ACI Concrete Field-Testing Technician Grade I
Certification Exam V2 (Latest Update 2026 / 2027)
Questions & Answers | Grade A | 100% Correct
Question:
ASTM C1064
Answer
Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement Concrete
Question:
The sensor of the temperature measuring device shall be submerged a minimum of ______
inches into the freshly mixed concrete.
Answer
3"
Question:
The temperature measuring device shall have a capacity of measuring temperature of freshly
mixed concrete to ± ______ °F throughout a range of ____________.
Answer
1 degree, 30 degrees to 120 degrees
Question:
The temperature measuring device shall be calibrated ______ , or whenever there is a question of
______ .
Answer
Annually, accuracy
Question:
The temperature of concrete may be measured in a wheelbarrow. True or False?
Answer
True
Question:
The temperature of concrete may be measured in a wall form. True or False?
Answer
True
Question:
What must be done to the sample container prior to sampling the concrete?
Answer
Dampen with water
Question:
What must be done to the concrete surrounding the temperature measuring device after the
device is submerged in the fresh concrete?
Answer
Close off air voids by gently pressing the concrete around the device
Question:
How long must the temperature measuring device remain in the freshly mixed concrete?
Answer
minimum of two minutes, maximum of five minutes
Question:
The temperature of the concrete is reported to the nearest ______ °F
Answer
1 degree
Question:
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True or False?
Answer
False
Question:
ASTM C172
Answer
Standard Practice for Sampling Freshly Mixed Concrete
Question:
Sampling by this method is required when tests are to be made to determine _____ with
specification requirements.
Answer
Compliance
Question:
This method covers sampling from four types of mixers, which are _____ , _____ , _____ , and
_____ .
Answer
Stationary mixers, paving mixers, revolving drum mixers and open top mixers
Question:
The maximum allowable time between obtaining the first and final portions of a composite
sample is _____ minutes.
Answer
15
Question:
Portions of a composite sample shall be thoroughly remixed before beginning tests on the
sample. True or False?
Answer
True
Question:
The maximum elapsed time allowed between obtaining the final portion of the composite sample
and beginning the tests for slump, temperature, and air content is _____ minutes.
Answer
5
Question:
The molding of strength test specimens shall begin within _____ minutes after fabricating the
composite
sample.
Answer
15
Question:
The concrete sample must be protected from contamination and _____.
Answer
Rapid evaporation
Question:
The minimum size sample for making strength test specimens is _____.
Answer
1 cubic foot
Question:
When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly
spaced intervals during discharge of the middle portion of the batch.
Answer
2
Question:
The composite sample for a paving mixer must represent a minimum of _____ different portions
of the batch of concrete taken from the pile after discharge.
Answer
5
Question:
When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of
_____ regularly spaced intervals during discharge of the middle portion of the batch.
Answer
2
Question:
Concrete samples from a truck mixer must be obtained before any water or admixtures are added
to the mixer at the job site. True or False?
Answer
False
Question:
The composite sample from a truck mixer must be obtained from the _____ portion of the batch.
Answer
middle
Question:
When the concrete contains aggregate larger than that permitted for a particular test method, the
sample of concrete must be _____ _____ before making the test.
Answer
wet sieved
Question:
What must occur before a sample of concrete can be taken from a revolving drum mixer? (Oral
Exam)
Answer
All of the water must be added to the mixer
Question:
Describe the different procedures that can be used to collect a sample of concrete from a
stationary or revolving drum mixer. (Oral Exam)
Answer
Repeatedly pass a receptacle through the entire discharge stream, Completely divert the
discharge stream into a sample container
Question:
What are the required steps for collecting a sample of concrete from a stationary or revolving
drum mixer? (Oral Exam)
Answer
Collect two or more portions of concrete, Take the portions at regularly spaced intervals, Take
the portions from the middle of the batch
Question:
Describe the procedure for collecting a sample of pavement concrete deposited on grade. (Oral
Exam)
Answer
Discharge the contents of the paving mixer, Obtain samples from at least five different portions
of the pile
Question:
What is the minimum size for a sample when strength test specimens are to be molded? (Oral
Exam)
Answer
1 cubic foot (28 L)
Question:
What is the maximum allowable time between obtaining the first and final portions of the
composite sample? (Oral Exam)
Answer
15 min.
Question:
What is required after the concrete sample has been transported to the place where tests are to be
performed? (Oral Exam)
Answer
Combine and remix the sample with a shovel
What should be done if the concrete contains aggregate larger than is appropriate for the size of
the molds or equipment being used? (Oral Exam)
Answer
Wet sieving
Start the tests for slump, temperature, and air content within how many minutes after obtaining
the final portion of the composite sample? (Oral Exam)
Answer
5 min.
Start molding specimens for strength tests within how many minutes after fabricating the
composite sample? (Oral Exam)
Answer
15 min.
From what must the concrete sample be protected? (Oral Exam)
Sun, wind, rapid evaporation, and contamination
ASTM C143
Standard Test Method for Slump of Hydraulic-Cement Concrete
The slump test is applicable to plastic concrete with a maximum size aggregate of _____ .
1½ in.
When the concrete contains aggregate larger than allowed for the slump test, the large aggregate
must be _____.
Removed by wet sieving the sample over 1½ in. sieve
The mold for making the slump test is in the shape of _____.
The frustum of a cone
The height of the slump mold is _____.
12 in.
The interior surface of the slump mold is allowed to have minor irregularities. True or False?
False
For use in the slump test, the end or both ends of the tamping rod must be _____.
Rounded to a hemispherical tip
The sample of concrete for use in making the slump test must be obtained in accordance with
ASTM Standard _____.
C172, Standard Practice for Sampling Freshly Mixed Concrete
The slump mold should be in a dry condition before beginning the test. True or False?
False
The surface on which the slump mold will be placed must be _____.
Flat, level, moist, nonabsorbent, and free of vibration
The slump mold is filled in _____ layers.
3
Each layer should fill approximately _____ the volume of the mold.
One-third
The approximate concrete depth (in vertical distance) after placing the first layer is _____, and
the second layer is _____.
2⅝ in. [70 mm], 6⅛ in. [160 mm]
What is the specified number of roddings for each layer?
25
How deep should the tamping rod penetrate into each layer?
Rod each layer throughout its depth; on the second and final layers, the rod should penetrate into
the previous layer approximately 1 in. [25 mm]
When rodding the bottom layer, the tamping rod must be _____ to uniformly distribute the
strokes.
Slightly inclined
What must be done if the concrete drops below the top of the slump mold while the top layer is
being rodded?
Add additional concrete to keep an excess of concrete above the top of the mold at all times
Prior to lifting the mold, concrete must be removed from _______.
The area surrounding the base of the mold
After the final rodding, the sides of the slump mold should be tapped lightly with the tamping
rod. True or False?
False
When raising the slump mold, it should not be rotated or twisted. True or False?
True
How much time is allowed for lifting the slump mold?
5 ± 2 seconds
The measurement for slump is made from the top of the mold to what point of the concrete
specimen?
The displaced original center of the top surface of the specimen
The slump of the concrete is measured and reported to the nearest _____.
¼ in. [5 mm]
How much time is allowed to conduct the slump test from beginning to completion?
2½ minutes
ASTM C138
Standard Test Method for Density (Unit Weight),
Yield, and Air Content (Gravimetric) of Concrete
The diameter of the tamping rod used in this test method is _____ .
⅝ in. [16 mm]
What is the required shape of the tamping end of the rod?
Rounded to a hemispherical tip
What is the required minimum frequency of the vibrator used in this test method?
7000 vibrations per minute
The outside diameter or side dimension of the vibrating element must be at least _____ but not
greater than _____ .
0.75 in. [19 mm], 1.50 in. [38 mm]
A plastic container can be used for the measure in this method. True or False?
False, measure must be steel or other suitable metal
What is the minimum thickness of a metal strike-off plate?
¼ in. [6 mm]
What is the minimum thickness for a glass or acrylic strike-off plate?
½ in. [12 mm]
What is the specified weight of the mallet used on measures that are 0.5 ft3 [14 L] or smaller?
1.25 ± 0.50 lb. [600 ± 200 g]
Measures other than air meter bowls used for this test must conform to ASTM _____.
C29
Air meter bowls used for this test must conform to ASTM _____ and be calibrated for volume
according
to ASTM _____.
C231, C29
The concrete sample must be obtained in accordance with what ASTM method?
C172
What method of consolidation must be used when the slump is greater than 3 in. [75 mm]?
Rodding
What method of consolidation must be used when the slump is less than 1 in. [25 mm]?
Vibration
If rodding is the method of consolidation being used, the measure must be filled in how many
layers?
3
For a measure of 0.5 ft3 [14 L], what is the required number of strokes of the tamping rod for
consolidation
of each layer?
25
When rodding the middle and the top layers, the tamping rod should penetrate into the layer
below approximately _____.
1 in. [25 mm]
If vibration is the method of consolidation, the measure must be filled in _____ approximately
equal layers.
