortfall is $100,000. Options B, C, and D
are incorrect because they misapply the percentage or confuse with other bond requirements.
Q2 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
In Florida, a contractor is performing a renovation project and discovers that the
owner has failed to obtain a required building permit. The contractor continues
work without the permit. Which of the following is the most accurate legal
consequence for the contractor?
A. The contractor may be subject to disciplinary action but can still enforce the contract for
payment.
B. The contractor is not liable because permit responsibility lies solely with the owner.
C. The contractor may lose the right to claim a construction lien and may face fines. CORRECT
D. The contractor can cure the issue by retroactively obtaining the permit after work is complete.
RATIONALE: Under Florida law, performing work without a required permit is a violation that can
result in fines and may invalidate lien rights. The contractor shares responsibility for ensuring
permits are obtained. Options A and B are incorrect because the contractor is not insulated from
liability. Option D is incorrect because retroactive permits may not cure all violations.
Page 2
,Q3 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A construction company is evaluating a project with an initial investment of
$500,000. The project is expected to generate net cash flows of $150,000 per year
for 5 years. The company's cost of capital is 10%. What is the net present value
(NPV) of the project? (Round to the nearest dollar.)
A. $58,500
B. $68,500 CORRECT
C. $78,500
D. $88,500
RATIONALE: NPV = -500,000 + 150,000 * [1 - (1.10)^-5] / 0.10 = -500,000 + 150,000 * 3.7908 =
-500,000 + 568,620 = $68,620, rounded to $68,500. Option A uses an incorrect annuity factor, C
and D are miscalculations.
Q4 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A Florida contractor is reviewing a contract with a 'pay-if-paid' clause. The owner
has failed to pay the general contractor, who has not paid the subcontractor. The
subcontractor is seeking payment from the general contractor. Under Florida law,
which of the following is the most accurate statement?
A. The pay-if-paid clause is void as against public policy in Florida.
B. The general contractor must pay the subcontractor within a reasonable time despite the
clause.
C. The pay-if-paid clause is enforceable only if the subcontractor explicitly agreed to it in writing.
D. The general contractor is not required to pay until the owner pays, but must act in good faith
to collect. CORRECT
RATIONALE: Florida courts generally enforce pay-if-paid clauses, but the general contractor
must make reasonable efforts to collect payment from the owner. Options A and B are incorrect
because the clause is not automatically void, and payment is not unconditionally required. Option
C is incorrect because the clause can be in the subcontract without separate explicit agreement.
Page 3
, Q5 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A construction firm is considering a change order that will increase the project's
cost by $50,000 and extend the schedule by 2 weeks. The firm's overhead rate is
10% of direct costs, and profit is 5% of total costs. What is the minimum additional
revenue the firm must receive to maintain its profit margin?
A. $55,000
B. $57,750 CORRECT
C. $60,000
D. $63,000
RATIONALE: Total cost including overhead = $50,000 * 1.10 = $55,000. Profit is 5% of total cost,
so required revenue = $55,000 * 1.05 = $57,750. Options A, C, and D are incorrect because they
either omit overhead or misapply profit percentage.
Q6 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
Which of the following best describes the purpose of a 'waiver of lien' in Florida
construction law?
A. It permanently extinguishes the right to file a lien, regardless of whether payment is made.
B. It releases the owner from liability for payment to the contractor.
C. It is a document that, when signed, may waive lien rights if payment is made, but conditional
waivers are effective only upon actual payment. CORRECT
D. It is a court order that prevents a contractor from filing a lien.
RATIONALE: Florida law distinguishes between conditional and unconditional waivers. A
conditional waiver is effective only upon receipt of payment, while an unconditional waiver takes
effect immediately upon signing, even if payment is not yet made. Option A is incorrect because
unconditional waivers can be used, but conditional waivers are common. Options B and D are
incorrect because waivers do not release liability or require court action.
Page 4