Question 1
Correct
1.00 points out of 1.00
Flag question
Question text
A significant difference between “planning” and “scheduling” is:
Question 1Select one:
A.
Scheduling determines what is going to be done, and planning determines
how to do.
B.
Scheduling determines how to do, and planning determines by whom.
C.
Scheduling determines when to do, and planning determines what to do,
how to do and by whom.
D.
Scheduling determines how to do, and planning determines what to do.
Feedback
The correct answer is: Scheduling determines when to do, and planning
determines what to do, how to do and by whom.
Question 2
, Correct
1.00 points out of 1.00
Flag question
Question text
What is a primary means that general contractors use to communicate the
construction plan to other parties?
Question 2Select one:
A.
Scope of the work
B.
Schedule
C.
Estimate
D.
Drawings and specifications
Feedback
The correct answer is: Schedule
Question 3
Correct
1.00 points out of 1.00
Flag question
Question text
In the bar chart, the free float is shown as:
Question 3Select one:
A.
A horizontal dotted line between each activity
Louisiana State University
Module 1 Assignment
Status Finished
Started Friday, July 10, 2026, 11:05 PM
Completed Friday, July 10, 2026, 11:12 PM
Duration 7 mins 35 secs
Grade 14.00 out of 14.00 (100%)
Question 1
Correct
1.00 points out of 1.00
Flag question
Question text
A significant difference between “planning” and “scheduling” is:
Question 1Select one:
A.
Scheduling determines what is going to be done, and planning determines
how to do.
B.
Scheduling determines how to do, and planning determines by whom.
C.
Scheduling determines when to do, and planning determines what to do,
how to do and by whom.
D.
Scheduling determines how to do, and planning determines what to do.
Feedback
The correct answer is: Scheduling determines when to do, and planning
determines what to do, how to do and by whom.
Question 2
, Correct
1.00 points out of 1.00
Flag question
Question text
What is a primary means that general contractors use to communicate the
construction plan to other parties?
Question 2Select one:
A.
Scope of the work
B.
Schedule
C.
Estimate
D.
Drawings and specifications
Feedback
The correct answer is: Schedule
Question 3
Correct
1.00 points out of 1.00
Flag question
Question text
In the bar chart, the free float is shown as:
Question 3Select one:
A.
A horizontal dotted line between each activity