2
If, after consolidation of the final layer, the concrete level is 1/2 in. (13 mm) above the top of the
measure, what should be done?
Remove a representative portion of the excess concrete with a trowel or scoop
After consolidation of the final layer, an excess of concrete _____ above the top of the measure
is considered optimum.
⅛ in. [3 mm]
After completing the strike-off procedure, what must be done before weighing the measure and
sample?
Clean off any excess concrete
Density (Unit Weight) Calculation
Known: Volume of measure = 0.504 ft3 [14.27 L or 0.01427 m3]
Mass of empty measure = 19.6 lb [8.89 kg]
The procedures of Method C138 are followed, and the mass of the measure plus the concrete is
found to be 92.1 lb [41.78 kg]. Calculate the density of the concrete in lb/ft3 [kg/m3].
143.9 lb/ft3 [2305 kg/m3]
Yield Calculations
For a design batch of 7.0 yd3 [5.4 m3], the total mass of all materials batched was 27,300 lb
[12,383 kg]. Using the density of the concrete as determined in Question 21, calculate:
a) The yield per batch in ft3
b) The yield per batch in yd3
c) The yield in m3
d) The yield per cubic yard in ft3/yd3
a. Yield per batch = 189.7 ft3
b. Yield per batch = 7.0 yd3
c. Yield per batch = 5.4 m3
d. Yield per cubic yard = 27.1 ft3/yd3
Relative Yield Calculation
Using the information given and calculated in Question 22, calculate the relative yield for the
batch of concrete.
1.00
Air Content Calculation
Your air meter has been damaged in transit to the job site. You do, however, possess the
theoretical density that was determined in the lab; it is 151.4 lb/ft3 (2425 kg/m3). Using the
density calculated in Question 21, calculate the air content of the batch (in percentage).
5.0% = [(151.4 lb/ft3 - 143.9 lb/ft3) / 151.4 lb/ft3] × 100
5.0% = [(2425 kg/m3 - 2305 kg/m3) / 2425 kg/m3] × 100
ASTM C231
StandardTestMethodforAirContentofFreshlyMixedConcretebythePressureMethod
The pressure method of determining air content can be used on concrete containing _____ _____
aggregate.
Relatively Dense
The pressure method of determining air content cannot be used on concrete containing the
following types of aggregate: _____, _____, _____.
Lightweight, air-cooled blast furnace slag, or aggregates of high porosity
What is the minimum allowable capacity of the measuring bowl used in this test method?
6 L (0.20 ft3)
What are the required characteristics of the tamping rod used in this test method?
Round, straight steel rod, with a 16 mm [5/8 in.] ± 2 mm [1/16 in.] diameter, length at least 100
mm [4 in.] greater than the depth of the measuring bowl, but not greater than 600 mm [24 in.] in
overall length, with the tamping end rounded to a hemispherical tip of the same diameter as the
rod.
What is the specified size of the mallet required for this test method when the measuring bowl
has a capacity of 14 L [0.5 ft3] or less?
0.60 ± 0.25 kg [1.25 ± 0.50 lb.]
The sample of concrete used for this test is to be obtained in accordance with what ASTM
Standard?
C172
The maximum size aggregate allowed for this test method is _____.
50 mm (2 in.)
If the concrete contains aggregate larger than the maximum allowed for this test, the sample must
be _____.
Wet sieved over a 1½ in. (37.5 mm) sieve
If the concrete sample is to be consolidated by rodding, the measure is filled in _____ layers.
3 equal
If the concrete sample is to be consolidated by vibration, the measure is filled in ______ layers.
2 equal
When rodding the concrete sample, what is the specified number of strokes required for each
layer?
25
Vibration of the concrete sample is not allowed when the slump of the concrete exceeds _____.
75 mm (3 in.)
In rodding the sample, how deep should the rod penetrate each layer?
Rod bottom layer to full depth; rod second and final layer penetrating the previous layer about 25
mm (1 in.)
After rodding each layer, what should be done to the measure before adding another layer of
concrete?
Tap the sides of the measure smartly 10 to 15 times with the mallet
When consolidating the concrete by vibration, how many times should the vibrator be inserted
into each layer?
Three (3)
What tools may be used to strike off the top surface of the concrete following consolidation of
the final layer?
A strike-off bar; a metal, glass, or acrylic plate
What must be done if there is a slight deficiency in the quantity of concrete in the measure
following consolidation of the final layer?
Add a quantity of representative concrete before strike off
What must be done if there is an excessive amount of concrete in the measure following
consolidation of the final layer?
