1. Which party generally has authority to issue a building permit for a
residential project within a municipality that administers its own building
program?
A. The state legislature
B. The local building department
C. The county assessor
D. The property owner
Answer: B. The local building department
Rationale: The local building department is generally responsible for
administering permits and inspections when the municipality has adopted and
enforces its own building regulations.
2. Before beginning construction that requires a permit, what should a
residential contractor generally do?
A. Begin excavation immediately
B. Obtain the required permit
,C. Wait until the framing inspection
D. Obtain approval from the property tax assessor
Answer: B. Obtain the required permit
Rationale: Required permits should generally be secured before covered
construction begins so the work can be reviewed for compliance.
3. Who is typically responsible for ensuring that permitted residential work
complies with the adopted building code?
A. The contractor
B. The utility company only
C. The mortgage lender
D. The real estate agent
Answer: A. The contractor
Rationale: Contractors are responsible for performing work in accordance with
applicable codes, approved plans, permits, and local requirements.
4. What is the primary purpose of a building permit?
A. To establish property ownership
B. To authorize regulated construction and provide code oversight
C. To determine the property's market value
D. To eliminate the need for inspections
Answer: B. To authorize regulated construction and provide code oversight
Rationale: Permits provide governmental authorization for regulated work and
allow inspections to verify compliance.
5. A contractor discovers that the approved plans conflict with field
conditions. What is the best course of action?
A. Ignore the plans
B. Proceed without documentation
,C. Contact the design professional or authority having jurisdiction as appropriate
D. Remove the conflicting construction immediately
Answer: C. Contact the design professional or authority having jurisdiction as
appropriate
Rationale: Conflicts should be resolved through the proper design and approval
process rather than through undocumented field changes.
6. What does AHJ commonly stand for in construction regulation?
A. Authorized Housing Judge
B. Authority Having Jurisdiction
C. Approved Housing Jurisdiction
D. Administrative Home Jurisdiction
Answer: B. Authority Having Jurisdiction
Rationale: AHJ refers to the governmental agency or official responsible for
enforcing applicable codes and regulations.
7. Which document normally identifies the scope and requirements of
permitted construction?
A. Approved construction plans
B. Property tax statement
C. Sales receipt
D. Insurance advertisement
Answer: A. Approved construction plans
Rationale: Approved plans communicate design requirements and provide the
basis for plan review and inspections.
8. What should a contractor do if work has been installed contrary to
approved plans?
, A. Conceal the work
B. Request an appropriate correction or approved revision
C. Continue construction without notifying anyone
D. Destroy the inspection records
Answer: B. Request an appropriate correction or approved revision
Rationale: Nonconforming work should be corrected or formally addressed
through the applicable approval process.
9. What is generally required before a final certificate of occupancy can be
issued when one is required?
A. Completion of applicable inspections and compliance requirements
B. Payment of the contractor's employees
C. Sale of the property
D. Removal of all construction documents
Answer: A. Completion of applicable inspections and compliance requirements
Rationale: Final approval generally depends on satisfactory completion of
required inspections and compliance with applicable regulations.
10.What is the primary purpose of residential inspections?
A. To determine the contractor's profit
B. To verify compliance with applicable requirements
C. To establish the property's resale price
D. To select subcontractors
Answer: B. To verify compliance with applicable requirements
Rationale: Inspections provide official verification that regulated construction
complies with adopted requirements.
11.Which construction stage is commonly inspected before framing is
concealed?