• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 2 out of 10 pages
Exam (elaborations)

STUDIO 2 - ESTIMATING EXAM 2026 UPDATE QUESTINS AND CORRECT VERIFIED ANSWERS ALREADY GRADED A+ (BRAND NEW VISION)

Document preview thumbnail
Preview 2 out of 10 pages

STUDIO 2 - ESTIMATING EXAM 2026 UPDATE QUESTINS AND CORRECT VERIFIED ANSWERS ALREADY GRADED A+ (BRAND NEW VISION)

Content preview

STUDIO 2 - ESTIMATING EXAM 2026
UPDATE QUESTINS AND CORRECT
VERIFIED ANSWERS ALREADY GRADED
A+ (BRAND NEW VISION)

The average end area method of quantifying cut and fill is often used when dealing with
long, narrow tracks, such as roads. In this method, the site is divided into stations.
Station 00 + 00 is the beginning, and station 01 + 75 means 75 feet from the beginning
station - ANS-False

6 inches of topsoil is to be removed and stockpiled for the building in the following
picture. The topsoil is to be removed 8 feet back from the perimeter of the building to
allow for working around the building and sloping the sides of the excavation. How
many bey of topsoil need to be removed and stockpiled? - ANS-68 bcy

All exposed concrete surfaces require some type of finishing. For each finish,
estimator(s) need to analyze thoroughly the operations involved, material and
equipment required, and labor hours needed to do the work. - ANS-True

Concrete is estimated by the _______________ or by the _________________ and
then converted into cubic yards dividing the number by __________________. - ANS-
cubic yard (cy) - cubic foot (cf) - 27

When estimating footings for buildings with irregular shapes and jogs, the estimator
must be careful to include the ___________________ only once. - ANS-corners

In estimating quantities, the estimator makes no deductions for holes smaller than
___________________ sf or for the space that reinforcing bars or other miscellaneous
accessories take up. - ANS-2

__________________________ footings typically have projecting formed piers that
support the building structure. - ANS-Spread

When estimating footings, columns, beams, and girders, their volume is determined by
taking the __________________________ of each item times its
_________________________. - ANS-linear footage - cross-sectional area

Concrete slab information will most commonly be found on wall sections, floor plans,
and structural details. - ANS-True

, Using a waste factor of 8 percent, determine the number of cubic yards of concrete
needed to pour two of the spread footings in the following picture. - ANS-0.42 cy

Using the following picture, calculate the following:
A. Number of dowels.
B. Length of each dowel if it turns 9 inches into the footing. Allow for 2'' of cover at each
end. - ANS-A=4 and B= 51 inches

Using the following picture, calculate the following:
A. Number of horizontal footing bars (both ways).
B. Length of each horizontal bar. Allow for 2'' of cover at each end.
C. Total weight of horizontal bars if rebar #4 unit weight is 0.668 pounds per lf. - ANS-
A=8, B= 26 inches, C=11.6 pounds

A building requires a 100-foot-long by 83-foot-wide by 5-inch-thick concrete slab. Using
a waste factor of 10 percent, determine the number of cubic yards of concrete needed
to pour the slab. - ANS-128 cy

A building requires a 100-foot-long by 83-foot-wide by 5-inch-thick concrete slab.
Determine the number of rolls of wire mesh needed for the slab. There are 750 square
feet of wire mesh per roll. Add 12 percent for lap and waste. - ANS-13 rolls

A building requires a 100-foot-long by 83-foot-wide by 5-inch-thick concrete slab.
Determine the number of long and short bars for the slab. The slab is reinforced with #4
rebar at 12 inches on center both ways. - ANS-Number of long bars= 84 bars,
Number of short bars= 101

Reinforcing bars are listed (noted) by the bar number, which corresponds to the bar
diameter in _____________ of an inch. For example, a No.7 bar (deform ___________-
inch nominal diameter. - ANS-Eighth, 7/8

Reinforcing bars are taken off by linear feet. The takeoff (workup) sheet should be set
up to include the number of the bars, pieces, lengths, and bends. Because reinforcing
bars are usually priced by the hundredweight (100 pounds, cwt), the weight of
reinforcing required must be calculated. - ANS-True

The reinforcing used in concrete may be reinforcing bars, WWF, or a combination of the
two. What does WWF stand for? - ANS-Welded Wire Fabric

Which of the following statements is not TRUE for a WWF, which is designated on the
drawings in the following manner: 4 X 8 D 8 X D 11 - ANS-both wires are smooth.

Proper curing is an important factor in obtaining good concrete. The concrete cures with
the chemical combinations between the cement and water. Curing is the final step in the
production of good concrete, which can be done by the following method(s): - ANS-A,
B, C, D, and E

Document information

Uploaded on
August 4, 2026
Number of pages
10
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$24.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
esthernyaguthii
3.5
(2)
Sold
5
Followers
0
Items
1125
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions