1. A project manager is reviewing the Business Case after a stage boundary.
What should they confirm before proceeding?
A. That all risks have been eliminated
B. That the project remains viable, desirable, and achievable
C. That all products are completed
D. That team members are reassigned
✔ Correct Answer: B (That the project remains viable, desirable, and
achievable)
Explanation: The Business Case must be continually justified; confirming
viability, desirability, and achievability ensures ongoing business
justification.
2. During a project, a team member raises a new risk. What is the first action?
A. Escalate to the Project Board
B. Ignore if low impact
C. Record it in the Risk Register
D. Implement a response immediately
✔ Correct Answer: C (Record it in the Risk Register)
, Explanation: All risks must first be captured formally before analysis or
escalation decisions are made.
3. A Project Board requests frequent updates beyond agreed tolerances. What
should the Project Manager do?
A. Ignore the request
B. Update the Communication Management Approach
C. Escalate to corporate management
D. Stop reporting
✔ Correct Answer: B (Update the Communication Management Approach)
Explanation: Adjusting communication ensures stakeholder needs are met
without breaching governance principles.
4. Which PRINCE2 principle ensures roles and responsibilities are clear?
A. Learn from experience
B. Defined roles and responsibilities
C. Manage by stages
D. Focus on products
✔ Correct Answer: B (Defined roles and responsibilities)
Explanation: This principle ensures accountability and clarity across the
project structure.
5. A stage is exceeding tolerance. What should the Project Manager do?
A. Continue working
B. Stop the project
C. Escalate via an Exception Report
D. Ignore variance
✔ Correct Answer: C (Escalate via an Exception Report)
Explanation: Exceeding tolerance requires escalation to the Project Board
for decision-making.
6. What is the primary purpose of the Risk Management Approach?
A. Define how risks are communicated and controlled
B. Eliminate all risks
, C. Assign risks to team members
D. Document lessons learned
✔ Correct Answer: A (Define how risks are communicated and controlled)
Explanation: It outlines procedures, roles, and techniques for managing
risk effectively.
7. A project is delivering outputs but no measurable benefits. Which theme is
weak?
A. Risk
B. Quality
C. Benefits
D. Plans
✔ Correct Answer: C (Benefits)
Explanation: The Benefits theme ensures outputs translate into
measurable value.
8. A Team Manager requests additional resources beyond plan. What should
the Project Manager check?
A. Product Descriptions
B. Stage Plan tolerances
C. Risk Register
D. Lessons Log
✔ Correct Answer: B (Stage Plan tolerances)
Explanation: Resource changes must align with agreed tolerances within
the Stage Plan.
9. What defines a product’s quality expectations?
A. Risk Register
B. Product Description
C. Issue Register
D. Highlight Report
✔ Correct Answer: B (Product Description)
Explanation: Product Descriptions specify quality criteria and acceptance
methods.
, 10.A stakeholder is dissatisfied with a deliverable. What should be reviewed?
A. Risk Management Approach
B. Quality criteria in Product Description
C. Project Plan
D. Lessons Report
✔ Correct Answer: B (Quality criteria in Product Description)
Explanation: Acceptance criteria define whether the product meets
expectations.
11.A project lacks formal checkpoints. Which process is weak?
A. Managing Product Delivery
B. Directing a Project
C. Initiating a Project
D. Closing a Project
✔ Correct Answer: A (Managing Product Delivery)
Explanation: This process ensures control over product creation and
checkpoints.
12.What is the purpose of a Highlight Report?
A. Provide daily updates
B. Update team members
C. Inform the Project Board of progress
D. Record risks
✔ Correct Answer: C (Inform the Project Board of progress)
Explanation: Highlight Reports provide regular progress updates to senior
stakeholders.
13.A supplier delays delivery. What type of issue is this?
A. Request for Change
B. Off-specification
C. Problem/Concern
D. Risk
✔ Correct Answer: C (Problem/Concern)