PRACTICE QUESTIONS
1. A project manager is leading a complex software development
project using an agile approach. A key stakeholder from the legal
department requests a comprehensive 200-page requirements
document before the team can begin the first sprint. What should the
project manager do first?
A) Ask the legal stakeholder to attend the daily stand-up meetings to stay
informed.
B) *Explain the benefits of iterative delivery and work with the
stakeholder to define a minimum viable product (MVP) for the first
sprint. *
C) Instruct the team to write the full document before starting any
development work.
D) Escalate the request to the project sponsor to override the stakeholder.
Rationale: The PMP mindset prioritizes stakeholder collaboration and
delivering value early. The PM should educate the stakeholder on agile
principles and negotiate a MVP (B). Giving in to the request (C) defeats agile.
Escalating (D) is a last resort. Asking them to stand-ups (A) does not resolve
the core request.
2. A project is behind schedule. The project manager has the option to
authorize overtime, hire two additional contractors, or reduce the
project scope. The project sponsor has stated that the budget cannot
increase. What should the project manager do?
,A) Authorize overtime to recover the schedule without increasing total
headcount.
B) *Analyze the critical path and evaluate which scope items deliver the
least business value, then propose a scope reduction to the change
control board. *
C) Hire the two contractors and request a budget increase from the
sponsor.
D) Accept the delay and update the schedule baseline.
Rationale: Since the budget is fixed, the PM should look to reduce scope (B)
after a value analysis. Overtime (A) would increase costs (overtime pay)
which violates the sponsor's constraint. Hiring contractors (C) definitely
increases budget. Accepting the delay (D) is passive and does not solve the
problem.
3. A project manager is in the middle of project execution when a new
regulatory law is passed that directly impacts the project's
deliverables. What should the project manager do first?
A) Update the risk register with this new regulatory risk.
B) *Evaluate the impact of the new law on the project scope, schedule,
and budget. *
C) Immediately stop all project work until the legal team provides guidance.
D) Ask the team to continue working while the PM figures out the legal
implications.
Rationale: The PM must first assess the impact (B) before taking action.
Updating the risk register (A) is important but comes after impact analysis.
Stopping work immediately (C) is premature without knowing the impact.
Continuing work without assessing (D) is irresponsible.
,4. A project manager notices that two team members are in frequent
conflict, which is affecting team morale and productivity. What should
the project manager do first?
A) Escalate the conflict to human resources.
B) *Meet with each team member individually to understand their
perspectives and concerns. *
C) Reassign one of the team members to a different project.
D) Ignore the conflict and hope it resolves on its own.
Rationale: The PM should address conflict early by understanding both
perspectives (B) before taking action. Escalating to HR (A) is premature.
Reassigning (C) avoids the root cause. Ignoring (D) will worsen the situation.
5. A project sponsor requests a major change to the project scope that
will significantly increase the budget and extend the timeline. The
project manager should:
A) Approve the change immediately to satisfy the sponsor.
B) *Submit the change request through the formal change control
process for evaluation and approval. *
C) Reject the change because it will impact the budget and schedule.
D) Implement the change and update the project documents later.
Rationale: Any major change must go through the formal change control
process (B). Approving it immediately (A) bypasses governance. Rejecting it
(C) without evaluation disregards the sponsor's request. Implementing
without documentation (D) is poor project management.
6. A project is experiencing scope creep. Which of the following should
the project manager implement to prevent this?
, A) Reduce the number of stakeholders.
B) *Strengthen the change control process and ensure all requests are
formally evaluated. *
C) Increase the project budget to accommodate extra work.
D) Extend the project schedule to allow for additional scope.
Rationale: A robust change control process (B) is the primary defense against
scope creep. Reducing stakeholders (A) is not realistic. Increasing budget (C)
or extending schedule (D) without control encourages further creep.
7. A project manager is leading a hybrid project (waterfall and agile).
The team is struggling with the daily stand-up meetings, which are
running over 30 minutes. What should the project manager do?
A) Cancel the daily stand-up meetings and switch to weekly status reports.
B) *Coach the team on the purpose of the stand-up (to inspect and
adapt, not to problem-solve) and limit the time to 15 minutes. *
C) Ask the team to send email updates instead of holding meetings.
D) Extend the stand-up to 45 minutes to allow for full discussion.
Rationale: The stand-up is a time-boxed (15 minutes) event focused on
coordination. The PM should coach the team (B). Canceling (A) or switching
to emails (C) defeats the purpose of daily alignment. Extending (D) makes it a
problem-solving session.
8. A project manager is closing a project. The final product has been
delivered, and the customer has accepted it. Which of the following is
the MOST important activity during project closure?
A) Throwing away all project documents to free up storage space.
B) *Conducting a lessons learned session and archiving project