◉ AHJ - Authorities Having Jurisdiction.
Answer: Protect public health, safety and welfare


◉ Design Team.
Answer: Address planning issues, determine design program,
identify codes and regulations, produce procurement and
construction documents, administer construction contract, *provide
QA/QC procedures*


◉ Contractor Team.
Answer: Entity that constructs a facility. Uses management abilities
to gather labor forces, subs, and material/product/equipment
suppliers


◉ Supplier Team.
Answer: Furnishes the materials and products for the facility to be
constructed. Fabricator, Distributor, Manufacturer, Supplier.


◉ Facility Life Cycle.

,Answer: The life cycle of a facility, from concept through
construction to use and eventual deconstruction.
Project Conception
Project Delivery
Design
Construction Documents
Procurement (Bidding/Negotiating/Purchasing)
Construction
Facility Management


◉ Project Conception.
Answer: Transforms the needs of owner into clear concept on which
project can be designed. Feasibility Study, Programming, Site
Selection, Budgeting.


◉ Project Delivery.
Answer: Determine delivery method to be used. Factors -
qualifications, experience, capacity, project extent, time
requirements.


◉ Design.
Answer: Two Phases: schematic design and design development.
Deliverables include graphic and written design documents and
estimates of project cost.

,◉ Schematic Design.
Answer: Overall relationships and functions. Site plan and area,
general size/shape/massing of elements, elevations and exteriors
established, conceptual design criteria identified.
Deliverables - schematic drawings, probable cost, preliminary
schedules


◉ Design Development.
Answer: Technical issues of constructibility and integration of
systems and components.
Deliverables - Tech information, outline specifications, updated
schedule, updated cost estimate.


◉ Construction Documents.
Answer: Defined as the written and graphic documents prepared or
assembled by the A/E for communicating the project design for
construction and administering the construction contract.
Construction documents include two major types of documents:
Procurement documents and Contract documents.


◉ Procurement (Bidding/Negotiating/Purchasing).
Answer: Acceptance of the contractor's bid or negotiated sum and
other conditions will result in award of a contract and
commencement of work.

, ◉ Construction.
Answer: Responsibilities:
Contractor - perform work, project coordination, comply with
project documents.
A/E - construction admin, evaluation services, certify application for
payment, final inspection of work.
Owner - provide information, process payments, approve contract
modifications, accept project upon completion.


◉ Facility Management.
Answer: During occupancy, owners & facility managers maintain
and evaluate the performance of the project and determine
suitability for continuing use.


◉ OmniClass.
Answer: A multi-table informational framework for organizing
information used by the architectural, engineering, and construction
industry.


◉ UniFormat.
Answer: Uniform classification system for organizing preliminary
construction information into a standard order or sequence on the

Document information

Uploaded on
August 16, 2026
Number of pages
36
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$17.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TopGradeInsider
4.2
(12)
Sold
144
Followers
1
Items
51004
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions