Question 1
pts
(Lesson 5.15: Two-Channel Manufacturing Example.) Consider the demo from class:
Module05-15 - Model 04-01-ElectronicAssembly-slow.doe
If you run the thing for a while, you’ll see that the rework Station gets pretty clogged up every once
in a while – probably because the service times are EXPO(45) minutes. Let’s suppose that
management has noticed this as well and decides to upgrade that station so that the service times
are now EXPO(10). Go ahead and make this change and comment on what you see.
, 11/2/25, 12:2G PM
a. There are still very long lines at Rework almost all of the time.
b. There are occasionally extremely long lines at Rework.
c. There are occasionally short lines, but long lines are very rare.
d. There is never, ever any line at Rework
(c).