QUESTION 1
Which of the following best describes the primary function of a
photovoltaic inverter in a grid-tied solar energy system?
A) To convert direct current electricity from the solar panels into
alternating current electricity compatible with the utility grid.
B) To step up the voltage of the solar array to match the battery bank
voltage.
C) To track the maximum power point of the solar array and convert AC
to DC for storage.
D) To disconnect the solar array from the grid during low irradiance
conditions.
Answer: A
Explanation: The primary function of a photovoltaic inverter in a grid-
tied system is to convert the DC output of the solar panels into AC
electricity that matches the utility grid's voltage, frequency, and phase
,2|Page
characteristics. Option B describes a charge controller or DC-DC
converter, not a grid-tie inverter. Option C inaccurately describes
maximum power point tracking and reverses the conversion direction.
Option D describes an anti-islanding protection feature, which is a
secondary function, not the primary conversion role.
QUESTION 2
When designing a ground-mounted solar array, what is the minimum
recommended vertical clearance between the lowest part of the array
and the ground surface, assuming standard residential installation?
A) 6 inches
B) 12 inches
C) 24 inches
D) 36 inches
Answer: C
Explanation: The Uniform Building Code and standard installation best
practices typically require a minimum of 24 inches (2 feet) of clearance
between the bottom of a ground-mounted solar array and the ground.
This clearance allows for adequate airflow beneath the panels to
prevent heat buildup, reduces the risk of shading from vegetation,
provides access for maintenance, and mitigates potential damage from
snow accumulation. Six inches is insufficient for airflow; 12 inches is
marginal; 36 inches may be specified in some jurisdictions for high snow
load regions.
,3|Page
QUESTION 3
In a series-connected photovoltaic string, which of the following
electrical parameters increases additively?
A) Current only
B) Voltage only
C) Both voltage and current
D) Neither voltage nor current
Answer: B
Explanation: When photovoltaic modules are connected in series, the
output voltages add together while the current remains constant at the
level of the lowest-performing module in the string. This is a
fundamental principle of electrical circuits: series connections produce
additive voltages. Option A is incorrect because current does not add in
series; option C is false; option D is incorrect as voltage does indeed
increase.
QUESTION 4
The term "irradiance" in solar energy terminology refers to which of the
following?
A) The total energy produced by a solar panel over a 24-hour period.
B) The power density of solar radiation incident on a surface, measured
in watts per square meter.
C) The efficiency of a solar cell in converting sunlight to electricity.
D) The spectral distribution of sunlight at sea level.
, 4|Page
Answer: B
Explanation: Irradiance is the instantaneous measure of solar power
density, expressed in watts per square meter (W/m²), representing the
amount of solar electromagnetic energy striking a given surface area at
a specific moment. Option A describes energy yield over time. Option C
describes conversion efficiency. Option D describes spectral content, not
power density.
QUESTION 5
Which of the following National Electrical Code (NEC) articles
specifically addresses photovoltaic systems?
A) Article 690
B) Article 700
C) Article 250
D) Article 310
Answer: A
Explanation: Article 690 of the National Electrical Code is specifically
titled "Solar Photovoltaic Systems" and contains comprehensive
requirements for the installation of PV systems, including sizing,
protection, disconnecting means, and wiring methods. Article 700
addresses emergency systems; Article 250 covers grounding and
bonding; Article 310 addresses conductor ampacity.