BSIS TEST 3 Exam #1 Questions with correct answers
The project manager must have a clear picture of how the actual progress or work
compares to the baseline plan in order to make well-informed decisions, take
appropriate actions, or to make adjustments to the project plan. - ✔✔True


If a stakeholder has been judged to adversarial and having a vested interest in the
failure of your project, it would probably be wise to keep him out of the
communication loop. - ✔✔False


All of the project stakeholders should receive exactly the same information
regarding the project's progress in order to eliminate any miscommunication. -
✔✔False


The project communications plan may be informal depending on the needs of the
project stakeholders and the size of the project. - ✔✔True


A project metric should be obtained from observable, quantifiable data that
allows the team and other stakeholders to gauge the efficiency and effectiveness
of the work being done. - ✔✔True


One attribute of a good project metric is that it should be subjective so that a
stakeholder can understand the project manager's personal opinion or insight as
to how the project is progressing. - ✔✔False


A good project metric should be understandable, quantifiable, cost effective,
proven, and be effective. - ✔✔True

,Generally, the more metrics one adopts, the greater the project control. -
✔✔False


Planned value (PV) is the planned or budgeted cost of work scheduled for an
activity or component of the WBS. - ✔✔True


Earned value provides a performance measurement that tells us how much of the
budget we really should have spent for the work completed so far. - ✔✔True


Budget At Completion (BAC) is the total planned cost of a project. - ✔✔True


As a project manager, you would be pleased see a Cost Performance Index CPI
less than one (1) for your project. - ✔✔False


The Schedule Performance Index (SPI) for our project is greater than one (1) and
so we would anticipate that all other things being equal, our project will finish
ahead of schedule. - ✔✔True


The schedule variance (SV) shows the difference between the current progress of
the project and its original or planned value. - ✔✔True


A cost variance (CV) can be positive or negative, but never zero. - ✔✔False


The Expected Time Complete (ETC) provides an estimate for completing the
scheduled work that remains. - ✔✔True

, The Estimate At Completion (EAC) is a project metric that can be used to estimate
the most likely total or final cost of the project based on the project's
performance and any risks that should be considered. - ✔✔True


The purpose of a project review is to not only show evidence that the project
work is being completed, but also that the work is being completed according to
various standards or agreed upon requirements. - ✔✔True


Given the advances that have been made in telecommunications and IT
technology in general, there is little value or necessity today for Face-to-Face
(F2F) meetings. - ✔✔False


Which of the following is not likely a characteristic of a good project metric?: -
✔✔d) Subjective


Earned Value tells us __________ - ✔✔d) how much of the budget we really
should have spent on the work completed so far


Budget At Completion (BAC) is __________ - ✔✔b) how much we budgeted to
spend at the beginning of the project


Actual Cost (AC) is __________ - ✔✔a) how much we actually spent for work
completed


Cost Variance (CV) is __________ - ✔✔e) the difference between the estimated
cost and how much we have actually spent

Document information

Uploaded on
July 19, 2026
Number of pages
18
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
1036
Last sold
-



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions