ACQ 202 Module 5 Exam: Producing the System ACTUAL UPDATED QUESTIONS
AND CORRECT ANSWERS
All of the five elements (5Ms) of manufacturing -Measurement
contribute to the cost of production. Which one of the -Mandates
following is NOT one of the 5Ms? -Methods
-Machinery
Choose the ideal cost of quality breakdown from the -Prevention 15%, Appraisal 35%, Failure 50%
following options. -Prevention 25%, Appraisal 50%, Failure 25%
-Prevention 5%, Appraisal 45%, Failure 50%
-Prevention 50%, Appraisal 35%, Failure 15%
Which of the following is considered to be a practice of -Low levels of inventory
"Lean Manufacturing"? -Centralized management control
-Mass production
-Highly specialized workforce
AND CORRECT ANSWERS
All of the five elements (5Ms) of manufacturing -Measurement
contribute to the cost of production. Which one of the -Mandates
following is NOT one of the 5Ms? -Methods
-Machinery
Choose the ideal cost of quality breakdown from the -Prevention 15%, Appraisal 35%, Failure 50%
following options. -Prevention 25%, Appraisal 50%, Failure 25%
-Prevention 5%, Appraisal 45%, Failure 50%
-Prevention 50%, Appraisal 35%, Failure 15%
Which of the following is considered to be a practice of -Low levels of inventory
"Lean Manufacturing"? -Centralized management control
-Mass production
-Highly specialized workforce