Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 62 pages
Exam (elaborations)

Florida Construction Business and Finance Practice Exam

Document preview thumbnail
Preview 4 out of 62 pages

A practice exam for Florida Construction Business and Finance (36-FL-CN) covering financial principles, risk management, legal obligations, and business strategy. Includes 99 questions with answers and explanations, focusing on budgeting, cash flow, cost control, liens, permits, and insurance.

Content preview

36-FL-CN FL CONSTRUCTION BUSINESS AND FINANCEFLORIDA
CONSTRUCTION BUSINESS AND FINANCE (36-FL-CN) PRACTICE EXAM
ACTUAL EXAM QUESTIONS WITH CORRECT ANSWERS & EXPLANATIONS
99 QUESTIONS




TABLE OF CONTENTS

# TOPIC

1 Apply financial principles to construction project budgeting, cash flow, and cost control

2 Analyze risk and insurance requirements in the Florida construction environment

3 Evaluate legal and regulatory obligations, including liens, licensing, and safety standards

4 Integrate business strategy with project management for sustainable profitability

5 CN FL Construction Business and FinanceFlorida Construction Business and Finance

6 Practice Exam Actual Exam Questions with Correct Answers & Explanations Graded A+ Study Guide.

7 Foundations of Construction Business and Finance (Florida-specific)

8 Applied Construction Business and Finance (Florida-specific)

9 Advanced Construction Business and Finance (Florida-specific)

10 Construction Business and Finance (Florida-specific) Review




Page 1

,Q1 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A contractor in Florida is preparing a bid for a commercial project with a 24-month
schedule. The project requires a performance bond and a payment bond. The
contractor's surety has a required working capital of 5% of the contract price. The
contract price is $10,000,000. The contractor's current working capital is $400,000.
To meet the surety's requirement, the contractor must increase working capital by
at least:
A. $100,000 CORRECT

B. $200,000

C. $300,000

D. $500,000

RATIONALE: The surety requires working capital equal to 5% of contract price: $10,000,000 *
0.05 = $500,000. The contractor has $400,000, so the shortfall is $100,000. Options B, C, and D
are incorrect because they misapply the percentage or confuse with other bond requirements.




Q2 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
In Florida, a contractor is performing a renovation project and discovers that the
owner has failed to obtain a required building permit. The contractor continues
work without the permit. Which of the following is the most accurate legal
consequence for the contractor?
A. The contractor may be subject to disciplinary action but can still enforce the contract for
payment.

B. The contractor is not liable because permit responsibility lies solely with the owner.

C. The contractor may lose the right to claim a construction lien and may face fines. CORRECT

D. The contractor can cure the issue by retroactively obtaining the permit after work is complete.

RATIONALE: Under Florida law, performing work without a required permit is a violation that can
result in fines and may invalidate lien rights. The contractor shares responsibility for ensuring
permits are obtained. Options A and B are incorrect because the contractor is not insulated from
liability. Option D is incorrect because retroactive permits may not cure all violations.




Page 2

,Q3 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A construction company is evaluating a project with an initial investment of
$500,000. The project is expected to generate net cash flows of $150,000 per year
for 5 years. The company's cost of capital is 10%. What is the net present value
(NPV) of the project? (Round to the nearest dollar.)
A. $58,500

B. $68,500 CORRECT

C. $78,500

D. $88,500

RATIONALE: NPV = -500,000 + 150,000 * [1 - (1.10)^-5] / 0.10 = -500,000 + 150,000 * 3.7908 =
-500,000 + 568,620 = $68,620, rounded to $68,500. Option A uses an incorrect annuity factor, C
and D are miscalculations.




Q4 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A Florida contractor is reviewing a contract with a 'pay-if-paid' clause. The owner
has failed to pay the general contractor, who has not paid the subcontractor. The
subcontractor is seeking payment from the general contractor. Under Florida law,
which of the following is the most accurate statement?
A. The pay-if-paid clause is void as against public policy in Florida.

B. The general contractor must pay the subcontractor within a reasonable time despite the
clause.

C. The pay-if-paid clause is enforceable only if the subcontractor explicitly agreed to it in writing.

D. The general contractor is not required to pay until the owner pays, but must act in good faith
to collect. CORRECT

RATIONALE: Florida courts generally enforce pay-if-paid clauses, but the general contractor
must make reasonable efforts to collect payment from the owner. Options A and B are incorrect
because the clause is not automatically void, and payment is not unconditionally required. Option
C is incorrect because the clause can be in the subcontract without separate explicit agreement.




Page 3

, Q5 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
A construction firm is considering a change order that will increase the project's
cost by $50,000 and extend the schedule by 2 weeks. The firm's overhead rate is
10% of direct costs, and profit is 5% of total costs. What is the minimum additional
revenue the firm must receive to maintain its profit margin?
A. $55,000

B. $57,750 CORRECT

C. $60,000

D. $63,000

RATIONALE: Total cost including overhead = $50,000 * 1.10 = $55,000. Profit is 5% of total cost,
so required revenue = $55,000 * 1.05 = $57,750. Options A, C, and D are incorrect because they
either omit overhead or misapply profit percentage.




Q6 APPLY FINANCIAL PRINCIPLES TO CONSTRUCTION PROJECT BUDGETING, CASH
FLOW, AND COST CONTROL
Which of the following best describes the purpose of a 'waiver of lien' in Florida
construction law?
A. It permanently extinguishes the right to file a lien, regardless of whether payment is made.

B. It releases the owner from liability for payment to the contractor.

C. It is a document that, when signed, may waive lien rights if payment is made, but conditional
waivers are effective only upon actual payment. CORRECT

D. It is a court order that prevents a contractor from filing a lien.

RATIONALE: Florida law distinguishes between conditional and unconditional waivers. A
conditional waiver is effective only upon receipt of payment, while an unconditional waiver takes
effect immediately upon signing, even if payment is not yet made. Option A is incorrect because
unconditional waivers can be used, but conditional waivers are common. Options B and D are
incorrect because waivers do not release liability or require court action.




Page 4

Document information

Uploaded on
August 16, 2026
Number of pages
62
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$28.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GoldenExams
4.6
(65)
Sold
24
Followers
17
Items
500
Last sold
7 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions