PRO4801 ASSIGNMENT 2 2026
DUE AUGUST 2026




Question 3.1


Distinguish between the different steps in the project planning process and
explain the purpose of typical questions to be answered in each step.




Project planning is the foundational function of project management that determines
what must be done, how it will be done, who will do it, when it will be done, and at what
cost. Without thorough planning, even the most skilled project team and appropriate
organisational structure cannot guarantee project success. The planning process is
particularly critical during the conception and definition phases, where a plan is
prepared specifying project goals, tasks, budgets, and schedules (Nicholas & Steyn,
2017, Chapter 6). This section distinguishes the key steps in the project planning
process and explains the purpose of the typical questions answered at each step.


The Project Planning Process

The planning process involves answering a series of fundamental questions in a logical
sequence. According to Nicholas and Steyn (2017, Section 6.1), the planning process
typically follows these steps:

Define the Desired End Result

Question: "What is the desired end result?"

This step establishes the project objectives, scope, and system requirements. It
specifies the project deliverables, end-items, and other sought-after results, as well as

,the time, cost, and performance targets. The purpose is to provide a clear, measurable
target against which all subsequent planning and execution will be evaluated. Without a
clear definition of the end result, the project lacks direction and cannot be effectively
controlled.

Typical Questions:

What are the project objectives and deliverables?

What are the user and system requirements?

What are the time, cost, and performance targets?

Step 2 Define the Work Activities

Question: "How will the result be achieved?"

This step translates the project objectives and deliverables into specific, well-defined
work activities, tasks, or jobs. It includes everything necessary to create and deliver the
end-item, including planning, control, and administration activities. The purpose is to
ensure that every necessary activity is identified and clearly defined, and that no
activities are overlooked. This is typically achieved through the Work Breakdown
Structure (WBS) process (Nicholas & Steyn, 2017, Section 6.4; Study Guide, Lesson 5).

Typical Questions:

What tasks and work packages are required?

What are the dependencies and relationships between tasks?

What resources (labour, materials, equipment) are needed for each task?

Step 3 Assign Responsibility

Question: "Who will do it?"

, This step specifies the project organization the individuals, departments,
subcontractors, and managers that will perform and manage the work and assigns
responsibilities. The purpose is to ensure accountability and clarity of roles, preventing
tasks from falling through the cracks. This is often documented in a Responsibility
Matrix (also known as a RACI chart) (Nicholas & Steyn, 2017, Section 6.5; Study Guide,
Lesson 5).

Typical Questions:

Who is responsible for each work package or task?

What are the roles and responsibilities of each team member?

What are the reporting relationships and communication channels?

Step 4 Create a Schedule

Question: "When and in what order?"

This step creates a schedule showing the timing of work activities, deadlines, and
milestone dates. The purpose is to provide a timeline for execution, enable resource
allocation, and establish a basis for tracking progress. Scheduling techniques such as
Gantt charts, network diagrams, and critical path analysis are used to visualise the
sequence and dependencies of activities (Nicholas & Steyn, 2017, Chapter 7; Study
Guide, Lesson 6).

Typical Questions:

What is the start and finish date for each task?

What are the dependencies and critical path?

What are the key milestones and deadlines?

Step 5 Develop a Budget

Document information

Uploaded on
July 28, 2026
Number of pages
26
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$4.75

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
UNIVIA
4.3
(45)
Sold
502
Followers
3
Items
746
Last sold
11 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions