300 Original Practice Questions with Marked
Answers & Rationales
Topics: project delivery • contracts • CPM • scheduling • procurement • cost control • changes •
quality • safety • risk • claims • documentation • closeout
Independent practice material — not an official NYC DCAS publication Page 1
, 1. A public owner wants one entity to take responsibility for both design coordination and
constructionexecution. Which delivery method best fits?
A. Design-Bid-Build
B. Design-Build ✓ CORRECT ANSWER
C. Multiple Prime Contracting
D. Construction Manager as Advisor
Rationale: Design-Build places design and construction responsibility under one contractual entity, reducing owner
coordination between separate design and construction contracts.
2. A contractor discovers an undocumented underground utility that materially affects excavation.
Whatshould the project manager do first?
A. Immediately approve extra payment
B. Direct the contractor to absorb the cost
C. Review contract provisions, site information, and available evidence ✓ CORRECT ANSWER D. Terminate the
contractor
Rationale: The entitlement question must be evaluated against the contract, site information, differing-site-condition
provisions, and documented facts before compensation is determined.
3. The primary purpose of Critical Path Method scheduling is to:
A. Eliminate all project risk
B. Determine labor rates
C. Identify activities controlling the completion date ✓ CORRECT ANSWER
D. Calculate contractor profit
Rationale: CPM identifies the sequence of schedule-sensitive activities that controls project completion and helps
management focus attention on critical work.
4. Which document most directly establishes the contractual scope and obligations between owner
andcontractor?
A. Daily report
B. Meeting agenda
C. Shop drawing
D. Construction contract documents ✓ CORRECT ANSWER
Rationale: The contract documents collectively define scope, specifications, drawings, conditions, responsibilities, and
other contractual requirements.
5. A noncritical activity uses all of its available float but the project finish date is unchanged. What
doesthis indicate?
A. Immediate project failure
B. Automatic contractor default
C. Reduced schedule flexibility ✓ CORRECT ANSWER
D. Automatic entitlement to a time extension
Independent practice material — not an official NYC DCAS publication Page 2
, Rationale: When float is consumed, the activity has less flexibility. Future delays can more easily affect the critical path.
6. A formal change order is generally appropriate when:
A. A contractor voluntarily hires more workers
B. Minor market prices fluctuate
C. Authorized scope, price, or time must be changed ✓ CORRECT ANSWER
D. The manager wants cleaner notes
Rationale: A change order formally modifies contractual requirements such as scope, compensation, schedule, or other
agreed terms.
7. A key public procurement principle is:
A. Restricting competition to preferred firms
B. Selecting only by experience
C. Using informal quotations for every project
D. Promoting fair competition and best value consistent with law ✓ CORRECT ANSWER
Rationale: Public procurement generally emphasizes fairness, competition, transparency, compliance, and responsible use
of public funds.
8. A submittal is returned with comments requiring revision. What should the contractor generally do?
A. Ignore the comments
B. Revise and resubmit as required ✓ CORRECT ANSWER
C. Start fabrication immediately
D. Delete the submittal from the project record
Rationale: A returned submittal with required revisions should be addressed and resubmitted through the established
submittal process.
9. What is the main purpose of a project baseline schedule?
A. To replace the contract
B. To establish the approved reference for measuring schedule performance ✓ CORRECT ANSWER
C. To guarantee no delays occur
D. To determine employee salaries
Rationale: The baseline provides the approved reference against which actual progress, delays, and forecast completion
can be evaluated.
10. Which activity is most likely to be critical in a CPM network?
A. An activity with large total float
B. An activity with zero or near-zero total float ✓ CORRECT ANSWER
C. An activity that is already completeD. An activity with no predecessor
Rationale: Critical activities generally have zero or very limited float and directly influence the planned completion date.
Independent practice material — not an official NYC DCAS publication Page 3
, 11. A contractor submits an invoice for work not supported by field records. What is the best initial action?
A. Pay it automatically
B. Reject all future invoices
C. Verify quantities and supporting documentation ✓ CORRECT ANSWER
D. Increase the contract value
Rationale: Payment review should be based on documented, measurable, and contractually eligible work.
12. Why are daily construction reports important?
A. They replace the contract
B. They provide contemporaneous records of site conditions and activities ✓ CORRECT ANSWER
C. They guarantee payment
D. They eliminate inspections
Rationale: Daily reports create a contemporaneous record of manpower, equipment, weather, work performed, visitors,
issues, and other project events.
13. A request for information (RFI) is primarily used to:
A. Authorize final payment
B. Seek clarification of contract documents ✓ CORRECT ANSWER
C. Replace the contractor's schedule
D. Set employee wages
Rationale: An RFI provides a controlled method for obtaining clarification when drawings, specifications, or other contract
information is unclear or conflicting.
14. Which document typically shows the contractor's planned sequence and timing of work?
A. Schedule ✓ CORRECT ANSWER
B. Purchase order receipt
C. Safety poster
D. Warranty certificate
Rationale: The project schedule communicates planned activity sequence, durations, milestones, logic, and forecast
dates.
15. A project manager notices repeated late submittals. What is the most effective management response?
A. Ignore the pattern
B. Document the issue and address its root cause and contractual impact ✓ CORRECT ANSWER
C. Cancel the project
D. Approve all submittals without review
Rationale: Repeated late submittals should be documented, analyzed for cause and impact, and addressed through
project controls and contract procedures.
16. What does schedule float represent?
Independent practice material — not an official NYC DCAS publication Page 4