CQM-C Certification Exam
Construction Quality Management for
Contractors Comprehensive
Questions (Frequently Tested) and
Complete Solutions Graded A+
The ______ consists of daily checks of the work to assure continuing
compliance with contract requirements - Answer: Follow-up phase
Design-Build contracts require: - Answer: *The QC Manager to be in
place and take an active role in the review and coordination of the
design*
Which of the following is included in all three phases of the Three
Phases of Control - Answer: Safety
The purpose of Construction Quality Management is to - Answer:
*Achieve the quality established by properly developed requirements
through the combined responsibility, but separate, efforts of contractor
and Government personnel*
Testing is extremely important in Construction Quality Management
and is performed by - Answer: Both the contractor and the
Government
, The primary purpose of the Three-Phase Control System is to: - Answer:
Require the contractor to plan, schedule, and perform quality
management actions to assure work meets all specified quality
standards
Quality Assurance Personnel have the responsibility to: - Answer:
*require the contractor to maintain the quality specified in the plans
and specifications*
the ____ is the appropriate time to assure that all materials and/or
equipment have been tested. submitted, and approved. - Answer:
Preparatory Phase
The Preconstruction Conference and the Coordination and Mutual
Understanding Meeting are: - Answer: conducted prior to the
commencement of any physical construction work
Contractor testing procedures: - Answer: are specified in the technical
specifications, outlined in the Quality Control Plan, and addressed at
the Coordination and Mutual Understanding Meeting.
The Quality Control Plan contains: - Answer: Identification of individual
quality control personnel, including name, qualifications, assigned
duties, responsibilities and authorities
Construction Quality Management for
Contractors Comprehensive
Questions (Frequently Tested) and
Complete Solutions Graded A+
The ______ consists of daily checks of the work to assure continuing
compliance with contract requirements - Answer: Follow-up phase
Design-Build contracts require: - Answer: *The QC Manager to be in
place and take an active role in the review and coordination of the
design*
Which of the following is included in all three phases of the Three
Phases of Control - Answer: Safety
The purpose of Construction Quality Management is to - Answer:
*Achieve the quality established by properly developed requirements
through the combined responsibility, but separate, efforts of contractor
and Government personnel*
Testing is extremely important in Construction Quality Management
and is performed by - Answer: Both the contractor and the
Government
, The primary purpose of the Three-Phase Control System is to: - Answer:
Require the contractor to plan, schedule, and perform quality
management actions to assure work meets all specified quality
standards
Quality Assurance Personnel have the responsibility to: - Answer:
*require the contractor to maintain the quality specified in the plans
and specifications*
the ____ is the appropriate time to assure that all materials and/or
equipment have been tested. submitted, and approved. - Answer:
Preparatory Phase
The Preconstruction Conference and the Coordination and Mutual
Understanding Meeting are: - Answer: conducted prior to the
commencement of any physical construction work
Contractor testing procedures: - Answer: are specified in the technical
specifications, outlined in the Quality Control Plan, and addressed at
the Coordination and Mutual Understanding Meeting.
The Quality Control Plan contains: - Answer: Identification of individual
quality control personnel, including name, qualifications, assigned
duties, responsibilities and authorities