PROJECT MANAGEMENT THE
MANAGERIAL PROCESS EXAM SCRIPT
SOLVED QUESTIONS ACCURATE ANSWER
COLLECTION
●● What is created when project costs are placed in a time schedule
depicting when they are to occur?
A. project cost baseline
B. project network
C. risk management plan
D. contingency plan
Answer: A
●● What project management tool/method is suggested to determine the
customer's opinion of a project being time or resource constrained?
A. risk management plant
B. project priority matrix
C. project scope
D. work breakdown structure
Answer: B
,●● What do resource allocation methods seek to improve for a time
constrained project?
A. minimization of resource cost
B. utilization of resources
C. resource scheduling conflicts
D. risk management plans
E. project scope
Answer: B
●● what tool allows project management software to handle a
multiproject environment by prioritizing resource allocation to specific
projects?
A. risk management plans
B. work breakdown structure numbering systems
C. project priority number rankings
D. project priority matrix
Answer: C
●● Which of the following is NOT a potential consequence of failing to
identify limited resources before project implementation?
, A. Difficulty in taking quick corrective action
B. Increase costs
C. Activity delays
D. Scope creep
E. Project delays
Answer: D
●● Splitting an activity can result in all of the following EXCEPT
A resource being moved from one activity to another and then back.
B. A better project schedule.
C. Possible startup and shutdown costs.
D. More people working on the same activity.
E. Activity work being placed on hold for a period until more resources
are available.
Answer: D
●● Gene is trying to order the concrete needed to continue his project.
However, the supplier will not be able to deliver it until next week. This
is an example of what kind of resource constraint?
A. Equipment
MANAGERIAL PROCESS EXAM SCRIPT
SOLVED QUESTIONS ACCURATE ANSWER
COLLECTION
●● What is created when project costs are placed in a time schedule
depicting when they are to occur?
A. project cost baseline
B. project network
C. risk management plan
D. contingency plan
Answer: A
●● What project management tool/method is suggested to determine the
customer's opinion of a project being time or resource constrained?
A. risk management plant
B. project priority matrix
C. project scope
D. work breakdown structure
Answer: B
,●● What do resource allocation methods seek to improve for a time
constrained project?
A. minimization of resource cost
B. utilization of resources
C. resource scheduling conflicts
D. risk management plans
E. project scope
Answer: B
●● what tool allows project management software to handle a
multiproject environment by prioritizing resource allocation to specific
projects?
A. risk management plans
B. work breakdown structure numbering systems
C. project priority number rankings
D. project priority matrix
Answer: C
●● Which of the following is NOT a potential consequence of failing to
identify limited resources before project implementation?
, A. Difficulty in taking quick corrective action
B. Increase costs
C. Activity delays
D. Scope creep
E. Project delays
Answer: D
●● Splitting an activity can result in all of the following EXCEPT
A resource being moved from one activity to another and then back.
B. A better project schedule.
C. Possible startup and shutdown costs.
D. More people working on the same activity.
E. Activity work being placed on hold for a period until more resources
are available.
Answer: D
●● Gene is trying to order the concrete needed to continue his project.
However, the supplier will not be able to deliver it until next week. This
is an example of what kind of resource constraint?
A. Equipment