FDNYC G60 EXAM PREP VERIFIED
QUESTIONS AND ANSWERS
COMPREHENSIVE REVIEW SHEET
●● The person conducting the fire watch ______ have other duties
Answer: CANNOT
●● A portable fire extinguisher with a rating of _________ is required
and should be within ____ feet travel distance hot work area
Answer: 2-A:20-B:C///30
●● For ROOFING OPERATIONS, a portable fire extinguisher with a
minimum rating of ______ is required
Answer: 3-A:40-B:C
●● Fire watch on floors below is ______
Answer: required
●● The fire watch must continue for a minimum of ____ minutes after
the hot work is done
Answer: 30
, ●● For any CNG or LPG torch operations, the first inspection shall be
conducted ___ minutes after completion. The second inspection shall be
conducted _______ after completion of torch operations.
Answer: 30 min///1 hour
●● The fire guard or fire watch personnel must complete a signed
inspection report and it must be submitted to and retained by the person
in charge of the torch operations.
Answer: The report must be made available and maintained on the
premises for a minimum of 48 hours after the work is complete.
●● Most common fuel gasses used in blowtorches are ______
Answer: LPG (butane, propane) natural gas (methane) (either CNG or
piped natural gasses)
●● Soldering and brazing temperatures are typically______
Answer: 840 degrees F
●● Oxy-acetylene generates the highest temperature which can reach up
to _____
Answer: 6000 degrees F
●● Gas torches can exceed _________ and are used for burning weeds,
melting ice, or applying tar to a roof
QUESTIONS AND ANSWERS
COMPREHENSIVE REVIEW SHEET
●● The person conducting the fire watch ______ have other duties
Answer: CANNOT
●● A portable fire extinguisher with a rating of _________ is required
and should be within ____ feet travel distance hot work area
Answer: 2-A:20-B:C///30
●● For ROOFING OPERATIONS, a portable fire extinguisher with a
minimum rating of ______ is required
Answer: 3-A:40-B:C
●● Fire watch on floors below is ______
Answer: required
●● The fire watch must continue for a minimum of ____ minutes after
the hot work is done
Answer: 30
, ●● For any CNG or LPG torch operations, the first inspection shall be
conducted ___ minutes after completion. The second inspection shall be
conducted _______ after completion of torch operations.
Answer: 30 min///1 hour
●● The fire guard or fire watch personnel must complete a signed
inspection report and it must be submitted to and retained by the person
in charge of the torch operations.
Answer: The report must be made available and maintained on the
premises for a minimum of 48 hours after the work is complete.
●● Most common fuel gasses used in blowtorches are ______
Answer: LPG (butane, propane) natural gas (methane) (either CNG or
piped natural gasses)
●● Soldering and brazing temperatures are typically______
Answer: 840 degrees F
●● Oxy-acetylene generates the highest temperature which can reach up
to _____
Answer: 6000 degrees F
●● Gas torches can exceed _________ and are used for burning weeds,
melting ice, or applying tar to a roof