Remove a representative quantity of concrete with the scoop or trowel before the strike off
ASTM C173
Standard Test Method For Air Content of Freshly Mixed Concrete by the Volumetric Method
The volumetric method of determining air content of concrete can be used on concrete
containing what types of aggregate?
All types of aggregate
What are the requirements for the tamping rod used in this test method?
Round, straight 5/8 [16 mm] ± 1/16 in.[2 mm] diameter rod at least 4 in. [300 mm] greater in
length than the depth of the bowl being used, with the tamping end rounded to a hemispherical
tip of the same diameter, made of steel, high-density polyethylene, or other plastic of equal or
greater abrasion resistance.
What are the requirements for the strike-off bar used in this test method?
Flat, straight steel bar at least 1/8 by 3/4 by 12 in. [3 by 20 by 300 mm] or a flat, straight high
density polyethylene bar, or other plastic of equal or greater abrasion resistance, at least 1/4 by
3/4 by 12 in. [6 by 20 by 300 mm].
What is the approximate volume of the measuring cup used to add water to the air meter, in
relation to the volume of the air meter bowl?
1.00% ± 0.04%
What type of alcohol and concentration must be used in this test method?
Isopropyl, 70% by volume (65% by weight)
A mallet weighing _____ must be used to tap the sides of the bowl after rodding each layer.
1.25 ± 0.50 lb. (600 ± 200 g)
The sample of concrete used in this test method must be obtained in accordance with what
ASTM Standard?
C172
The maximum size aggregate allowed in this test method is _____.
1½ in. (37.5 mm)
If the concrete sample contains aggregate larger than that allowed for this test, the sample must
be _____.
Wet sieved over a 1-in. (25-mm) sieve
When filling the measuring bowl of the air meter, the concrete must be placed in _____ layers of
equal depth.
2
What is the specified number of strokes required when rodding each layer of concrete?
25
It is necessary to tap the sides of the measuring bowl after each layer has been rodded. True or
False?
True
The initial quantity of water and alcohol added to the air meter can be poured directly into the
neck of the top section of the air meter. True or False?
False; the funnel must be used
Upon final filling of the air meter with water, what part of the liquid level should be adjusted to
the zero mark on the meter?
Bottom of the meniscus
How long should the air meter be inverted and agitated?
No more than five seconds at a time, but must be repeated for a minimum of 45 seconds to free
concrete from the base
How many times does the rolling operation occur?
A minimum of 2, a maximum of 3
Why is the isopropyl alcohol added to the meter?
To dispel any foam that may be on the surface of the water
The direct reading of the final liquid level in the neck of the air meter, is estimated to the nearest
_____.
0.25%
If the air content is greater than the 9% range of the meter, __________.
Calibrated cups of water are added to bring the liquid level within the graduated range
In order for an initial meter reading to be valid, the meter must not be leaking, the liquid level
must stabilize within 6 minutes, and the foam on the surface of the liquid must not be greater
than 2 full percent divisions. True or False?
True
If less than 1.25 L [2.5 pt] of alcohol are used, the air content is always indicated by the final
meter reading. True or False?
False, if the air content is more than 9%, the number of calibrated cups of water introduced into
the meter to bring the liquid level within the graduated range must be added
If more than 1.25 L [2.5 pt] of alcohol are used, the final meter reading is always adjusted using
_______.
A correction factor
When large amounts of alcohol are used, the direct reading will tend to indicate a __________
air content.
Higher
At the end of the procedure, the air meter is _______.
Disassembled and its contents examined
If portions of undisturbed concrete are found in the air meter at the end of the test, _________.
The test is invalid
ASTM C31
Standard Practice for Making and Curing
Concrete Test Specimens in the Field
ASTM Method C31 gives standardized requirements for _____, _____, _____, and _____, of
test specimens.
Making, curing, protecting, transporting
For cylinders with a diameter of 6 in. [150 mm] or greater, the tamping rod must be a round,
straight steel rod with a diameter of _____.
5/8 ± 1/16 in. [16 mm ± 2 mm]
The minimum frequency of an internal vibrator used in this procedure is _____ .
9000 vibrations per minute [150 Hz]
The container for obtaining the concrete sample used in this procedure can be a _____, _____, or
_____ .
Metal pan, wheelbarrow, flat, clean nonabsorbent mixing board
A 6 by 12 in. [150 mm by 300 mm] cylinder mold can be used for concrete containing aggregate
with particles not exceeding _____ in size, without the need for wet sieving the concrete.
2 in. [50 mm]
The sample of concrete used in molding test specimens must be obtained in accordance with
what ASTM Standard?
