1. The lean ratio of an extension ladder 4:1
2. According to AHERA, to complete a response action of 5 samples taken inside
a non-NESHAP size project, how many samples must with results of each <0.0
be taken with results of what? f/cc
3. What are the notification requirements in Virginia? 20 calendar days for any
project greater than 10 sq
feet or linear feet
4. In what jurisdiction do individuals need an asbestos Need a license everywhere
supervisor or working linsense
5. Type of bond that would ensure that the general con- Performance Bond
tractor will compensate subcontractors for labor and
materials
6. Minimum respiratory protection on a class 1 asbestos Full face air purifying res-
project with no NEA pirator
7. What is the maximum content permitted in the work 23.5%
area where an air purifying respirator is being worn?
8. Chest XRays must be evaluated by what class reader? Class B
9. What is the APF for a full face air purifying respirator 50
10. Friable ACM is any material that can be: Crushed, pulverized, re-
duced to powder by hand
pressure when dry
11. The OSHA permissible exposure limit is 0.1 f/cc over 8 hours TWA
12.
1/8
, Maryland Asbestos exam
Maryland Asbestos exam
Study online at https://quizlet.com/_84xmf5
According to ASHERA, how many air samples must be 13 samples (5 inside, 5
taken for final clearance for NESHAP size project? outside, 2 fields blanks ,
one sealed blank)TEM
13. Laboratories that perform PLM and TEM must be ac- National Voluntary Labo-
credited by ratory Accreditation Pro-
gram
14. AHERA is for Public schools K-12
15. What is the notification requirement for asbestos pro- 10 working days prior to
jects in DC start NESHAP size projects
and any project over 18
square feet of flooring.
Building owner to notify
tenants no less than 30
days prior to start of the
project in writing
16. What is a NESHAP sized project 160 square feet, 260 linear
feet, or 35 cubic feet
17. The competent person must inspect the work suits of Once a shift
the crew at least:
18. In Maryland, the asbestos project notification must be Three days prior to any as-
posted when and where? bestos project, at all en-
trances and exits from the
work site.
19. NESHAP regulations provide definitions for Renovations, Adequately
Wet, and Demolitions
20. The definition of PACM is