• Scheduling:
3 steps in creating a schedule -✓✓ 1. ID activities
2. Estimate activity durations
3. Determine the sequence
• Scheduling:
FF vs. TF -✓✓ FF - time an activity can be delayed w/o delaying ES of successor
TF - time an activity can be delayed w/o delaying project
• Scheduling:
3 common schedule analysis techniques -✓✓ - Precedence diagramming method
- Critical path method
- PERT & EVM
• Construction Mgmt:
Who's role is quality control vs quality assurance? -✓✓ QC - Contractor
QA - CO/PM/Inspector
• Design Process, Reviews, Guidance:
Steps in design process -✓✓ Planning
Programming
Design
Construction
Operations
• Design Process, Reviews, Guidance:
What are the products developed from each design process? -✓✓ Requirements
Analysis - prgm req's
Conceptual Design - bubble diagrams
Schematic Design - schematic floor plans
Design Development - scaled floor plan
, Pre-final Design & Details - Full construction sheet
• Design Process, Reviews, Guidance:
List 4 types of design reviews & their reviewer -✓✓ Functional - User
Technical - ?
Maintainability - Ops flight
Constructability - PM/ QA team
• Design Process, Reviews, Guidance:
What design criteria is the highest DoD guidance? -✓✓ Unified Facilities Criteria (UFC)
• Design Process, Reviews, Guidance:
What do codes do? -✓✓ Provide minimum requirements to protect occupants and public
• Design Process, Reviews, Guidance:
What 3 aspects does code seek to protect? -✓✓ Health
Safety
General Welfare
• Design Process, Reviews, Guidance:
List hierarchy of military construction codes -✓✓ DoD Reqs - UFC, UFGS
USAF Reqs - AFI, AFMAN, TO, ETL, Playbook
USAF Guidance - AFH, AFDG, AFPAM
• Design Process, Reviews, Guidance:
Where do you start when finding applicable code? -✓✓ UFC 1-200-01
• Design Process, Reviews, Guidance:
What is code applicability based on? -✓✓ Construction start date (most of time)
• Contracting Fundamentals:
The contracting officer is the sole person who can: -✓✓ 1. Award a Govt contract
2. Administer or modify a contract
3. Terminate a contract
UPDATED ACTUAL Exam | Detailed Solutions
• Scheduling:
3 steps in creating a schedule -✓✓ 1. ID activities
2. Estimate activity durations
3. Determine the sequence
• Scheduling:
FF vs. TF -✓✓ FF - time an activity can be delayed w/o delaying ES of successor
TF - time an activity can be delayed w/o delaying project
• Scheduling:
3 common schedule analysis techniques -✓✓ - Precedence diagramming method
- Critical path method
- PERT & EVM
• Construction Mgmt:
Who's role is quality control vs quality assurance? -✓✓ QC - Contractor
QA - CO/PM/Inspector
• Design Process, Reviews, Guidance:
Steps in design process -✓✓ Planning
Programming
Design
Construction
Operations
• Design Process, Reviews, Guidance:
What are the products developed from each design process? -✓✓ Requirements
Analysis - prgm req's
Conceptual Design - bubble diagrams
Schematic Design - schematic floor plans
Design Development - scaled floor plan
, Pre-final Design & Details - Full construction sheet
• Design Process, Reviews, Guidance:
List 4 types of design reviews & their reviewer -✓✓ Functional - User
Technical - ?
Maintainability - Ops flight
Constructability - PM/ QA team
• Design Process, Reviews, Guidance:
What design criteria is the highest DoD guidance? -✓✓ Unified Facilities Criteria (UFC)
• Design Process, Reviews, Guidance:
What do codes do? -✓✓ Provide minimum requirements to protect occupants and public
• Design Process, Reviews, Guidance:
What 3 aspects does code seek to protect? -✓✓ Health
Safety
General Welfare
• Design Process, Reviews, Guidance:
List hierarchy of military construction codes -✓✓ DoD Reqs - UFC, UFGS
USAF Reqs - AFI, AFMAN, TO, ETL, Playbook
USAF Guidance - AFH, AFDG, AFPAM
• Design Process, Reviews, Guidance:
Where do you start when finding applicable code? -✓✓ UFC 1-200-01
• Design Process, Reviews, Guidance:
What is code applicability based on? -✓✓ Construction start date (most of time)
• Contracting Fundamentals:
The contracting officer is the sole person who can: -✓✓ 1. Award a Govt contract
2. Administer or modify a contract
3. Terminate a contract