C172
When strength specimens are to be made, what three other tests must be made?
Slump, air content, temperature
After molding test specimens, you should wait two hours before moving them to the location of
initial storage. True or False?
False; the specimens must be moved immediately
The supporting surface on which specimens are stored shall be level within ______.
1/4 in. per ft. [20 mm per m]
For concrete with a slump of less than 1 in. [25 mm], the test specimens must be consolidated by
_____.
Vibration
If the concrete is to be consolidated by vibration, a standard 4 by 8 in. [100 mm by 200 mm]
cylinder mold must be filled in _____ equal layers.
2
When rodding a standard 6 by 12 in. [150 mm by 300 mm] cylinder, each layer must be rodded
_____ times.
25
When rodding each upper layer of concrete in a cylinder, the tamping rod should penetrate into
the underlying layer by about _____.
1 in. [25 mm]
When using an internal vibrator to consolidate a 6 by 12 in. [150 mm by 300 mm] compressive
strength test specimen, the vibrator must be inserted at _____ different points for each layer.
2
When consolidating a flexural strength test specimen by rodding, rod one stroke for each _____
of top surface area.
2 square inches
When internal vibration is used to consolidate a standard flexural strength test specimen, the
technician should insert the vibrator at intervals not exceeding _____ along the center line of the
beam.
6 in. [150 mm]
Concrete mixtures with specified strengths of 6000 psi [40 MPa] or greater shall have an initial
curing temperature between ___________.
68 and 78 ºF [20 and 26 ºC]
Up to 48 hours after molding, test specimens that are to be standard cured shall be stored in a
temperature range between _____ to _____.
60 and 80 ºF [16 and 27 ºC]
Upon completion of initial curing, the test specimens may be left in their molds and sealed in
plastic bags. True or False?
False; specimens are to be demolded and placed in water storage tanks or moist rooms with free
water at a temperature of 73.5 ± 3.5 °F [23.0 ± 2.0 °C]
During transportation, test specimens must be protected from damage due to _____, _____, and
_____ .
Jarring, freezing temperatures, moisture loss
Specimens shall not be transported until _______ after final set.
8h
Transportation time shall not exceed _____________ .
4h
Standard Curing is the curing method used when test specimens are to be used for
______________.
Acceptance testing for specified strength, checking the adequacy of mixture proportions for
strength, quality control
Field Curing is the curing method used when test specimens are to be used for
______________.
Determination of whether the structure is capable of being put into service; Comparison with
standard cured specimens test results or with results from various in-place test methods;
Adequacy of curing and protection of concrete in the Structure, or Form or shoring removal time
requirements
Cylinders that are to be field cured are stored ___________________________ and protected
_______.
In or on the structure as near to the point of deposit of the concrete represented as possible; In as
near as possible the same way as the formed work
The temperature and moisture environment for field cured cylinders must be
_____________________________________________________________________________.
The same as the structural work
Cylinders made for the purpose of determining when a structure may be put into service shall be
removed from the molds _________________________________________________________.
At the time of the removal of formwork
Content preview
ACI Concrete Field-Testing Technician Grade I
Certification Exam V2 (Latest Update )
Questions & Answers | Grade A | 100% Correct
Question:
ASTM C1064
Answer
Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement Concrete
Question:
The sensor of the temperature measuring device shall be submerged a minimum of ______
inches into the freshly mixed concrete.
Answer
3"
Question:
The temperature measuring device shall have a capacity of measuring temperature of freshly
mixed concrete to ± ______ °F throughout a range of ____________.
Answer
1 degree, 30 degrees to 120 degrees
Question:
The temperature measuring device shall be calibrated ______ , or whenever there is a question of
______ .
Answer
,Annually, accuracy
Question:
The temperature of concrete may be measured in a wheelbarrow. True or False?
Answer
True
Question:
The temperature of concrete may be measured in a wall form. True or False?
Answer
True
Question:
What must be done to the sample container prior to sampling the concrete?
Answer
Dampen with water
Question:
What must be done to the concrete surrounding the temperature measuring device after the
device is submerged in the fresh concrete?
Answer
Close off air voids by gently pressing the concrete around the device
, Question:
How long must the temperature measuring device remain in the freshly mixed concrete?
Answer
minimum of two minutes, maximum of five minutes
Question:
The temperature of the concrete is reported to the nearest ______ °F
Answer
1 degree
Question:
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True or False?
Answer
False
Question:
ASTM C172
Answer
Standard Practice for Sampling Freshly Mixed Concrete
Question: