Sedimentation - CORRECT ANSWER✔✔-the process by which eroded | | | | | | | |
material is transported and deposited | | | |
"CGP" stand for - CORRECT ANSWER✔✔-Construction General Permit;
| | | | | | | |
one of the NPDES permits administered by DHEC
| | | | | | |
When do you need a land disturbance permit - CORRECT ANSWER✔✔->
| | | | | | | | | |
or = 1 acre
| | | | |
or
> or = 0.5acres with in 0.5 miles of a water body in a coastal county
| | | | | | | | | | | | | | |
What is a SWPPP - CORRECT ANSWER✔✔-Storm Water Pollution
| | | | | | | | |
Prevention Plan | |
-Identifies potential sources of storm water pollution
| | | | | |
-describes storm water control measures | | | | |
-tells how CGP will be followed
| | | | |
, Whats in a SWPPP - CORRECT ANSWER✔✔--Copy of Permit
| | | | | | | | |
-Copy of "Notice of Intent" (NOI)
| | | | |
-Copy of approval letter from SCDHEC
| | | | | |
-Construction plans | |
-Inspection report | |
-Copy o 404 permit and 401 certificate when applicable
| | | | | | | |
In coastal zones the SWPPP must also include what 2 documents -
| | | | | | | | | | | |
CORRECT ANSWER✔✔--Coastal Zone Consistency Letter (CZC)
| | | | |
-Critical Area Permit (when applicable)
| | | |
Who are the three parties in a CGP - CORRECT ANSWER✔✔--Owner:
| | | | | | | | | | |
person or business who took out the CGP
| | | | | | | |
-Operator: individual who has day-to-day operational control
| | | | | | |
-Secondary Operator: Primary contractor | | |
How often are inspections done? - CORRECT ANSWER✔✔-Every 7 days
| | | | | | | | |
once a month for temporarily stabilized area
| | | | | |
Does a rain gauge need to be present of site? - CORRECT ANSWER✔✔-
| | | | | | | | | | | |
Yes
SOLUTIONS
Sedimentation - CORRECT ANSWER✔✔-the process by which eroded | | | | | | | |
material is transported and deposited | | | |
"CGP" stand for - CORRECT ANSWER✔✔-Construction General Permit;
| | | | | | | |
one of the NPDES permits administered by DHEC
| | | | | | |
When do you need a land disturbance permit - CORRECT ANSWER✔✔->
| | | | | | | | | |
or = 1 acre
| | | | |
or
> or = 0.5acres with in 0.5 miles of a water body in a coastal county
| | | | | | | | | | | | | | |
What is a SWPPP - CORRECT ANSWER✔✔-Storm Water Pollution
| | | | | | | | |
Prevention Plan | |
-Identifies potential sources of storm water pollution
| | | | | |
-describes storm water control measures | | | | |
-tells how CGP will be followed
| | | | |
, Whats in a SWPPP - CORRECT ANSWER✔✔--Copy of Permit
| | | | | | | | |
-Copy of "Notice of Intent" (NOI)
| | | | |
-Copy of approval letter from SCDHEC
| | | | | |
-Construction plans | |
-Inspection report | |
-Copy o 404 permit and 401 certificate when applicable
| | | | | | | |
In coastal zones the SWPPP must also include what 2 documents -
| | | | | | | | | | | |
CORRECT ANSWER✔✔--Coastal Zone Consistency Letter (CZC)
| | | | |
-Critical Area Permit (when applicable)
| | | |
Who are the three parties in a CGP - CORRECT ANSWER✔✔--Owner:
| | | | | | | | | | |
person or business who took out the CGP
| | | | | | | |
-Operator: individual who has day-to-day operational control
| | | | | | |
-Secondary Operator: Primary contractor | | |
How often are inspections done? - CORRECT ANSWER✔✔-Every 7 days
| | | | | | | | |
once a month for temporarily stabilized area
| | | | | |
Does a rain gauge need to be present of site? - CORRECT ANSWER✔✔-
| | | | | | | | | | | |
Yes